Completed
P49900020433
Shubhamangal · Jalgaon (M Corp.), Jalgaon · Shubhamangal Developers
Promised for 30 Dec 2022; MahaRERA reports the project completed.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- ✓Clear: MahaRERA reports the project as completed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 18
Orders 0
No MahaRERA order or list names this number.
Questions about P49900020433
Is Shubhamangal delayed?
MahaRERA reports it completed. Its promised completion date was 30 Dec 2022.
How many extensions has it had?
Deedo holds 0 extension certificates for P49900020433.
Who is the promoter?
MahaRERA records Shubhamangal Developers as the promoter of P49900020433.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P49900020433.