P50500013132
Imperial Heights · Nagpur (M Corp.), Nagpur · Swaraj And Mohta Infracon
Promised for 18 Jun 2018, extended once to 29 Feb 2024 — and that date has passed without the project marked complete on MahaRERA.
8 years and 5 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 18 Jun 2018 to 29 Feb 2024 (1 extension certificate on record).
- !Risk: The latest completion date on record, 29 Feb 2024, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 27
Orders 0
No MahaRERA order or list names this number.
Questions about P50500013132
Is Imperial Heights delayed?
Yes. MahaRERA records a promised completion of 18 Jun 2018, revised to 29 Feb 2024, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P50500013132. The completion date moved from 18 Jun 2018 to 29 Feb 2024.
Who is the promoter?
MahaRERA records Swaraj And Mohta Infracon as the promoter of P50500013132.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P50500013132.
Answers are generated from the record.