RERA projects in Chinchpada
7 projects under 7 MahaRERA registrations, registered 2017–2020. None has an extended completion date on record.
Locality
7RERA projects
7Registrations
0Completion still due7 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
7Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 2 |
| 2019 | 3 |
| 2020 | 1 |
Projects in Chinchpada
7 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Shiv GalaxyBhagwan Maya Bhoir | P52000024583 | 24 Feb 2020 | 30 Mar 2024 | 30 Mar 2024 | Promised date passed | 0 |
| NandiniNandini Enterprises | P52000022031 | 25 Aug 2019 | 30 Dec 2022 | 30 Dec 2022 | Promised date passed | 0 |
| Shree Deep EnterprisesAmbibai Bharat Gavand | P52000021101 | 31 May 2019 | 30 Jun 2023 | 30 Jun 2023 | Promised date passed | 0 |
| Sunrise SevenSunrise Builders And Developers | P52000020814 | 10 May 2019 | 1 Sep 2022 | 1 Sep 2022 | Promised date passed | 0 |
| Shiv ResidencyVikas Mirya Pardeshi | P52000016793 | 12 Jun 2018 | 30 Mar 2021 | 30 Mar 2021 | Promised date passed | 0 |
| Joma Keni ResidencyPralhad Joma Keni | P52000015292 | 15 Feb 2018 | 30 Mar 2022 | 30 Mar 2022 | Promised date passed | 0 |
| Savitri NiwasRamesh Gulab Tupe | P52000011962 | 1 Sep 2017 | 31 Mar 2018 | 31 Mar 2018 | Promised date passed | 0 |
Other localities in Panvel
Most active promoters
By projects registered here, as named on MahaRERA.
- Ambibai Bharat Gavand1 project
- Bhagwan Maya Bhoir1 project
- Nandini Enterprises1 project
- Pralhad Joma Keni1 project
- Ramesh Gulab Tupe1 project
- Sunrise Builders And Developers1 project
- Vikas Mirya Pardeshi1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology