RERA projects in Pushpak Vahal
5 projects under 5 MahaRERA registrations, registered 2026–2026. 60% have a completion date extended beyond the one promised.
Locality
5RERA projects
5Registrations
5Completion still due0 past their completion date
4 monthsMedian extension beyond promised date60% of registrations extended
0Regulatory casesnone on MahaRERA's lists
28Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2026 | 5 |
Projects in Pushpak Vahal
5 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Anmol Nagesh ResidencyVasant Nagesh Bhopi | PM1270002602394 | 17 Oct 2026 | 31 May 2028 | — | Not yet due | 0 |
| Shree Ram DeltaShreenathji Enterprises | PR1270002601579 | 18 Aug 2026 | 30 Jun 2032 | 30 Jun 2032 | Not yet due | 0 |
| Shreepati GurukrupaGurukrupa Buildcon | PM1270002601105 | 9 Jul 2026 | 30 Jun 2029 | 30 Oct 2029 | Extended 4 mo | 0 |
| Madhavi ResidencyMahavir Enterprises | PR1270002503043 | 25 Mar 2026 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| PearlSakha Developers | PM1270002502901 | 18 Mar 2026 | 31 Mar 2029 | 31 Jul 2029 | Extended 4 mo | 0 |
Other localities in Panvel
Most active promoters
By projects registered here, as named on MahaRERA.
- Gurukrupa Buildcon1 project
- Mahavir Enterprises1 project
- Sakha Developers1 project
- Shreenathji Enterprises1 project
- Vasant Nagesh Bhopi1 project
Data through18 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology