Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Completed

P50400031384

Shree Sadguru Krushnagiri Nagari · Umari (Meghe), Wardha · Shree Samarth Infra

Promised for 31 Mar 2023; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 16

Encumbrance details12 Oct 2021View
Title report13 Oct 2021View
Commencement certificate13 Oct 2021View
Form B13 Oct 2021View
Form 113 Oct 2021View
Form 213 Oct 2021View
Registration certificate23 Oct 2021View
Form 120 May 2023View
Show all 16 documents
Form 120 May 2023View
Form 220 May 2023View
Form 220 May 2023View
OtherView
OtherView
Layout planView
Commencement certificateView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P50400031384

Is Shree Sadguru Krushnagiri Nagari delayed?

MahaRERA reports it completed. Its promised completion date was 31 Mar 2023.

How many extensions has it had?

Deedo holds 0 extension certificates for P50400031384.

Who is the promoter?

MahaRERA records Shree Samarth Infra as the promoter of P50400031384.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50400031384.

Answers are generated from the record.

Data through23 Nov 2026, 01:44SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology