RegisteredCompletion date passedMahaRERA status: Certificate Signed

P50500018727

Uttara Galaxy · Hingna, Nagpur · Sundershilp Builders & Developers

Promised for 30 Jun 2019 — that date has passed and MahaRERA does not mark the project complete.

7 years and 5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Jun 2019, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 12

Registration certificate29 Nov 2018View
OtherView
Commencement certificateView
OtherView
OtherView
OtherView
Form 1View
OtherView
Show all 12 documents
Title reportView
Encumbrance detailsView
Layout planView
Form BView

Orders 0

No MahaRERA order or list names this number.

Questions about P50500018727

Is Uttara Galaxy delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2019, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P50500018727.

Who is the promoter?

MahaRERA records Sundershilp Builders & Developers as the promoter of P50500018727.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50500018727.

Answers are generated from the record.

Data through4 Nov 2026, 02:51SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology