Main building, Reddys Pride
Deedo IDDP-RAI-M6NM-RP6 flats have a sale on record, 2 are booked without a sale deed yet and 11 are unsold, per MahaRERA's Oct 2026 disclosure and the registered deeds.
Every flat, floor by floor
Tap a flat to see its record.
- Sale registered
- Booked, no deed yet
- Unsold
- Reserved, rehab or other
Other units on these floors (no stack in the number):
Sale status from MahaRERA's Oct 2026 disclosure; deeds from IGR Index II, placed on a flat only when the deed names this tower and flat. “Listed by developer” comes from the developer and is labelled as such.
Flat 705
2 BHK · 394 sq ft · floor 7
- Deeds
- 0
- Last activity
- None on record
- Last sale
- None registered
Units & parking in Main building
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 26.1 m² (281 sq.ft) | 2 | 0 |
| 1BHK | 26.2 m² (281 sq.ft) | 2 | 0 |
| 1BHK | 27.8 m² (299 sq.ft) | 5 | 0 |
| 1BHK | 27.9 m² (300 sq.ft) | 5 | 1 |
| 2BHK | 36.6 m² (394 sq.ft) | 2 | 1 |
| 2BHK | 38.2 m² (411 sq.ft) | 4 | 2 |
| 2BHK | 49.5 m² (533 sq.ft) | 1 | 0 |
| 2BHK | 49.6 m² (534 sq.ft) | 1 | 1 |
| 2BHK | 51 m² (549 sq.ft) | 1 | 0 |
| 2BHK | 51.1 m² (550 sq.ft) | 1 | 0 |
| 2BHK | 53.8 m² (579 sq.ft) | 2 | 0 |
| 2BHK | 53.9 m² (580 sq.ft) | 2 | 0 |
| 2BHK | 55.6 m² (598 sq.ft) | 3 | 0 |
| 2BHK | 55.7 m² (599 sq.ft) | 3 | 1 |
| Shop | 20.9 m² (224 sq.ft) | 2 | 1 |
| Shop | 29.1 m² (313 sq.ft) | 2 | 1 |
As registered with MahaRERA
- RERA registration
- P52000054827 · registered 15 Feb 2024
- Promised completion
- 31 Dec 2026
- Revised completion
- 30 Apr 2027
- Sanctioned habitable floors
- 8
- Building
- REDDYS PRIDE
- Sanctioned floors (incl. basement, stilt, podium)
- 8
- Units declared
- 38
- Homes
- 34
- Shops and offices
- 4
- Sanctioned FSI area (sq m)
- 8
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-RAI-M6NM-RP
Questions about Main building
How many flats in Main building are sold?
6 flats have a sale on record, 2 are booked without a sale deed yet and 11 are unsold, per MahaRERA's Oct 2026 disclosure and the registered deeds.
When is Main building due for completion?
The MahaRERA registration promises 31 Dec 2026, revised to 30 Apr 2027.
How many floors does Main building have?
8 sanctioned habitable floors, as registered with MahaRERA.