Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Completed

P50300013903

Uday Nagar Layout A · Amravati (M Corp.), Amravati · Umesh Ramchandra Chandak

Promised for 31 Oct 2019; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 10

Title report25 Oct 2017View
Encumbrance details25 Oct 2017View
Form B25 Oct 2017View
Registration certificate2 Nov 2017View
Form 529 Sep 2018View
Form 41 Feb 2020View
OtherView
Layout planView
Show all 10 documents
Commencement certificateView
Allotment letterView

Orders 0

No MahaRERA order or list names this number.

Questions about P50300013903

Is Uday Nagar Layout A delayed?

MahaRERA reports it completed. Its promised completion date was 31 Oct 2019.

How many extensions has it had?

Deedo holds 0 extension certificates for P50300013903.

Who is the promoter?

MahaRERA records Umesh Ramchandra Chandak as the promoter of P50300013903.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50300013903.

Answers are generated from the record.