Skip to content
Residential / Group Housing · 2 buildings · 20 unitsRERA P52000049898

Dhanashree Apartment

Deedo IDDP-RAI-JMWW

Completion was pushed back 1 year to Dec 2025, and that date has passed too; no MahaRERA orders on record; 30% of its units are booked.

Rees, Raigarh 410222 · by Manunayak Manshing Rathlavath

Delivery1 yr 11 mo latePromised Dec 2024 · revised Dec 2025 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales30% booked6 of 20 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 1 year to Dec 2025, and that date has passed too

  • This projectRegistered 6 Mar 2023, completion promised 31 Dec 2024, revised to 30 Dec 2025, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000049898
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P520000498986 Mar 202331 Dec 202430 Dec 2025Manunayak Manshing RathlavathProject page
Documents111

3 documents held by Deedo, 108 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPAN CARD.pdf · uploaded 11 Jan 2023Source
  • Other – FinanceForm E.pdf · uploaded 8 Mar 2025Source

Legal

  • Legal Title reportTitle Report new.pdf · uploaded 13 Feb 2023Source
  • Legal Title reportSearch Report, Title Report flow.pdf · uploaded 13 Feb 2023Source
  • Declaration Form BB FORM NEW Promoter.pdf · uploaded 1 Mar 2023Source
Show all 111 documentsShow fewer documents

Legal

  • Declaration Form BB FORM NEW Land Owner.pdf · uploaded 1 Mar 2023Source
  • Other – LegalFormat B.pdf · uploaded 9 Feb 2025Source
  • Declaration Form BB Form Declaration Before Me.pdf · uploaded 9 Feb 2025Source
  • Other – LegalFormat B.pdf · uploaded 8 Mar 2025Source
  • Declaration Form B'Declaration form B' Before me.pdf · uploaded 21 Mar 2025Source

Migrated

  • 1 PAN CardPAN CARD.pdf · uploaded 11 Jan 2023Source
  • 1 a Details of encumbrances concerned to FinanceDeclaration for Cersai.pdf · uploaded 11 Jan 2023Source
  • 1 b Details of encumbrances concerned to LegalDeclaration for Cersai.pdf · uploaded 11 Jan 2023Source
  • 1 Copy of Layout Approval (in case of layout)Layout1.pdf · uploaded 11 Jan 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 11 Jan 2023Source
  • 1 Declaration about Commencement CertificateDeclaration for CC.pdf · uploaded 11 Jan 2023Source
  • 1 CERSAI detailsDeclaration_Cersai.pdf · uploaded 11 Jan 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 12 Jan 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsRadha Krishna Enterprises.pdf · uploaded 12 Jan 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameCheque.pdf · uploaded 12 Jan 2023Source
  • 2 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Declaration.pdf · uploaded 12 Jan 2023Source
  • 1 Deviation Report with respect to Allotment letterDeclaration for Allotment.pdf · uploaded 12 Jan 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeclaration_Deviation in Agreeement For Sale.pdf · uploaded 12 Jan 2023Source
  • 2 a Details of encumbrances concerned to FinanceNo Encumbrances.pdf · uploaded 4 Feb 2023Source
  • 2 b Details of encumbrances concerned to LegalNo Encumbrances.pdf · uploaded 4 Feb 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentPLAN 1.pdf · uploaded 4 Feb 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentPLAN 2.pdf · uploaded 4 Feb 2023Source
  • 3 Building Plan Approval / NA Order for plotted developmentPLAN 3.pdf · uploaded 4 Feb 2023Source
  • 1 Proforma of Agreement for saleAgreement for Sale RERA Radha Krishna.pdf · uploaded 4 Feb 2023Source
  • 1 Copy of the legal title reportTitle Report new.pdf · uploaded 13 Feb 2023Source
  • 2 Copy of the legal title reportSearch Report, Title Report flow.pdf · uploaded 13 Feb 2023Source
  • 1 Proforma of Allotment letterModel Form Allotment Letter.pdf · uploaded 13 Feb 2023Source
  • 1 Declaration in FORM BB FORM NEW Promoter.pdf · uploaded 1 Mar 2023Source
  • 2 Declaration in FORM BB FORM NEW Land Owner.pdf · uploaded 1 Mar 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ilovepdf_merged (3).pdf · uploaded 6 Mar 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ilovepdf_merged (4).pdf · uploaded 6 Mar 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)ilovepdf_merged (5).pdf · uploaded 6 Mar 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)ilovepdf_merged (6).pdf · uploaded 6 Mar 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Apr 23.pdf · uploaded 6 Mar 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Jan 23.pdf · uploaded 6 Mar 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Jan 24.pdf · uploaded 6 Mar 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 July 23.pdf · uploaded 6 Mar 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Oct 23.pdf · uploaded 6 Mar 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q1 ending 31-03-2023_ signed.pdf · uploaded 6 Mar 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q2 Ending 30-06-2023_ signed.pdf · uploaded 6 Mar 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q3 ending 30-09-2023 _ signed.pdf · uploaded 6 Mar 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q4 Form 3 31-12-2023 -signed_compressed.pdf · uploaded 6 Mar 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1.pdf · uploaded 13 Jun 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 13 Jun 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 13 Jun 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1_merged.pdf · uploaded 6 Nov 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q1.pdf · uploaded 6 Nov 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2.pdf · uploaded 6 Nov 2024Source
  • 1 Declaration in FORM BB Form Declaration Before Me.pdf · uploaded 9 Feb 2025Source
  • 1 Other – LegalFormat B.pdf · uploaded 9 Feb 2025Source
  • 1 Disclosure of sold/ booked inventoryFlats Details.pdf · uploaded 9 Feb 2025View
  • 1 Other – TechnicalForm E.pdf · uploaded 9 Feb 2025Source
  • 1 Other – LegalFormat B.pdf · uploaded 8 Mar 2025Source
  • 1 Disclosure of sold/ booked inventoryFlats Details.pdf · uploaded 8 Mar 2025View
  • 1 Other – FinanceForm E.pdf · uploaded 8 Mar 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5.pdf · uploaded 8 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)2A July23.pdf · uploaded 8 Mar 2025Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)2A Dec23.pdf · uploaded 8 Mar 2025Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)2A Oct23.pdf · uploaded 8 Mar 2025Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)2A Mar24.pdf · uploaded 8 Mar 2025Source
  • 5 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)2A June24.pdf · uploaded 8 Mar 2025Source
  • 6 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)2A Oct24.pdf · uploaded 8 Mar 2025Source
  • 7 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)2A Dec24.pdf · uploaded 8 Mar 2025Source
  • 1 Declaration in FORM B'Declaration form B' Before me.pdf · uploaded 21 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 (1-10-24 to 31-12-24).pdf · uploaded 25 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 25 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Radha Krushana Ent - Form 2.pdf · uploaded 25 Mar 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5.pdf · uploaded 25 Mar 2025Source
  • Form 1Form 1 (1-10-24 to 31-12-24).pdf · uploaded 16 May 2025Source
  • Form 2Radha Krushana Ent - Form 2.pdf · uploaded 16 May 2025Source
  • Form 3FORM 3.pdf · uploaded 16 May 2025Source
  • Form 1Form 1 (1-10-24 to 31-12-24).pdf · uploaded 16 May 2025Source
  • Form 2Radha Krushana Ent - Form 2.pdf · uploaded 16 May 2025Source
  • Form 3FORM 3.pdf · uploaded 16 May 2025Source
  • Form 1Form 1 (1-10-24 to 31-12-24).pdf · uploaded 16 May 2025Source
  • Form 2Radha Krushana Ent - Form 2.pdf · uploaded 16 May 2025Source
  • Form 3FORM 3.pdf · uploaded 16 May 2025Source
  • Form 1Form 1 (1-10-24 to 31-12-24).pdf · uploaded 16 May 2025Source
  • Form 2Radha Krushana Ent - Form 2.pdf · uploaded 16 May 2025Source
  • Form 3FORM 3.pdf · uploaded 16 May 2025Source
  • Form 1Form 1 (1-10-24 to 31-12-24).pdf · uploaded 16 May 2025Source
  • Form 2Radha Krushana Ent - Form 2.pdf · uploaded 16 May 2025Source
  • Form 3FORM 3.pdf · uploaded 16 May 2025Source
  • Form 1Form 1 (1-10-24 to 31-12-24).pdf · uploaded 16 May 2025Source
  • Form 2Radha Krushana Ent - Form 2.pdf · uploaded 16 May 2025Source
  • Form 3FORM 3.pdf · uploaded 16 May 2025Source
  • Form 1Form 1 (1-10-24 to 31-12-24).pdf · uploaded 16 May 2025Source
  • Form 2Radha Krushana Ent - Form 2.pdf · uploaded 16 May 2025Source
  • Form 3FORM 3.pdf · uploaded 16 May 2025Source
  • Form 1Radha Krushana Ent - Form 2.pdf · uploaded 16 May 2025Source
  • Form 2Form 1 (1-10-24 to 31-12-24).pdf · uploaded 16 May 2025Source
  • Form 3FORM 3.pdf · uploaded 16 May 2025Source

Technical

  • DocumentLayout1.pdf · uploaded 11 Jan 2023Source
  • DocumentPLAN 1.pdf · uploaded 4 Feb 2023Source
  • DocumentPLAN 2.pdf · uploaded 4 Feb 2023Source
  • DocumentPLAN 3.pdf · uploaded 4 Feb 2023Source
  • Other – TechnicalForm E.pdf · uploaded 9 Feb 2025Source

Technical (Architect)

  • DocumentForm1.pdf · uploaded 13 Jun 2024Source
  • DocumentForm-1_merged.pdf · uploaded 6 Nov 2024Source
  • DocumentForm 1 (1-10-24 to 31-12-24).pdf · uploaded 25 Mar 2025Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 13 Jun 2024Source
  • DocumentForm-2.pdf · uploaded 6 Nov 2024Source
  • DocumentRadha Krushana Ent - Form 2.pdf · uploaded 25 Mar 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel NEW SURVEY NO. 3/3/A/4 (OLD SURVEY NO. 3/3, PLOT NO. 4)

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK20 units in all
Address
New Survey No. 3/3/A/4 (Old Survey No. 3/3, Plot No. 4), Plot No. 4, Survey No. 3/3/A/4PIN 410222
Village
Rees, Khalapur taluka
Land area for this project
388 sq m (4,176 sq ft)
Permissible built-up area
866 sq m (9,325 sq ft)
Sanctioned built-up area
866 sq m (9,325 sq ft)
Designated bank account
148
Developed in phases
No

Survey, CTS, gat or plot numbers

NEW SURVEY NO. 3/3/A/4 (OLD SURVEY NO. 3/3PLOT NO. 4)

Land as published on MahaRERA's project page

NEW SURVEY NO. 3/3/A/4 (OLD SURVEY NO. 3/3, PLOT NO. 4)

Boundaries

North
Plot No
South
Plot No
East
Plot No
West
Plot No

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking20 units

6 of 20 units booked (30%), as the promoter reported to MahaRERA

1BHK · 20 units
TypeCarpet areaUnitsBooked
1BHK28.85 sq m · 311 sq ft51
1BHK29.48 sq m · 317 sq ft50
1BHK31.23 sq m · 336 sq ft105

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectA And K Associates—
Chartered accountantMayur G Shinde—
EngineerA And K Associates—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology