Progressive Grande
Deedo IDDP-RAI-74DHMahaRERA shows it completed; no MahaRERA orders on record; 100% of its units are booked.
Ulawe, Raigarh 410206 · by Progressive Homes
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed
- This projectRegistered 5 Jun 2018, completion promised 30 Dec 2022.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000016703
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000016703 | 5 Jun 2018 | 30 Dec 2022 | 30 Dec 2022 | Progressive Homes | Project page |
Documents63
1 document held by Deedo, 62 filings listed on MahaRERA's project page
Finance
- PAN CardPH.pdf · uploaded 13 Jan 2021Source
Legal
- Legal Title reportTitle Report.pdf · uploaded 24 May 2018Source
- Declaration Form BFORM B.pdf · uploaded 25 May 2018Source
- OtherCourt Order new.pdf · uploaded 20 Nov 2018Source
- Legal Title reportNew Title Report.pdf · uploaded 20 Nov 2018Source
- OtherOccupancy Certificate Plot No 3.pdf · uploaded 19 Feb 2020Source
Migrated
- 1 Copy of the legal title reportTitle Report.pdf · uploaded 24 May 2018Source
Show all 63 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentCommencement certificate with receipt.pdf · uploaded 24 May 2018Source
- 1 Certificates of CA (Form 3)PH RERA Certificate.pdf · uploaded 24 May 2018Source
- 1 Details of encumbrancesNo Encumbrance.pdf · uploaded 25 May 2018Source
- 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 25 May 2018Source
- 1 Building Plan Approval (IOD)Ground and 1st Floor.pdf · uploaded 25 May 2018Source
- 2 Building Plan Approval (IOD)2nd Floor.pdf · uploaded 25 May 2018Source
- 3 Building Plan Approval (IOD)3rd Floor.pdf · uploaded 25 May 2018Source
- 4 Building Plan Approval (IOD)4th Floor.pdf · uploaded 25 May 2018Source
- 5 Building Plan Approval (IOD)5th Floor.pdf · uploaded 25 May 2018Source
- 6 Building Plan Approval (IOD)6th Floor.pdf · uploaded 25 May 2018Source
- 7 Building Plan Approval (IOD)7th Floor.pdf · uploaded 25 May 2018Source
- 8 Building Plan Approval (IOD)8th Floor.pdf · uploaded 25 May 2018Source
- 9 Building Plan Approval (IOD)9th Floor.pdf · uploaded 25 May 2018Source
- 10 Building Plan Approval (IOD)10th Floor.pdf · uploaded 25 May 2018Source
- 11 Building Plan Approval (IOD)11th Floor.pdf · uploaded 25 May 2018Source
- 12 Building Plan Approval (IOD)Terrace Floor Plan.pdf · uploaded 25 May 2018Source
- 13 Building Plan Approval (IOD)Elevation.pdf · uploaded 25 May 2018Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 25 May 2018Source
- 1 Proforma of Allotment letterAgreement for Sale by Promoter.pdf · uploaded 26 May 2018Source
- 2 Copy of the legal title reportNew Title Report.pdf · uploaded 20 Nov 2018Source
- 1 OtherCourt Order new.pdf · uploaded 20 Nov 2018Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 23 Nov 2018Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer's Certificate.pdf · uploaded 23 Nov 2018Source
- 2 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 23 Nov 2018Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)RERA.pdf · uploaded 26 Mar 2019Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate Mar 2019.pdf · uploaded 26 Mar 2019Source
- 3 Certificates of CA (Form 3)IMG_0003.pdf · uploaded 26 Mar 2019Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT FORM 1.pdf · uploaded 10 Jul 2019Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate Form 2.pdf · uploaded 10 Jul 2019Source
- 4 Certificates of CA (Form 3)CA FORM 3.pdf · uploaded 10 Jul 2019Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)RERA AUDIT REPORT.pdf · uploaded 18 Dec 2019Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOccupancy Certificate Plot No 3.pdf · uploaded 16 Jan 2020Source
- 2 OtherOccupancy Certificate Plot No 3.pdf · uploaded 19 Feb 2020Source
- 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4.pdf · uploaded 3 Mar 2020Source
- 1 PAN CardPH.pdf · uploaded 13 Jan 2021Source
- 5 Certificates of CA (Form 3)FORM 3.pdf · uploaded 13 Jan 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 DT 25092020.pdf · uploaded 13 Jan 2021Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society Registration Certificate.pdf · uploaded 31 Aug 2023Source
- 1 Foreclosure of the ProjectLOAN Closure Letter.pdf · uploaded 31 Aug 2023Source
Technical
- DocumentGround and 1st Floor.pdf · uploaded 25 May 2018Source
- Document2nd Floor.pdf · uploaded 25 May 2018Source
- Document3rd Floor.pdf · uploaded 25 May 2018Source
- Document4th Floor.pdf · uploaded 25 May 2018Source
- Document5th Floor.pdf · uploaded 25 May 2018Source
- Document6th Floor.pdf · uploaded 25 May 2018Source
- Document7th Floor.pdf · uploaded 25 May 2018Source
- Document8th Floor.pdf · uploaded 25 May 2018Source
- Document9th Floor.pdf · uploaded 25 May 2018Source
- Document10th Floor.pdf · uploaded 25 May 2018Source
- Document11th Floor.pdf · uploaded 25 May 2018Source
- DocumentTerrace Floor Plan.pdf · uploaded 25 May 2018Source
- DocumentElevation.pdf · uploaded 25 May 2018Source
- DocumentLayout.pdf · uploaded 25 May 2018Source
Technical (Architect)
- DocumentARCHITECT FORM 1.pdf · uploaded 10 Jul 2019Source
Technical (Engineer)
- DocumentEngineer Certificate Form 2.pdf · uploaded 10 Jul 2019Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 3
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2 BHK, 2 BHK WITH TERRACE, 3 BHK, 4 BHK94 units in all
- Address
- 3, Sector 8a, Ulwe Navi MumbaiPIN 410206
- Village
- Ulawe, Panvel taluka
- Location
- 18.96890, 73.01313
- Land area for this project
- 3,299 sq m (35,506 sq ft)
- Permissible built-up area
- 4,948 sq m (53,257 sq ft)
- Sanctioned built-up area
- 4,948 sq m (53,257 sq ft)
- Recreational open space
- 182 sq m (1,962 sq ft)
- Designated bank account
- 171
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
3
Boundaries
- North
- Plot No 2
- South
- Plot No 4
- East
- Plot No 8-7
- West
- 30 Mtrs Wide Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking94 units
94 of 94 units booked (100%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2 BHK | 37.94 sq m · 408 sq ft | 1 | 1 |
| 2 BHK | 40.62 sq m · 437 sq ft | 19 | 19 |
| 2 BHK | 40.81 sq m · 439 sq ft | 34 | 34 |
| 2 BHK | 48.22 sq m · 519 sq ft | 4 | 4 |
| 2 BHK WITH TERRACE | 48.37 sq m · 521 sq ft | 4 | 4 |
| 3 BHK | 57.65 sq m · 621 sq ft | 14 | 14 |
| 3 BHK | 61.25 sq m · 659 sq ft | 14 | 14 |
| 4 BHK | 64.55 sq m · 695 sq ft | 2 | 2 |
| 4 BHK | 72.02 sq m · 775 sq ft | 2 | 2 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Atul Patel Architects | — |
| Engineer | Amitesh L Prabhu | — |
Source: MahaRERA project page. Contact details are not shown.