Varniraj 23
Deedo IDDP-RAI-5MBHCompletion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 21% of its units are booked.
Ulawe, Raigarh 400706 · by Varniraj Group · 100% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2028
- This projectRegistered 25 May 2026, completion promised 31 Dec 2027, revised to 30 Apr 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPM1270002600538
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PM1270002600538 | 25 May 2026 | 31 Dec 2027 | 30 Apr 2028 | Varniraj Group | Project page |
Documents25
1 document held by Deedo, 24 filings listed on MahaRERA's project page
Finance
Legal
- OthersSearch Report.pdf · uploaded 18 Mar 2026Source
- OthersFlow of Title.pdf · uploaded 18 Mar 2026Source
- OthersLetter of Allotment.pdf · uploaded 18 Mar 2026Source
- Declaration Form BLegal Title Report with Litigation.pdf · uploaded 18 Mar 2026Source
- Declaration Form BFORM B_Varniraj Group.pdf · uploaded 18 Mar 2026Source
Show all 25 documentsShow fewer documents
Legal
- Declaration Form BLand Ownership Document.pdf · uploaded 18 Mar 2026Source
- OthersAnnx A All Partners.pdf · uploaded 25 Mar 2026Source
- Declaration Form BAgreement to Lease_.pdf · uploaded 24 Apr 2026Source
- OthersTripartie Agreement Varniraj Group.pdf · uploaded 13 May 2026Source
- OthersFinal Order.pdf · uploaded 13 May 2026Source
- Declaration Form BFinal Order.pdf · uploaded 13 May 2026Source
- Declaration Form BTripartie Agreement Varniraj Group.pdf · uploaded 13 May 2026Source
Migrated
Technical
Technical (Architect)
- DocumentForm 1.pdf · uploaded 20 Jul 2026Source
Technical (Engineer)
- DocumentForm 2.pdf · uploaded 20 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel PLOT NO 159
As registered with MahaRERA and published on its project page
- Project type
- Mixed
- Status on MahaRERA
- Certificate Signed
- Unit types
- —19 units in all
- Address
- Plot No. 159, UlwePIN 400706
- Village
- Ulawe, Panvel taluka
- Location
- 18.97201, 73.03482
- Land area for this project
- 600 sq m (6,457 sq ft)
- Permissible built-up area
- 839 sq m (9,033 sq ft)
- Sanctioned built-up area
- 839 sq m (9,033 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 82
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
PLOT NO 159
Boundaries
- North
- Plot No. 158
- South
- Plot No. 160
- East
- 15.00 Mtrs, Wide Road
- West
- Plot No. 171 & 172
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking19 units
19 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 19 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Chartered accountant | Govind Manjibhai Sandha | — |
| Chartered accountant | Jayesh Keshavji Patel | — |
| Engineer | Samarth Agarwal | — |
Source: MahaRERA project page. Contact details are not shown.