Completed

P49900049006

Sai Krushanasha Height · Savkhede Bk., Jalgaon · Sai Krushna Associates

Promised for 31 Mar 2025; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 36

Allotment letter24 Nov 2022View
Title report24 Nov 2022View
Encumbrance details24 Nov 2022View
Commencement certificate24 Nov 2022View
Form B24 Nov 2022View
Allotment letter24 Nov 2022View
Other24 Nov 2022View
Commencement certificate29 Nov 2022View
Show all 36 documents
Other9 Dec 2022View
Encumbrance details10 Dec 2022View
Other12 Jan 2023View
Other12 Jan 2023View
Registration certificate24 Jan 2023View
Form 14 May 2023View
Form 24 May 2023View
Form 116 Aug 2023View
Form 116 Aug 2023View
Form 214 Dec 2023View
Form 129 Dec 2023View
Form 229 Dec 2023View
Form 13 Jan 2024View
Form 23 Jan 2024View
Form 59 Jan 2024View
Occupancy / completion certificate9 Jan 2024View
Occupancy / completion certificate15 Mar 2024View
Form 415 Mar 2024View
Form 117 Apr 2024View
Form 217 Apr 2024View
OtherView
Layout planView
Building planView
Building planView
Allotment letterView
OtherView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P49900049006

Is Sai Krushanasha Height delayed?

MahaRERA reports it completed. Its promised completion date was 31 Mar 2025.

How many extensions has it had?

Deedo holds 0 extension certificates for P49900049006.

Who is the promoter?

MahaRERA records Sai Krushna Associates as the promoter of P49900049006.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P49900049006.

Answers are generated from the record.

Data through23 Nov 2026, 01:50SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology