Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P50200018767
Vrundavan Nagari · Washim (M Cl), Washim · Rukmani Builders And Developers
Promised for 30 Apr 2022, extended once to 30 Apr 2023 — and that date has passed without the project marked complete on MahaRERA.
4 years and 7 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Apr 2022 to 30 Apr 2023 (1 extension certificate on record).
- !Risk: The latest completion date on record, 30 Apr 2023, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 43
Show all 43 documents
Orders 0
No MahaRERA order or list names this number.
Questions about P50200018767
Is Vrundavan Nagari delayed?
Yes. MahaRERA records a promised completion of 30 Apr 2022, revised to 30 Apr 2023, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P50200018767. The completion date moved from 30 Apr 2022 to 30 Apr 2023.
Who is the promoter?
MahaRERA records Rukmani Builders And Developers as the promoter of P50200018767.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P50200018767.
Answers are generated from the record.