Aayushi Pride
Deedo IDDP-RAI-RX9EMahaRERA shows it completed; no MahaRERA orders on record; 73% of its units are booked.
Karanjade, Raigarh 410206 · by Aayushi Infracone Llp
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed
- This projectRegistered 3 Jan 2023, completion promised 31 Mar 2025.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000048520
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000048520 | 3 Jan 2023 | 31 Mar 2025 | 31 Mar 2025 | Aayushi Infracone LLP | Project page |
Documents88
2 documents held by Deedo, 86 filings listed on MahaRERA's project page
Show all 88 documentsShow fewer documents
Migrated
- 1 Building Plan Approval / NA Order for plotted development06 IOD.pdf · uploaded 21 Nov 2022Source
- 1 Commencement Certificates / NA Order for plotted development07 Comencement Certificate.pdf · uploaded 21 Nov 2022Source
- 1 CERSAI details18 No Finacial Interest CERSAI.pdf · uploaded 21 Nov 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)11 Form 2 Engineer Certificate.pdf · uploaded 24 Nov 2022Source
- 1 a Details of encumbrances concerned to Finance04 Details of Encumbrances - Legal.pdf · uploaded 25 Nov 2022Source
- 1 b Details of encumbrances concerned to Legal04 Details of Encumbrances - Legal.pdf · uploaded 25 Nov 2022Source
- 1 Declaration about Commencement Certificate08 Format D.pdf · uploaded 25 Nov 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)10 Form 1 Architect Certificate.pdf · uploaded 25 Nov 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)19 Form 3.pdf · uploaded 25 Nov 2022Source
- 1 Deviation Report with respect to Allotment letter35 Deviation Report with respect to Allotment letter.pdf · uploaded 25 Nov 2022Source
- 1 Proforma of Allotment letterLetter of Allotment.pdf · uploaded 6 Dec 2022Source
- 1 Deviation Report with respect to model copy of AgreementRERA Agreement_Deviation Report.pdf · uploaded 6 Dec 2022Source
- 1 Other – LegalPlot No 37 Tripartite.pdf · uploaded 6 Dec 2022Source
- 1 Declaration in FORM BFORM B - Promotor.pdf · uploaded 7 Dec 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.pdf · uploaded 7 Dec 2022Source
- 1 Proforma of Agreement for saleAgreement to Sale.pdf · uploaded 16 Dec 2022Source
- 1 Copy of the legal title reportLegal Title Report.pdf · uploaded 21 Dec 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 8 May 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 8 May 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 9 May 2023Source
- 1 Disclosure of sold/ booked inventorySoldUnsold.pdf · uploaded 9 Jun 2023View
- 2 Copy of Layout Approval (in case of layout)CIDCOBP-18106 DRAWING PDF.pdf · uploaded 26 Jul 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 MahaRERA.pdf · uploaded 7 Aug 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 8 Aug 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 18 Aug 2023Source
- 2 Disclosure of sold/ booked inventorySold Unsold inventory.pdf · uploaded 21 Aug 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 29 Aug 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5.pdf · uploaded 6 Sep 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q2Form1.pdf · uploaded 23 Oct 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q2Form2.pdf · uploaded 23 Oct 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q2Form3.pdf · uploaded 23 Oct 2023Source
- 3 Disclosure of sold/ booked inventoryQ2Soldunsold.pdf · uploaded 9 Nov 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q3Form1.pdf · uploaded 16 Jan 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q3Form2.pdf · uploaded 24 Jan 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q3Form3.pdf · uploaded 24 Jan 2024Source
- 4 Disclosure of sold/ booked inventoryQ3SoldUnsold.pdf · uploaded 11 Feb 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q4Form1.pdf · uploaded 16 Apr 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q4Form2.pdf · uploaded 2 May 2024Source
