Ambeghar, Raigarh

5 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects4
Registrations4
Completion still due22 past their date
Median extension4 months50% of registrations extended
Regulatory cases0none on MahaRERA's lists
Ambeghar market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Projects in Ambeghar

4 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Mrudagandhar Phase 3 Rageshree D Type BuildingThe United Group Of Builders And DevelopersP5200007917212 Feb 202531 Dec 202730 Apr 2028Extended 4 mo0
Mrudagandhar Phase 2 Devashree E type BuildingThe United Group Of Builders And DevelopersP5200002892815 Apr 202131 Mar 202431 Mar 2024Promised date passed0
Tarun Plantations CompanyTarun Plantations CompanyP520000141499 Nov 201731 Mar 202731 Jul 2027Extended 4 mo0
Mrudagandhar Phase 1The United Group Of Builders And DevelopersP5200000099825 Jul 201730 Mar 202230 Mar 2022Promised date passed0

Most active promoters

  1. The United Group Of Builders And Developers3 projects
  2. Tarun Plantations Company1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology