Shivkrishna Arcade
Deedo IDDP-RAI-CE43Completion was pushed back 1 year and 6 months to Nov 2022, and that date has passed too; no MahaRERA orders on record; 74% of its units are booked.
Ulawe, Raigarh 410206 · by Shiv Krishana Developers
Buying a flat here?
See every deed registered on it.
Completion was pushed back 1 year and 6 months to Nov 2022, and that date has passed too
- This projectRegistered 31 Aug 2017, completion promised 28 May 2021, revised to 28 Nov 2022, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000011590
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000011590 | 31 Aug 2017 | 28 May 2021 | 28 Nov 2022 | Shiv Krishana Developers | Project page |
Documents30
2 documents held by Deedo, 28 filings listed on MahaRERA's project page
Legal
Migrated
- 1 Details of encumbrancesconsern leter 302 shiv.pdf · uploaded 1 Aug 2017Source
Show all 30 documentsShow fewer documents
Migrated
- 1 Declaration in FORM Bdec shiv 1.pdf · uploaded 1 Aug 2017Source
- 2 Declaration in FORM Bdec shiv 2.pdf · uploaded 1 Aug 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)kalpak ar 1.pdf · uploaded 1 Aug 2017Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)kalpak ar 2.pdf · uploaded 1 Aug 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)imfr doc 1.pdf · uploaded 1 Aug 2017Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)imfra doc shiv 302 2.pdf · uploaded 1 Aug 2017Source
- 1 Certificates of CA (Form 3)FORM 3_CA CERTIFICATE.pdf · uploaded 1 Aug 2017Source
- 1 Proforma of Allotment letterAgreement to Sale- Flat-Builder -rera.pdf · uploaded 1 Aug 2017Source
- 1 Copy of the legal title reporttitale 1.pdf · uploaded 2 Aug 2017Source
- 2 Copy of the legal title reporttitle 2.pdf · uploaded 2 Aug 2017Source
- 3 Copy of the legal title reporttitale 3.pdf · uploaded 2 Aug 2017Source
- 1 Copy of Layout Approval (in case of layout)floor plan.pdf · uploaded 2 Aug 2017Source
- 2 Copy of Layout Approval (in case of layout)plan bilding.pdf · uploaded 2 Aug 2017Source
- 1 Building Plan Approval (IOD)aprood plan.pdf · uploaded 2 Aug 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentShiv Krishna CC.pdf · uploaded 19 Sep 2018Source
- 1 Other – TechnicalShiv Krishna Arcade.pdf · uploaded 14 Mar 2023Source
Technical
Technical (Architect)
- Documentkalpak ar 2.pdf · uploaded 1 Aug 2017Source
Technical (Engineer)
- Documentimfra doc shiv 302 2.pdf · uploaded 1 Aug 2017Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel PLOT NO 302
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1 BHK, 1 RK, 1 RK WITH TERRACE, Shop23 units in all
- Address
- Plot No 302PIN 410206
- Village
- Ulawe, Panvel taluka
- Location
- 18.97509, 73.05233
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Plot No 301
- South
- Plot No 303
- East
- Plot No 300
- West
- 11 Mtrs Wide Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking23 units
17 of 23 units booked (74%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 24.25 sq m · 261 sq ft | 3 | 2 |
| 1 BHK | 25.37 sq m · 273 sq ft | 3 | 3 |
| 1 BHK | 25.54 sq m · 275 sq ft | 3 | 3 |
| 1 BHK | 25.83 sq m · 278 sq ft | 3 | 0 |
| 1 RK | 16.8 sq m · 181 sq ft | 3 | 2 |
| 1 RK WITH TERRACE | 19.21 sq m · 207 sq ft | 2 | 2 |
| 1 RK WITH TERRACE | 19.81 sq m · 213 sq ft | 2 | 1 |
| Shop | 11.83 sq m · 127 sq ft | 3 | 3 |
| Shop | 14.42 sq m · 155 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Kalpak Architects | — |
| Registered real estate agent | Rajnandan kumar Jaiswal | — |
Source: MahaRERA project page. Contact details are not shown.