- 5 Disclosure of sold/ booked inventorySoldUnsold.pdf · uploaded 2 May 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q4Form3.pdf · uploaded 10 May 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q1Form1.pdf · uploaded 14 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q1Form2.pdf · uploaded 14 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q1Form3.pdf · uploaded 14 Oct 2024Source
- 1 Disclosure of sold/ booked inventorySold-Unsold.pdf · uploaded 14 Oct 2024View
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q1Form1.pdf · uploaded 14 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q1Form2.pdf · uploaded 14 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q1Form3.pdf · uploaded 14 Oct 2024Source
- 1 Disclosure of sold/ booked inventorySold-Unsold.pdf · uploaded 14 Oct 2024View
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q1Form1.pdf · uploaded 14 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q1Form3.pdf · uploaded 14 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q1Form2.pdf · uploaded 14 Oct 2024Source
- 2 Disclosure of sold/ booked inventorySold-Unsold.pdf · uploaded 14 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q2Form1.pdf · uploaded 30 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q2Form1.pdf · uploaded 30 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q2Form1.pdf · uploaded 30 Oct 2024Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOccupationCertificate.pdf · uploaded 6 Nov 2024Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOccupationCertificate.pdf · uploaded 6 Nov 2024Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOccupationCertificate.pdf · uploaded 6 Nov 2024Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 14 Nov 2024Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 16 Dec 2024Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 16 Dec 2024Source
- 2 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 16 Dec 2024Source
- 1 Disclosure of sold/ booked inventoryQ2SoldUnsold.pdf · uploaded 18 Feb 2025View
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form2A.pdf · uploaded 18 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form5.pdf · uploaded 18 Feb 2025Source
- Occupational CertificateOccupationCertificate.pdf · uploaded 20 Jun 2025Source
Technical
Technical (Architect)
- DocumentQ1Form1.pdf · uploaded 11 Sep 2024Source
- DocumentQ1Form1.pdf · uploaded 14 Oct 2024Source
- DocumentQ1Form1.pdf · uploaded 14 Oct 2024Source
- DocumentQ1Form1.pdf · uploaded 14 Oct 2024Source
- DocumentQ2Form1.pdf · uploaded 30 Oct 2024Source
- DocumentQ2Form1.pdf · uploaded 30 Oct 2024Source
- DocumentQ2Form1.pdf · uploaded 30 Oct 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Plot No 37
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, Shop45 units in all
- Address
- Plot No 37, Sector 4, KaranjadePIN 410206
- Village
- Karanjade, Panvel taluka
- Location
- 18.97557, 73.10727
- Land area for this project
- 650 sq m (6,996 sq ft)
- Permissible built-up area
- 2,023 sq m (21,773 sq ft)
- Sanctioned built-up area
- 2,023 sq m (21,773 sq ft)
- Designated bank account
- 109
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Plot No 37
Boundaries
- North
- 15 Mtr Wide Road
- South
- Plot No 22
- East
- Plot No 36
- West
- Plot No 21
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking45 units
33 of 45 units booked (73%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 25.6 sq m · 276 sq ft | 2 | 0 |
| 1BHK | 25.61 sq m · 276 sq ft | 2 | 0 |
| 1BHK | 25.68 sq m · 276 sq ft | 2 | 0 |
| 1BHK | 27.71 sq m · 298 sq ft | 1 | 1 |
| 1BHK | 28.56 sq m · 307 sq ft | 1 | 1 |
| 1BHK | 29.84 sq m · 321 sq ft | 5 | 1 |
| 1BHK | 29.86 sq m · 321 sq ft | 5 | 5 |
| 1BHK | 29.93 sq m · 322 sq ft | 5 | 5 |
Show all 15 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 29.95 sq m · 322 sq ft | 1 | 1 |
| 1BHK | 29.98 sq m · 323 sq ft | 5 | 5 |
| 1BHK | 31.78 sq m · 342 sq ft | 7 | 7 |
| 1BHK | 32.2 sq m · 347 sq ft | 5 | 5 |
| Shop | 16.63 sq m · 179 sq ft | 1 | 1 |
| Shop | 18.08 sq m · 195 sq ft | 2 | 0 |
| Shop | 19.42 sq m · 209 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.