Others · 1 building · 33 unitsRERA P52100049391

Weone 121

Deedo IDDP-PUN-VWZZ

Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 70% of its units are booked.

Wakad, Pune 411057 · Promoter: Grd Infraprojects Private Limited

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales70% booked23 of 33 units · as the promoter reported to MahaRERA
Weone 121 project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 7 Feb 2023, completion promised 31 Dec 2026, revised to 30 Apr 2027.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100049391
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000493917 Feb 202331 Dec 202630 Apr 2027Grd Infraprojects Private LimitedProject page
Documents119

2 documents held by Deedo, 117 filings listed on MahaRERA's project page

Extension certificate

Registration certificate

Finance

  • PAN Cardpan card of GRD.pdf · uploaded 7 Dec 2022Source

Legal

  • Declaration Form BPromoter Declaration (1).pdf · uploaded 7 Dec 2022Source
  • Legal Title reportSearch Of GRD dt.pdf · uploaded 5 Jan 2023Source
  • Other – LegalRERA Declaration of Weone 121.pdf · uploaded 16 Jan 2023Source

Migrated

  • 1 PAN Cardpan card of GRD.pdf · uploaded 7 Dec 2022Source
  • 1 Copy of Layout Approval (in case of layout)Sanction Plan No I_compressed.pdf · uploaded 7 Dec 2022Source
Show all 119 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval / NA Order for plotted developmentSanction Plan No II_compressed.pdf · uploaded 7 Dec 2022Source
  • 2 Building Plan Approval / NA Order for plotted developmentSanction Plan No III_compressed.pdf · uploaded 7 Dec 2022Source
  • 3 Building Plan Approval / NA Order for plotted developmentSanction Plan No IV_compressed.pdf · uploaded 7 Dec 2022Source
  • 4 Building Plan Approval / NA Order for plotted developmentSanction Plan No V_compressed.pdf · uploaded 7 Dec 2022Source
  • 5 Building Plan Approval / NA Order for plotted developmentSanction Plan No VI_compressed.pdf · uploaded 7 Dec 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC (2).pdf · uploaded 7 Dec 2022Source
  • 1 Declaration about Commencement CertificateCommencement declaration (Format D).pdf · uploaded 7 Dec 2022Source
  • 1 Declaration in FORM BPromoter Declaration (1).pdf · uploaded 7 Dec 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate (8).pdf · uploaded 7 Dec 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Form 2.pdf · uploaded 7 Dec 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration for Bank account Format A.pdf · uploaded 7 Dec 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA form 3 (1).pdf · uploaded 9 Dec 2022Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure-A Gaurav Attarde.pdf · uploaded 4 Jan 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsAnnexure-A Devidas Attarde.pdf · uploaded 4 Jan 2023Source
  • 1 Proforma of Allotment letterAllotment Letter as per rera.pdf · uploaded 4 Jan 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation Report of Allotment Letter.pdf · uploaded 4 Jan 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report of Agreement to Sale.pdf · uploaded 4 Jan 2023Source
  • 1 Copy of the legal title reportSearch Of GRD dt.pdf · uploaded 5 Jan 2023Source
  • 1 a Details of encumbrances concerned to Finance1 a Details of legal encumbrances concerned to.pdf · uploaded 5 Jan 2023Source
  • 2 a Details of encumbrances concerned to Finance2 b Details of encumbrances concerned to finance.pdf · uploaded 5 Jan 2023Source
  • 1 b Details of encumbrances concerned to Legal1 a Details of legal encumbrances concerned to.pdf · uploaded 5 Jan 2023Source
  • 2 b Details of encumbrances concerned to Legal2 b Details of encumbrances concerned to finance.pdf · uploaded 5 Jan 2023Source
  • 1 CERSAI detailsGRD revised CERSAI Search Report.pdf · uploaded 5 Jan 2023Source
  • 1 Proforma of Agreement for sale1 Proforma of Agreement for sale_compressed.pdf · uploaded 13 Jan 2023Source
  • 1 Other – LegalRERA Declaration of Weone 121.pdf · uploaded 16 Jan 2023Source
  • 6 Building Plan Approval / NA Order for plotted developmentPlan No 1.pdf · uploaded 27 May 2023Source
  • 7 Building Plan Approval / NA Order for plotted developmentPlan No 2.pdf · uploaded 27 May 2023Source
  • 8 Building Plan Approval / NA Order for plotted developmentPlan No 3.pdf · uploaded 27 May 2023Source
  • 9 Building Plan Approval / NA Order for plotted developmentPlan No 4.pdf · uploaded 27 May 2023Source
  • 10 Building Plan Approval / NA Order for plotted developmentPlan No 5.pdf · uploaded 27 May 2023Source
  • 11 Building Plan Approval / NA Order for plotted developmentPlan No 6.pdf · uploaded 27 May 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentCommencement Certificate Dated 23-05-2023.pdf · uploaded 27 May 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate (W 121) Q4.pdf · uploaded 7 Jun 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer certificate form 2 Weone 121 Q4.pdf · uploaded 7 Jun 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Engineer certificate - Form 2A (FY 2022-23) W 121.pdf · uploaded 7 Jun 2023Source
  • 1 Disclosure of sold/ booked inventoryPromoter Disclosure - W121 Q4.pdf · uploaded 7 Jun 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate - WEONE- 121 Q4.pdf · uploaded 7 Jun 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Form 1 Q1.pdf · uploaded 2 Aug 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Form 2 W 121.pdf · uploaded 2 Aug 2023Source
  • 2 Disclosure of sold/ booked inventoryPromoter Disclosure Q1 W 121.pdf · uploaded 2 Aug 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate - WEONE- 121 Q1.pdf · uploaded 2 Aug 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)2A.pdf · uploaded 21 Aug 2023Source
  • 2 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A-Declaration for separate bank account (2).pdf · uploaded 13 Sep 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Weone 121 RERA quarterly update Architect Certificate - Form 1 30-09-2023.pdf · uploaded 9 Nov 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers certificate - Form 2 Weone 121 Dt 30-09-2023.pdf · uploaded 9 Nov 2023Source
  • 3 Disclosure of sold/ booked inventoryWeone 121 Dicloser List Sold and unsold Dt 30-09-2023.pdf · uploaded 9 Nov 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form3 -Q2 Weone 121.pdf · uploaded 9 Nov 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Annual Audit Signed (W121) FY 22-23.pdf · uploaded 14 Feb 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Weone 121 Q3 2023-24.pdf · uploaded 6 Mar 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Weone 121 Form 2 Engineer Certificate Q3.pdf · uploaded 6 Mar 2024Source
  • 4 Disclosure of sold/ booked inventoryPromoters Disclosure unit wise Weone 121 Q3.pdf · uploaded 6 Mar 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form3 CA Certificate Weone 121 FY 23-24 Q3.pdf · uploaded 6 Mar 2024Source
  • 2 CERSAI detailsCERSAI GRD Search Report.PDF · uploaded 5 Apr 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY 23-24 Q4 W121.pdf · uploaded 20 May 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 FY 23-24 Q4 W-121.pdf · uploaded 20 May 2024Source
  • 5 Disclosure of sold/ booked inventoryPromoter Disclosure W-121 Q4.pdf · uploaded 20 May 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3FY 23-24 Q-121.pdf · uploaded 27 May 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)WO 121 Form 1.pdf · uploaded 25 Jul 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)WO 121 Form 2.pdf · uploaded 25 Jul 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 2024-25 Q1 W-121.pdf · uploaded 25 Jul 2024Source
  • 6 Disclosure of sold/ booked inventoryPromoter Disclosure FY 24-25 Q1.pdf · uploaded 6 Aug 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate Weone 121.pdf · uploaded 20 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Signed Form 1.pdf · uploaded 20 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed Form 3.pdf · uploaded 20 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q 3 2024-25 WO 121.pdf · uploaded 20 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Signed Form 2.pdf · uploaded 20 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engg Certificate WO 121 Q3.pdf · uploaded 20 Feb 2025Source
  • Form 1Form 1.pdf · uploaded 11 Jun 2025Source
  • Form 2Form 2.pdf · uploaded 11 Jun 2025Source
  • Form 3form 3.pdf · uploaded 11 Jun 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD.pdf · uploaded 11 Jun 2025Source
  • Self-declaration of Quarterly Progressdelcartion self.pdf · uploaded 11 Jun 2025Source
  • Form 5 (FY 2024-2025)FORM 5 121 24 25.pdf · uploaded 23 Dec 2025Source
  • Withdrawal Update Form 1121 Form 1 JULY TO SEP.pdf · uploaded 29 Mar 2026Source
  • Withdrawal Update Form 2121 Form 2 JULY TO SEP.pdf · uploaded 29 Mar 2026Source
  • Withdrawal Update Form 3WO 121 Form 3 JULY TO SEP.pdf · uploaded 29 Mar 2026Source
  • Withdrawal Update Form 1Q 3 form 1 121 .pdf · uploaded 1 Apr 2026Source
  • Withdrawal Update Form 2Q 3 FORM 2 121.pdf · uploaded 1 Apr 2026Source
  • Withdrawal Update Form 3Q3 -2025 Weone 121 - .pdf · uploaded 1 Apr 2026Source
  • Form 2A (FY 2024-2025)FORM 2A 2024-2025 GRD 121.pdf · uploaded 1 May 2026Source
  • Form 2A (FY 2025-2026)FORM 2A 2025-2026 GRD 121.pdf · uploaded 1 May 2026Source
  • Withdrawal Update Form 1Weone 121 - Form 1 FY25-26 Q4_page-0001 (1).pdf · uploaded 10 May 2026Source
  • Withdrawal Update Form 2Weone 121 Form 2 FY25-26 Q4_page-0002.pdf · uploaded 10 May 2026Source
  • Withdrawal Update Form 3Form 3 - Weone 121.pdf · uploaded 10 May 2026Source
  • Withdrawal Update Form 1Weone 121 Form 1.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 2Form 2 - Weone 121.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 3F 3 - WEONE 121_compressed.pdf · uploaded 27 Jul 2026Source

