Skip to content
Others · 1 building · 14 unitsRERA P52000032775

Sai Sankalp

Deedo IDDP-RAI-B5Z2

Its promised completion date, Dec 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.

Pushapak, Raigarh 410206 · by Swaraj Developers

Delivery1 yr 11 mo past duePromised Dec 2024 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 14 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Dec 2024, has passed and MahaRERA does not show it completed

  • This projectRegistered 29 Jan 2022, completion promised 15 Dec 2024, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000032775
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200003277529 Jan 202215 Dec 202415 Dec 2024Swaraj DevelopersProject page
Documents19

1 document held by Deedo, 18 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan Card_Swaraj.pdf · uploaded 29 Dec 2021Source

Legal

  • Legal Title reportTitle_MahaRERA.pdf · uploaded 29 Dec 2021Source
  • Declaration Form BForm B Promoter Sai Sankalp_compressed.pdf · uploaded 29 Dec 2021Source

Migrated

  • 1 Copy of Layout Approval (in case of layout)plan.pdf · uploaded 21 Dec 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentplan.pdf · uploaded 21 Dec 2021Source
  • 1 PAN CardPan Card_Swaraj.pdf · uploaded 29 Dec 2021Source
  • 1 Copy of the legal title reportTitle_MahaRERA.pdf · uploaded 29 Dec 2021Source
Show all 19 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesSai Sankalp Encumbrance.pdf · uploaded 29 Dec 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentcc.pdf · uploaded 29 Dec 2021Source
  • 2 Commencement Certificates / NA Order for plotted developmentlatest cc.PDF · uploaded 29 Dec 2021Source
  • 1 Declaration about Commencement CertificateCircular 32 Sai Sankalp.pdf · uploaded 29 Dec 2021Source
  • 1 Declaration in FORM BForm B Promoter Sai Sankalp_compressed.pdf · uploaded 29 Dec 2021Source
  • 1 CERSAI detailsSai Sankalp.pdf · uploaded 29 Dec 2021Source
  • 1 Proforma of Allotment letterAgreement For Sale_Swaraj_Developers.pdf · uploaded 29 Dec 2021Source
  • 2 Proforma of Allotment letterAllotment Letter_Swaraj Developers.pdf · uploaded 29 Dec 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed Form 3 Sai Sankalp_compressed.pdf · uploaded 7 Jan 2022Source

Technical

  • Documentplan.pdf · uploaded 21 Dec 2021Source
  • Documentplan.pdf · uploaded 21 Dec 2021Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot No113

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, 2BHK, Multipurpose, Shop14 units in all
Address
Plot No-113, Sector-R2, Pushpak(New)PIN 410206
Village
Vadghar (CT), Panvel taluka
Land area for this project
200 sq m (2,151 sq ft)
Permissible built-up area
300 sq m (3,227 sq ft)
Sanctioned built-up area
300 sq m (3,227 sq ft)
Designated bank account
220
Developed in phases
No

Survey, CTS, gat or plot numbers

Plot No113

Land as published on MahaRERA's project page

Plot No-113

Boundaries

North
Plot No-131
South
9 M Wide Road
East
Plot No-114
West
Plot No-112

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking14 units

0 of 14 units booked (0%), as the promoter reported to MahaRERA

1BHK · 3 units1RK · 4 units2BHK · 3 unitsMultipurpose · 2 unitsShop · 2 units
TypeCarpet areaUnitsBooked
1BHK23.93 sq m · 258 sq ft30
1RK11.48 sq m · 124 sq ft10
1RK18.73 sq m · 202 sq ft30
2BHK26.79 sq m · 288 sq ft30
Multipurpose13.32 sq m · 143 sq ft10
Multipurpose13.48 sq m · 145 sq ft10
Shop4.85 sq m · 52 sq ft10
Shop5.31 sq m · 57 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPradnya Kishore—
Chartered accountantRutuja Narsingh and Associates—
EngineerB S Sukthankar—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology