RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P49800011701
Santkrupa Sankul · Dhule (M Corp.), Dhule · Chandrakant Kashinath Kele
Promised for 31 Dec 2019; MahaRERA reports the project completed.
The revised date is 2 years after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Dec 2019 to 30 Dec 2021 (1 extension certificate on record).
- ✓Clear: MahaRERA reports the project as completed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 41
Orders 0
No MahaRERA order or list names this number.
Questions about P49800011701
Is Santkrupa Sankul delayed?
MahaRERA reports it completed. Its promised completion date was 31 Dec 2019.
How many extensions has it had?
Deedo holds 1 extension certificate for P49800011701. The completion date moved from 31 Dec 2019 to 30 Dec 2021.
Who is the promoter?
MahaRERA records Chandrakant Kashinath Kele as the promoter of P49800011701.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P49800011701.