Technical

  • DocumentSanction Plan No I_compressed.pdf · uploaded 7 Dec 2022Source
  • DocumentSanction Plan No II_compressed.pdf · uploaded 7 Dec 2022Source
  • DocumentSanction Plan No III_compressed.pdf · uploaded 7 Dec 2022Source
  • DocumentSanction Plan No IV_compressed.pdf · uploaded 7 Dec 2022Source
  • DocumentSanction Plan No V_compressed.pdf · uploaded 7 Dec 2022Source
  • DocumentSanction Plan No VI_compressed.pdf · uploaded 7 Dec 2022Source
  • DocumentPlan No 1.pdf · uploaded 27 May 2023Source
  • DocumentPlan No 2.pdf · uploaded 27 May 2023Source
  • DocumentPlan No 3.pdf · uploaded 27 May 2023Source
  • DocumentPlan No 4.pdf · uploaded 27 May 2023Source
  • DocumentPlan No 5.pdf · uploaded 27 May 2023Source
  • DocumentPlan No 6.pdf · uploaded 27 May 2023Source
  • DocumentPLAN 1 .pdf · uploaded 1 Apr 2026Source
  • DocumentPLAN 2.pdf · uploaded 1 Apr 2026Source
  • DocumentPLAN 3.pdf · uploaded 1 Apr 2026Source
  • DocumentPLAN 4.pdf · uploaded 1 Apr 2026Source
  • DocumentPLAN 5.pdf · uploaded 1 Apr 2026Source
  • DocumentPLAN 6.pdf · uploaded 1 Apr 2026Source

Technical (Architect)

  • DocumentArchitect's Certificate Weone 121.pdf · uploaded 20 Feb 2025Source
  • DocumentSigned Form 1.pdf · uploaded 20 Feb 2025Source
  • DocumentWeone 121 Form 1.pdf · uploaded 27 Jul 2026Source

Technical (Engineer)

  • DocumentSigned Form 2.pdf · uploaded 20 Feb 2025Source
  • DocumentForm 2 Engg Certificate WO 121 Q3.pdf · uploaded 20 Feb 2025Source
  • DocumentForm 2 - Weone 121.pdf · uploaded 27 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals121/2/2, 121/2/4/1

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
Room, Showroom33 units in all
Address
Survey No. 121/2/1, 121/2/2, 121/2/4/1, 121/2/5/1PIN 411057
Village
Wakad, Mulshi taluka
Designated bank account
119
Developed in phases
No

Survey, CTS, gat or plot numbers

121/2/2121/2/4/1121/2/5/1SURVEY NO. 121/2/1

Boundaries

North
By A Building Of Existing Projects
South
By 45 Mtr Wide Road
East
By S No 121 P
West
By 9 Mtr Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking33 units

23 of 33 units booked (70%), as the promoter reported to MahaRERA

Room · 32 unitsShowroom · 1 unit
TypeCarpet areaUnitsBooked
Room11.33 sq m · 122 sq ft33
Room12.46 sq m · 134 sq ft33
Room17.26 sq m · 186 sq ft105
Room17.35 sq m · 187 sq ft106
Room17.5 sq m · 188 sq ft33
Room17.66 sq m · 190 sq ft33
Showroom128.13 sq m · 1,379 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals7

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDesign Associates Architectural Consultants—
Chartered accountantSnehal G Patil—
Chartered accountantV S A P & Company—
EngineerANIL Bawaskar—
EngineerPranav Manoj Khalate—
EngineerSuhel Abbas Patel—
OtherBALAJI CONSTURCTIONS Hanumant Datkhile—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology