RegisteredCompletion date passedMahaRERA status: Certificate Signed

P50500009629

Greenfield 1 Wing D · Wanadongri, Nagpur · L G Developers And Builders

Promised for 31 Dec 2019 — that date has passed and MahaRERA does not mark the project complete.

6 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Dec 2019, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 20

Registration certificate22 Aug 2017View
OtherView
OtherView
Form 2View
Form 1View
Layout planView
Layout planView
Layout planView
Show all 20 documents
Building planView
Building planView
Form 1View
Title reportView
Form BView
OtherView
Commencement certificateView
OtherView
OtherView
OtherView
Form 1View
Form 1View

Orders 0

No MahaRERA order or list names this number.

Questions about P50500009629

Is Greenfield 1 Wing D delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2019, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P50500009629.

Who is the promoter?

MahaRERA records L G Developers And Builders as the promoter of P50500009629.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50500009629.