RegisteredCompletion date passedMahaRERA status: Certificate Signed

P50500022121

Mahalaxmi Nagar 6 52 · Jamtha, Nagpur · Mahalaxmi Estate

Promised for 9 Jul 2024 — that date has passed and MahaRERA does not mark the project complete.

2 years and 3 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 9 Jul 2024, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 35

Registration certificate8 Sep 2021View
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
Show all 35 documents
OtherView
OtherView
Form 1View
OtherView
OtherView
Commencement certificateView
OtherView
OtherView
OtherView
Form 1View
OtherView
Title reportView
Encumbrance detailsView
Layout planView
Commencement certificateView
Commencement certificateView
Form BView
Form 1View
Form 1View
Form 2View
OtherView
OtherView
Form 1View
Form 1View
Layout planView
Layout planView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P50500022121

Is Mahalaxmi Nagar 6 52 delayed?

Yes. MahaRERA records a promised completion of 9 Jul 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P50500022121.

Who is the promoter?

MahaRERA records Mahalaxmi Estate as the promoter of P50500022121.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50500022121.

Answers are generated from the record.

Data through31 Oct 2026, 02:15SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology