Completed

P50300024912

Radha City · Walgaon, Amravati · Krishnagiri Developers

Promised for 30 Mar 2022; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 13

Title report19 Feb 2020View
Encumbrance details19 Feb 2020View
Form B19 Feb 2020View
Allotment letter19 Feb 2020View
Form 29 Mar 2020View
Occupancy / completion certificate9 Mar 2021View
Occupancy / completion certificate9 Mar 2021View
Form 2A9 Mar 2021View
Show all 13 documents
Registration certificate8 Sep 2021View
OtherView
Layout planView
Commencement certificateView
Allotment letterView

Orders 0

No MahaRERA order or list names this number.

Questions about P50300024912

Is Radha City delayed?

MahaRERA reports it completed. Its promised completion date was 30 Mar 2022.

How many extensions has it had?

Deedo holds 0 extension certificates for P50300024912.

Who is the promoter?

MahaRERA records Krishnagiri Developers as the promoter of P50300024912.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50300024912.