RERA projects in Shivkar

6 projects under 8 MahaRERA registrations, registered 2017–2026. 75% have a completion date extended beyond the one promised.

Locality
6RERA projects
8Registrationssome projects hold several
3Completion still due5 past their completion date
22 monthsMedian extension beyond promised date75% of registrations extended
0Regulatory casesnone on MahaRERA's lists
13Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171
20184
20192
20200
20210
20220
20230
20240
20250
20261

Projects in Shivkar

6 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Vighnaharta HeightOm EnterprisesPR127000260050222 May 202631 Dec 203030 Apr 2031Extended 4 mo0
Shree Sai CornerShree Ganesh Builders And DevelopersP517000229848 Nov 201930 Dec 202331 Mar 2027Extended 39 mo0
KPS ParkKPS EnterprisesP5200002002919 Mar 201928 Feb 202331 Dec 2027Extended 58 mo0
Shambhavi ResidencyShree Siddhivinayak DevelopersP520000188666 Dec 201830 Dec 202230 Dec 2022Promised date passed0
Utsav CityToday Micron DevelopersP52000016710, P52000018102, P520000190695 Jun 201830 Dec 202230 Dec 2023Extended 12 mo0
Rumee RegencyShabbir Mohiddin SheikhP5200001444030 Nov 201730 Jun 202630 Jun 2026Promised date passed0

Other localities in Panvel

Most active promoters

By projects registered here, as named on MahaRERA.

  1. KPS Enterprises1 project
  2. Om Enterprises1 project
  3. Shabbir Mohiddin Sheikh1 project
  4. Shree Ganesh Builders And Developers1 project
  5. Shree Siddhivinayak Developers1 project
  6. Today Micron Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology