Ambeghar, Raigarh
5 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects4
Registrations4
Completion still due22 past their date
Median extension4 months50% of registrations extended
Regulatory cases0none on MahaRERA's lists
Projects in Ambeghar
4 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Mrudagandhar Phase 3 Rageshree D Type BuildingThe United Group Of Builders And Developers | P52000079172 | 12 Feb 2025 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Mrudagandhar Phase 2 Devashree E type BuildingThe United Group Of Builders And Developers | P52000028928 | 15 Apr 2021 | 31 Mar 2024 | 31 Mar 2024 | Promised date passed | 0 |
| Tarun Plantations CompanyTarun Plantations Company | P52000014149 | 9 Nov 2017 | 31 Mar 2027 | 31 Jul 2027 | Extended 4 mo | 0 |
| Mrudagandhar Phase 1The United Group Of Builders And Developers | P52000000998 | 25 Jul 2017 | 30 Mar 2022 | 30 Mar 2022 | Promised date passed | 0 |
Nearby: other localities in Pen
Most active promoters
- The United Group Of Builders And Developers3 projects
- Tarun Plantations Company1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology