RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Completed

P50400056030

Shri Ram Vatika · Umari (Meghe), Wardha · Krushna Builders & Developers

Promised for 31 Mar 2026; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 18

Encumbrance details7 Mar 2024View
Other7 Mar 2024View
Encumbrance details8 Mar 2024View
Other8 Mar 2024View
Title report13 Mar 2024View
Other13 Mar 2024View
Other5 Apr 2024View
Registration certificate4 Dec 2024View
Show all 18 documents
OtherView
OtherView
Layout planView
Commencement certificateView
Commencement certificateView
OtherView
OtherView
OtherView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P50400056030

Is Shri Ram Vatika delayed?

MahaRERA reports it completed. Its promised completion date was 31 Mar 2026.

How many extensions has it had?

Deedo holds 0 extension certificates for P50400056030.

Who is the promoter?

MahaRERA records Krushna Builders & Developers as the promoter of P50400056030.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50400056030.

Answers are generated from the record.

Data through23 Nov 2026, 01:51SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology