P49800011983
Rohini Apertment · Dhule (M Corp.), Dhule · Yogiraj Shivajirao Marathe
Promised for 31 Mar 2019; MahaRERA reports the project completed.
The revised date is 4 years after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Mar 2019 to 10 Mar 2023 (1 extension certificate on record).
- ✓Clear: MahaRERA reports the project as completed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 40
Orders 0
No MahaRERA order or list names this number.
Questions about P49800011983
Is Rohini Apertment delayed?
MahaRERA reports it completed. Its promised completion date was 31 Mar 2019.
How many extensions has it had?
Deedo holds 1 extension certificate for P49800011983. The completion date moved from 31 Mar 2019 to 10 Mar 2023.
Who is the promoter?
MahaRERA records Yogiraj Shivajirao Marathe as the promoter of P49800011983.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P49800011983.