RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
Completed
P50500010162
Venu Enclave · Nagpur (M Corp.), Nagpur · Om Sai Builder & Developers
Promised for 31 Dec 2018; MahaRERA reports the project completed.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- ✓Clear: MahaRERA reports the project as completed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 6
Orders 0
No MahaRERA order or list names this number.
Questions about P50500010162
Is Venu Enclave delayed?
MahaRERA reports it completed. Its promised completion date was 31 Dec 2018.
How many extensions has it had?
Deedo holds 0 extension certificates for P50500010162.
Who is the promoter?
MahaRERA records Om Sai Builder & Developers as the promoter of P50500010162.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P50500010162.
Answers are generated from the record.
Data through23 Nov 2026, 01:36SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology
