RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P49800009342
Raka Park · Walwadi (Ct), Dhule · Adinath Infrastructure
Promised for 26 Aug 2018; MahaRERA reports the project completed.
The revised date is 2 years and 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 26 Aug 2018 to 30 Dec 2020 (1 extension certificate on record).
- ✓Clear: MahaRERA reports the project as completed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 20
Orders 0
No MahaRERA order or list names this number.
Questions about P49800009342
Is Raka Park delayed?
MahaRERA reports it completed. Its promised completion date was 26 Aug 2018.
How many extensions has it had?
Deedo holds 1 extension certificate for P49800009342. The completion date moved from 26 Aug 2018 to 30 Dec 2020.
Who is the promoter?
MahaRERA records Adinath Infrastructure as the promoter of P49800009342.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P49800009342.
Answers are generated from the record.