Completed

P50100052994

Shakambari Business Center · Akola (M Corp.), Akola · S P Builders & Developers

Promised for 31 Dec 2024; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 22

Title report3 Jun 2023View
Encumbrance details3 Jun 2023View
Commencement certificate3 Jun 2023View
Form B3 Jun 2023View
Other3 Jun 2023View
Other3 Jun 2023View
Other3 Jun 2023View
Allotment letter3 Jun 2023View
Show all 22 documents
Other3 Jun 2023View
Encumbrance details5 Jul 2023View
Commencement certificate5 Jul 2023View
Other5 Jul 2023View
Encumbrance details5 Jul 2023View
Commencement certificate20 Jul 2023View
Registration certificate10 Oct 2023View
Form 120 Jan 2024View
Form 220 Jan 2024View
Form 125 Apr 2024View
Form 225 Apr 2024View
OtherView
Layout planView
Allotment letterView

Orders 0

No MahaRERA order or list names this number.

Questions about P50100052994

Is Shakambari Business Center delayed?

MahaRERA reports it completed. Its promised completion date was 31 Dec 2024.

How many extensions has it had?

Deedo holds 0 extension certificates for P50100052994.

Who is the promoter?

MahaRERA records S P Builders & Developers as the promoter of P50100052994.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50100052994.

Answers are generated from the record.

Data through3 Nov 2026, 01:55SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology