Deedo IDDP-RAI-TSC7MahaRERA shows it completed; no MahaRERA orders on record; 0% of its units are booked.
Karanjade, Raigarh 410206 · by Shree Ganesh Builders & Developers · 50% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed
- This projectRegistered 24 Feb 2020, completion promised 20 May 2023.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000024604
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000024604 | 24 Feb 2020 | 20 May 2023 | 20 May 2023 | Shree Ganesh Builders & Developers | Project page |
Documents17
1 document held by Deedo, 16 filings listed on MahaRERA's project page
Finance
- PAN Carddownload.pdf · uploaded 12 Feb 2020Source
Legal
Migrated
- 1 Copy of the legal title reportTITLE.pdf · uploaded 31 Jan 2020Source
- 1 Details of encumbrancesself declaration.pdf · uploaded 31 Jan 2020Source
- 1 Copy of Layout Approval (in case of layout)CC DRG.pdf · uploaded 31 Jan 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentCC DRG.pdf · uploaded 31 Jan 2020Source
Show all 17 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentCC_compressed.pdf · uploaded 31 Jan 2020Source
- 1 Declaration in FORM Bform b new.pdf · uploaded 31 Jan 2020Source
- 1 Proforma of Allotment letterRERA AGREEMENT SALE AGREEMENT Plot 122 and 123 Karanjade-.pdf · uploaded 31 Jan 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A CERTIFICATE.pdf · uploaded 4 Feb 2020Source
- 1 PAN Carddownload.pdf · uploaded 12 Feb 2020Source
- 2 Proforma of Allotment letterallotment letter.pdf · uploaded 12 Feb 2020Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentoc 122123.pdf · uploaded 13 Feb 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 122, 123
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 1RK12 units in all
- Address
- 122, 123, Sector - 6, Karanjade PanvelPIN 410206
- Village
- Karanjade, Panvel taluka
- Land area for this project
- 199 sq m (2,139 sq ft)
- Permissible built-up area
- 298 sq m (3,209 sq ft)
- Sanctioned built-up area
- 298 sq m (3,209 sq ft)
- Designated bank account
- 35
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
122, 123
Boundaries
- North
- Plot No 135 136
- South
- 9 Metre Road
- East
- Plot No 121
- West
- Plot No 124
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking12 units
0 of 12 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 23.2 sq m · 250 sq ft | 2 | 0 |
| 1BHK | 26.17 sq m · 282 sq ft | 6 | 0 |
| 1RK | 11.76 sq m · 127 sq ft | 1 | 0 |
| 1RK | 15.89 sq m · 171 sq ft | 3 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Atul Patel | — |
| Chartered accountant | Keyur Bhayani | — |
| Engineer | Subramanya Rao | — |
| Other | Sharifur Rahman | — |
Source: MahaRERA project page. Contact details are not shown.