RERA projects in Pushpak Nagar
4 projects under 4 MahaRERA registrations, registered 2025–2026. 75% have a completion date extended beyond the one promised.
Locality
4RERA projects
4Registrations
4Completion still due0 past their completion date
4 monthsMedian extension beyond promised date75% of registrations extended
0Regulatory casesnone on MahaRERA's lists
6Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2025 | 1 |
| 2026 | 3 |
Projects in Pushpak Nagar
4 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Shreepati SukhkartaShreepati Group | PR1270002602041 | 24 Sep 2026 | 31 Dec 2031 | 31 Dec 2031 | Not yet due | 0 |
| Ideal ResidencyIdeal Builders & Developers | PM1270002600979 | 29 Jun 2026 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Jai Mata DiVraj Developers | PM1270002600681 | 8 Jun 2026 | 30 Nov 2026 | 30 Mar 2027 | Extended 4 mo | 0 |
| Siddhivinayak HorizonSiddhivinayak Builders & Developers | PM1270002501639 | 2 Dec 2025 | 31 Mar 2030 | 31 Jul 2030 | Extended 4 mo | 0 |
Other localities in Panvel
Most active promoters
By projects registered here, as named on MahaRERA.
- Ideal Builders & Developers1 project
- Shreepati Group1 project
- Siddhivinayak Builders & Developers1 project
- Vraj Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology