Mahindra Bloomdale 4C · Khapari, Nagpur · Mahindra Bebanco Developers Limited
Promised for 30 Sep 2022, extended once to 29 Sep 2023 — and that date has passed without the project marked complete on MahaRERA.
4 years and 2 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Sep 2022 to 29 Sep 2023 (1 extension certificate on record).
- !Risk: The latest completion date on record, 29 Sep 2023, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 134
Show all 134 documents
Orders 0
No MahaRERA order or list names this number.
Questions about P50500020205
Is Mahindra Bloomdale 4C delayed?
Yes. MahaRERA records a promised completion of 30 Sep 2022, revised to 29 Sep 2023, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P50500020205. The completion date moved from 30 Sep 2022 to 29 Sep 2023.
Who is the promoter?
MahaRERA records Mahindra Bebanco Developers Limited as the promoter of P50500020205.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P50500020205.