Completed
P50400030896
Kirange Nagari · Hingni, Wardha · Vishvanath Rama Kirange
Promised for 31 Dec 2022; MahaRERA reports the project completed.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- ✓Clear: MahaRERA reports the project as completed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 4
Orders 0
No MahaRERA order or list names this number.
Questions about P50400030896
Is Kirange Nagari delayed?
MahaRERA reports it completed. Its promised completion date was 31 Dec 2022.
How many extensions has it had?
Deedo holds 0 extension certificates for P50400030896.
Who is the promoter?
MahaRERA records Vishvanath Rama Kirange as the promoter of P50400030896.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P50400030896.