Residential / Group Housing · 1 building · 28 unitsRERA P52000055179

Sai Prathamesh

Deedo IDDP-RAI-FKPQ

Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 0% of its units are booked.

Dapoli, Raigarh 410206 · by Vaijanti Anil Mhatre

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 28 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 11 Mar 2024, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000055179
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200005517911 Mar 202431 Dec 202630 Apr 2027Vaijanti Anil MhatreProject page
Documents110

1 document held by Deedo, 109 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN.pdf · uploaded 20 Jan 2024Source

Legal

  • Declaration Form BFORM B VAIJANTI A MHATRE.pdf · uploaded 20 Jan 2024Source
  • Other – LegalDEED OF RECTIFICATION.pdf · uploaded 13 Feb 2024Source
  • Other – LegalTrparty.pdf · uploaded 13 Feb 2024Source
  • Legal Title reportTitle Search Report.pdf · uploaded 13 Feb 2024Source
  • Other – LegalLEASE AGREEMENT.pdf · uploaded 24 Feb 2024Source

Migrated

  • 1 PAN CardPAN.pdf · uploaded 20 Jan 2024Source
Show all 110 documentsShow fewer documents

Migrated

  • 1 a Details of encumbrances concerned to FinanceENCUMBRANCES FINANCE.pdf · uploaded 20 Jan 2024Source
  • 2 a Details of encumbrances concerned to FinanceENCUMBRANCES LEGAL.pdf · uploaded 20 Jan 2024Source
  • 1 b Details of encumbrances concerned to LegalENCUMBRANCES FINANCE.pdf · uploaded 20 Jan 2024Source
  • 2 b Details of encumbrances concerned to LegalENCUMBRANCES LEGAL.pdf · uploaded 20 Jan 2024Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN.pdf · uploaded 20 Jan 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentBUILDING PLAN.pdf · uploaded 20 Jan 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC COPY.pdf · uploaded 20 Jan 2024Source
  • 1 Declaration in FORM BFORM B VAIJANTI A MHATRE.pdf · uploaded 20 Jan 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 20 Jan 2024Source
  • 1 CERSAI detailsCERSAI DECLARATION.pdf · uploaded 20 Jan 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 SANJIVANI ENTERPRISES.pdf · uploaded 20 Jan 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDECLARATION ABOUT SEPARATE BANK ACCOUNT.pdf · uploaded 20 Jan 2024Source
  • 1 Deviation Report with respect to Allotment letterDEVIATION REPORT ALLOTMENT LETTER.pdf · uploaded 20 Jan 2024Source
  • 1 Copy of the legal title reportTitle Search Report.pdf · uploaded 13 Feb 2024Source
  • 1 Declaration about Commencement CertificateDECLARATION ABOUT CC.pdf · uploaded 13 Feb 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDICLOSURE OF INTEREST.pdf · uploaded 13 Feb 2024Source
  • 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 13 Feb 2024Source
  • 1 Other – LegalDEED OF RECTIFICATION.pdf · uploaded 13 Feb 2024Source
  • 2 Other – LegalTrparty.pdf · uploaded 13 Feb 2024Source
  • 1 Other – TechnicalDECLARATION CUM UNDERTAKING.pdf · uploaded 13 Feb 2024Source
  • 3 Other – LegalLEASE AGREEMENT.pdf · uploaded 24 Feb 2024Source
  • 1 Proforma of Agreement for saleAGREEMENT FOR SALE.pdf · uploaded 4 Mar 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION REPORT AGREEMENT.pdf · uploaded 4 Mar 2024Source
  • 2 Other – TechnicalFwd_ Development permission_CC granted by CIDCO.pdf · uploaded 4 Mar 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1.pdf · uploaded 21 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)SANJIVANI ENTERPRISES FORM 1.pdf · uploaded 21 Nov 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentACC COPY.pdf · uploaded 21 Nov 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)SANJIVANI ENTERPRISES FORM 2.pdf · uploaded 21 Nov 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1.pdf · uploaded 21 Nov 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)SANJIVANI ENTERPRISES FORM 1.pdf · uploaded 21 Nov 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)SANJIVANI ENTERPRISES FORM 2.pdf · uploaded 21 Nov 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentACC COPY.pdf · uploaded 21 Nov 2024Source
  • 1 Copy of Layout Approval (in case of layout)CC DWG.pdf · uploaded 7 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 SANJIVANI ENTERPRISES.pdf · uploaded 7 Jan 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentCC DWG.pdf · uploaded 7 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 MARCH 24.pdf · uploaded 3 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 JUN24.pdf · uploaded 3 Feb 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 SEP 24.pdf · uploaded 3 Feb 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 JUN 24.pdf · uploaded 3 Feb 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 SEP 24.pdf · uploaded 3 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 MAR 24.pdf · uploaded 3 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 MAR 24.pdf · uploaded 3 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 JUN 24.pdf · uploaded 3 Feb 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 SEP 24.pdf · uploaded 3 Feb 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsFORM 3 SEP 24.pdf · uploaded 3 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 DEC 24.pdf · uploaded 5 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 DEC 24.pdf · uploaded 5 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 DEC 24.pdf · uploaded 5 Mar 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5.pdf · uploaded 29 Mar 2025Source
  • Form 1FORM 1 MAR 24.pdf · uploaded 30 Jun 2025Source
  • Form 2FORM 2 MAR 24.pdf · uploaded 30 Jun 2025Source
  • Form 3FORM 3 MAR 24.pdf · uploaded 30 Jun 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD MAR 24.pdf · uploaded 30 Jun 2025Source
  • Form 1FORM 1 JUN24.pdf · uploaded 30 Jun 2025Source
  • Form 2FORM 2 JUN 24.pdf · uploaded 30 Jun 2025Source
  • Form 3FORM 3 JUN 24.pdf · uploaded 30 Jun 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD JUN 24.pdf · uploaded 30 Jun 2025Source
  • Form 1FORM 1 SEP 24.pdf · uploaded 30 Jun 2025Source
  • Form 2FORM 2 SEP 24.pdf · uploaded 30 Jun 2025Source
  • Form 3FORM 3 SEP 24.pdf · uploaded 30 Jun 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD SEPT 24.pdf · uploaded 30 Jun 2025Source
  • Form 1FORM 1 DEC 24.pdf · uploaded 30 Jun 2025Source
  • Form 2FORM 2 DEC 24.pdf · uploaded 30 Jun 2025Source
  • Form 3FORM 3 DEC 24.pdf · uploaded 30 Jun 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD DEC 24.pdf · uploaded 30 Jun 2025Source
  • Form 1FORM 1 MAR 25.pdf · uploaded 30 Jun 2025Source
  • Form 2FORM 2 MAR 25.pdf · uploaded 30 Jun 2025Source
  • Form 3FORM 3 MAR 25.pdf · uploaded 30 Jun 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD MAR 25.pdf · uploaded 30 Jun 2025Source
  • Withdrawal Update Form 1FORM 1 JUN 25.pdf · uploaded 29 Aug 2025Source
  • Withdrawal Update Form 2FORM 2 JUN 25.pdf · uploaded 29 Aug 2025Source
  • Withdrawal Update Form 3FORM 3 JUN 25.pdf · uploaded 29 Aug 2025Source
  • Withdrawal Update Form 1FORM 1 SEPT 25.pdf · uploaded 14 Feb 2026Source
  • Withdrawal Update Form 1FORM 1 DEC 25.pdf · uploaded 14 Feb 2026Source
  • Withdrawal Update Form 2FORM 2 SEPT 25.pdf · uploaded 14 Feb 2026Source
  • Withdrawal Update Form 2FORM 2 DEC 25.pdf · uploaded 14 Feb 2026Source
  • Withdrawal Update Form 3FORM 3 SEPT 25.pdf · uploaded 14 Feb 2026Source
  • Withdrawal Update Form 3FORM 3 DEC 25.pdf · uploaded 14 Feb 2026Source
  • Withdrawal Update Form 1FORM 1 MAR 26.pdf · uploaded 9 Jun 2026Source
  • Withdrawal Update Form 2FORM 2 MAR 26.pdf · uploaded 9 Jun 2026Source
  • Withdrawal Update Form 3FORM 3 MAR 26.pdf · uploaded 9 Jun 2026Source

Technical

  • DocumentLAYOUT PLAN.pdf · uploaded 20 Jan 2024Source
  • DocumentBUILDING PLAN.pdf · uploaded 20 Jan 2024Source
  • Other – TechnicalDECLARATION CUM UNDERTAKING.pdf · uploaded 13 Feb 2024Source
  • Other – TechnicalFwd_ Development permission_CC granted by CIDCO.pdf · uploaded 4 Mar 2024Source
  • DocumentCC DWG.pdf · uploaded 7 Jan 2025Source
  • DocumentCC DWG.pdf · uploaded 7 Jan 2025Source

Technical (Architect)

  • DocumentSANJIVANI ENTERPRISES FORM 1.pdf · uploaded 21 Nov 2024Source
  • DocumentFORM-1.pdf · uploaded 21 Nov 2024Source
  • DocumentSANJIVANI ENTERPRISES FORM 1.pdf · uploaded 21 Nov 2024Source
  • DocumentFORM 1 MARCH 24.pdf · uploaded 3 Feb 2025Source
  • DocumentFORM 1 JUN24.pdf · uploaded 3 Feb 2025Source
  • DocumentFORM 1 SEP 24.pdf · uploaded 3 Feb 2025Source
  • DocumentFORM 1 DEC 24.pdf · uploaded 5 Mar 2025Source
  • DocumentFORM 1 MAR 26.pdf · uploaded 9 Jun 2026Source

Technical (Engineer)

  • DocumentSANJIVANI ENTERPRISES FORM 2.pdf · uploaded 21 Nov 2024Source
  • DocumentSANJIVANI ENTERPRISES FORM 2.pdf · uploaded 21 Nov 2024Source
  • DocumentFORM 2 MAR 24.pdf · uploaded 3 Feb 2025Source
  • DocumentFORM 2 JUN 24.pdf · uploaded 3 Feb 2025Source
  • DocumentFORM 2 SEP 24.pdf · uploaded 3 Feb 2025Source
  • DocumentFORM 2 DEC 24.pdf · uploaded 5 Mar 2025Source
  • DocumentFORM 2 MAR 26.pdf · uploaded 9 Jun 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel PLOT NO 380 SECTOR 03

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK28 units in all
Address
Plot No 380 Sector 03, Plot No 380 Sector 03, Pushpak NodePIN 410206
Village
Dapoli, Panvel taluka
Land area for this project
380 sq m (4,088 sq ft)
Permissible built-up area
1,379 sq m (14,846 sq ft)
Sanctioned built-up area
1,379 sq m (14,846 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
148
Developed in phases
No

Survey, CTS, gat or plot numbers

PLOT NO 380 SECTOR 03

Land as published on MahaRERA's project page

PLOT NO 380 SECTOR 03

Boundaries

North
15 Mtrs Wide Road
South
Plot No 360
East
Plot No 381
West
Plot No 379

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking28 units

0 of 28 units booked (0%), as the promoter reported to MahaRERA

1BHK · 28 units
TypeCarpet areaUnitsBooked
1BHK26.39 sq m · 284 sq ft20
1BHK28.39 sq m · 306 sq ft120
1BHK29.07 sq m · 313 sq ft140

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDestination Architecture Interior Designs—
Chartered accountantR V Thakkar & Associates—
EngineerVastukalp Architect—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology