RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P50500006571
Meghdoot Enclave · Hudkeshwar Bu, Nagpur · Raghav Associates
Promised for 31 Dec 2018; MahaRERA reports the project completed.
The revised date is 1 year and 10 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Dec 2018 to 30 Oct 2020 (1 extension certificate on record).
- ✓Clear: MahaRERA reports the project as completed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 28
Orders 0
No MahaRERA order or list names this number.
Questions about P50500006571
Is Meghdoot Enclave delayed?
MahaRERA reports it completed. Its promised completion date was 31 Dec 2018.
How many extensions has it had?
Deedo holds 1 extension certificate for P50500006571. The completion date moved from 31 Dec 2018 to 30 Oct 2020.
Who is the promoter?
MahaRERA records Raghav Associates as the promoter of P50500006571.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P50500006571.
Answers are generated from the record.