P50300024912
Radha City · Walgaon, Amravati · Krishnagiri Developers
Promised for 30 Mar 2022; MahaRERA reports the project completed.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- ✓Clear: MahaRERA reports the project as completed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 13
Orders 0
No MahaRERA order or list names this number.
Questions about P50300024912
Is Radha City delayed?
MahaRERA reports it completed. Its promised completion date was 30 Mar 2022.
How many extensions has it had?
Deedo holds 0 extension certificates for P50300024912.
Who is the promoter?
MahaRERA records Krishnagiri Developers as the promoter of P50300024912.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P50300024912.