Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Completed

P50100029630

Devki Park · Akola (M Corp.), Akola · Anil Gunwant Takwale

Promised for 31 Dec 2022; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 13

Title report8 Jun 2021View
Encumbrance details8 Jun 2021View
Commencement certificate8 Jun 2021View
Form B8 Jun 2021View
Form 28 Jun 2021View
Registration certificate14 Jun 2021View
Other19 Feb 2022View
OtherView
Show all 13 documents
Layout planView
Layout planView
Building planView
Building planView
Allotment letterView

Orders 0

No MahaRERA order or list names this number.

Questions about P50100029630

Is Devki Park delayed?

MahaRERA reports it completed. Its promised completion date was 31 Dec 2022.

How many extensions has it had?

Deedo holds 0 extension certificates for P50100029630.

Who is the promoter?

MahaRERA records Anil Gunwant Takwale as the promoter of P50100029630.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50100029630.

Answers are generated from the record.

Data through3 Nov 2026, 01:35SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology