Residential / Group Housing · 2 buildings · 13 unitsRERA P52000027641

Housai

Deedo IDDP-RAI-JNPM

Completion was pushed back 4 years and 3 months, to Dec 2026; no MahaRERA orders on record; 0% of its units are booked.

Ulawe, Raigarh 410206 · by Prashant Dashrath Mhatre

DeliveryExtended 4 yrs 3 moPromised Sep 2022 · now due Dec 2026RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 13 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 years and 3 months, to Dec 2026

  • This projectRegistered 25 Dec 2020, completion promised 30 Sep 2022, revised to 30 Dec 2026.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000027641
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200002764125 Dec 202030 Sep 202230 Dec 2026Prashant Dashrath MhatreProject page
Documents24

3 documents held by Deedo, 21 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPANCARD (1).pdf · uploaded 11 Dec 2020Source

Legal

  • Declaration Form BFORM B PRASHANT .pdf · uploaded 12 Dec 2020Source
  • Legal Title reportTitle-Shree Sai-A-17_compressed (3).pdf · uploaded 14 Dec 2020Source

Migrated

  • 1 PAN CardPANCARD (1).pdf · uploaded 11 Dec 2020Source
  • 1 Copy of Layout Approval (in case of layout)IOD PLAN.pdf · uploaded 11 Dec 2020Source
Show all 24 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval / NA Order for plotted developmentIOD PLAN.pdf · uploaded 11 Dec 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 11 Dec 2020Source
  • 1 Details of encumbrancesPRASHANT ENCUMBRANCE.pdf · uploaded 12 Dec 2020Source
  • 1 Declaration in FORM BFORM B PRASHANT .pdf · uploaded 12 Dec 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 HOUSAI.pdf · uploaded 12 Dec 2020Source
  • 1 Copy of the legal title reportTitle-Shree Sai-A-17_compressed (3).pdf · uploaded 14 Dec 2020Source
  • 1 Proforma of Allotment letterAgreement For Sale_shree sai developers.pdf · uploaded 14 Dec 2020Source
  • 2 Proforma of Allotment letterAllotment Letter.pdf · uploaded 14 Dec 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 FY 2020-2021.pdf · uploaded 24 Nov 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 FY 2021-2022.pdf · uploaded 24 Nov 2022Source
  • 1 Disclosure of sold/ booked inventoryHousai 29.pdf · uploaded 6 Dec 2022View
  • 1 Declaration about Commencement CertificateHousai Format D.pdf · uploaded 3 Jan 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Housai Form 2A 20-21.pdf · uploaded 3 Jan 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Housai Form 2A 21-22.pdf · uploaded 3 Jan 2023Source

Technical

  • DocumentIOD PLAN.pdf · uploaded 11 Dec 2020Source
  • DocumentIOD PLAN.pdf · uploaded 11 Dec 2020Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel PLOT NO A 17

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, Multipurpose13 units in all
Address
Plot No -A 17, Sector 16, UlwePIN 410206
Village
Ulawe, Panvel taluka
Land area for this project
200 sq m (2,152 sq ft)
Permissible built-up area
300 sq m (3,227 sq ft)
Sanctioned built-up area
300 sq m (3,227 sq ft)
Designated bank account
190
Developed in phases
No

Survey, CTS, gat or plot numbers

PLOT NO A 17

Land as published on MahaRERA's project page

PLOT NO -A 17

Boundaries

North
Plot No -3
South
9 Mtr Wide Road
East
Plot No 1 And 2
West
Plot No -16

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking13 units

0 of 13 units booked (0%), as the promoter reported to MahaRERA

1BHK · 7 units1RK · 1 unitMultipurpose · 5 units
TypeCarpet areaUnitsBooked
1BHK25.6 sq m · 276 sq ft30
1BHK26.07 sq m · 281 sq ft30
1BHK27.22 sq m · 293 sq ft10
1RK19.79 sq m · 213 sq ft10
Multipurpose12.69 sq m · 137 sq ft10
Multipurpose14.88 sq m · 160 sq ft30
Multipurpose14.97 sq m · 161 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAtul Patel Architects—
Chartered accountantRutuja Narsingh & Associates—
EngineerAgharkar Consultants—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology