Completed1 extension

P50400046793

Sakhuaai Developers · Palasgaon, Wardha · Ajay P. Deshmukh, Rupali J. Khodake

Promised for 31 Dec 2023; MahaRERA reports the project completed.

The revised date is 1 year after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2023 to 30 Dec 2024 (1 extension certificate on record).
  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 10

Encumbrance details30 Aug 2022View
Commencement certificate30 Aug 2022View
Form B30 Aug 2022View
Registration certificate10 Sep 2022View
Form B11 Mar 2024View
Extension certificate2 Apr 2024View
OtherView
Layout planView
Show all 10 documents
Commencement certificateView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P50400046793

Is Sakhuaai Developers delayed?

MahaRERA reports it completed. Its promised completion date was 31 Dec 2023.

How many extensions has it had?

Deedo holds 1 extension certificate for P50400046793. The completion date moved from 31 Dec 2023 to 30 Dec 2024.

Who is the promoter?

MahaRERA records Ajay P. Deshmukh, Rupali J. Khodake as the promoter of P50400046793.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50400046793.

Answers are generated from the record.