Manor Crystal
Completion was pushed back 4 months, to Jan 2027; no MahaRERA orders on record; 31% of its units are booked.
Wakad, Pune 411057 · Promoter: Oxford Infra Group
Completion was pushed back 4 months, to Jan 2027
- This projectRegistered 25 Mar 2019, completion promised 30 Sep 2026, revised to 30 Jan 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100020056
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100020056 | 25 Mar 2019 | 30 Sep 2026 | 30 Jan 2027 | Oxford Infra Group | Project page |
Documents308
1 document held by Deedo, 307 filings listed on MahaRERA's project page
Finance
- PAN Card1.pdf · uploaded 2 Jan 2024Source
Legal
- Declaration Form BForm 3B Amar Bhumkar.pdf · uploaded 5 Mar 2019Source
- Otherallottment letter.pdf · uploaded 18 Mar 2019Source
- Legal Title reportSEARCH AND TITLE REPORT.pdf · uploaded 18 Mar 2019Source
- OtherGetUserDocumentFileContent.pdf · uploaded 11 Mar 2024Source
- OtherPIMPRI CHINCHWAD MUNICIPAL CORPORATION Mail - Commencement Certificate Verification For Application No - EXT52100017660.pdf · uploaded 11 Mar 2024Source
- Declaration Form Baffidavit manor crystal.pdf · uploaded 22 Mar 2024Source
Show all 308 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)layout plan_converted_compressed.pdf · uploaded 27 Feb 2019Source
- 1 Building Plan Approval (IOD)Building Plan_converted.pdf · uploaded 27 Feb 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentcommencement copy.pdf · uploaded 27 Feb 2019Source
- 1 Details of encumbrancesNIL LITIGATION OXFORD INFRA GR 2.pdf · uploaded 5 Mar 2019Source
- 1 Declaration in FORM BForm 3B Amar Bhumkar.pdf · uploaded 5 Mar 2019Source
- 1 Copy of the legal title reportSEARCH AND TITLE REPORT.pdf · uploaded 18 Mar 2019Source
- 1 Certificates of CA (Form 3)rear oxford CA CERT.pdf · uploaded 18 Mar 2019Source
- 1 Proforma of Allotment letter137-2-2 RERA Agreement-18thMarch2019 final.pdf · uploaded 18 Mar 2019Source
- 1 Otherallottment letter.pdf · uploaded 18 Mar 2019Source
- 2 a Details of encumbrances concerned to FinanceEncumbrance certificate Finance .pdf · uploaded 16 Dec 2023Source
- 1 b Details of encumbrances concerned to LegalEncumbrance certificate Finance .pdf · uploaded 16 Dec 2023Source
- 2 Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 16 Dec 2023Source
- 2 Commencement Certificates / NA Order for plotted developmentREVISED CC.pdf · uploaded 16 Dec 2023Source
- 1 Declaration about Commencement CertificateDeclaration about commencement certificate 2023.pdf · uploaded 16 Dec 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)00000026-2020crystal Architect certificate Unusual Spaces sutar sir.pdf · uploaded 16 Dec 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)00000025-2021crystal Architect certificate Unusual Spaces sutar sir.pdf · uploaded 16 Dec 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)00000024-2022 crystal Architect certificate Unusual Spaces.pdf · uploaded 16 Dec 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)00000023-2023 crystal Architect Unusual Spaces.pdf · uploaded 16 Dec 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)00000036-Rera Crystal form-2A Engineer certificate.pdf · uploaded 16 Dec 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)00000029-crystal Rera form 2-A 2020 engineer quality Assurance.pdf · uploaded 16 Dec 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)00000028-crystal Rera form 2-A 2021 engineer quality Assurance.pdf · uploaded 16 Dec 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)00000027-crystal Rera form 2-A 2022 engineer quality Assurance.pdf · uploaded 16 Dec 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)00000030-crystal Rera form 2-A 2023 engineer quality Assurance.pdf · uploaded 16 Dec 2023Source
- 1 CERSAI detailsself declaration regarding non applicability CERSAI.pdf · uploaded 16 Dec 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of interest in other real estate.pdf · uploaded 16 Dec 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of interest in other real estat.pdf · uploaded 16 Dec 2023Source
- 1 Deviation Report with respect to Allotment letterDeviation Report allotments letter.pdf · uploaded 16 Dec 2023Source
- 1 Deviation Report with respect to model copy of AgreementDeviation Agreement to sale 2023.pdf · uploaded 16 Dec 2023Source
- 1 PAN Card1.pdf · uploaded 2 Jan 2024Source
- 1 Disclosure of sold/ booked inventoryRera crystal disclosure sold inventory 1.pdf · uploaded 2 Jan 2024Source
- 2 Proforma of Allotment letter1 Other.pdf · uploaded 2 Jan 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSEPERATE BANK.pdf · uploaded 2 Jan 2024Source
- 2 OtherGetUserDocumentFileContent.pdf · uploaded 11 Mar 2024Source
- 3 OtherPIMPRI CHINCHWAD MUNICIPAL CORPORATION Mail - Commencement Certificate Verification For Application No - EXT52100017660.pdf · uploaded 11 Mar 2024Source
- 1 Other – TechnicalPIMPRI CHINCHWAD MUNICIPAL CORPORATION Mail - Commencement Certificate Verification For Application No - EXT52100017660.pdf · uploaded 11 Mar 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Crystal Architect Certificate 8 Feb 2024.pdf · uploaded 12 Mar 2024Source
- 2 Disclosure of sold/ booked inventoryRera.pdf · uploaded 12 Mar 2024Source
- 2 Certificates of CA (Form 3)FORM3_11zon.pdf · uploaded 12 Mar 2024Source
- 2 Declaration in FORM Baffidavit manor crystal.pdf · uploaded 22 Mar 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 2020-jan to march-merged_compressed.pdf · uploaded 3 Apr 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 2020-april to june-merged_compressed.pdf · uploaded 3 Apr 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 2020-july to sept-merged.pdf · uploaded 3 Apr 2024Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 2020-oct to dec-merged.pdf · uploaded 3 Apr 2024Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 2021 jan to march-merged.pdf · uploaded 3 Apr 2024Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 2021 apr to june-merged.pdf · uploaded 3 Apr 2024Source
- 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 2021 july to sept-merged.pdf · uploaded 3 Apr 2024Source
- 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 2021 oct to dec-merged.pdf · uploaded 3 Apr 2024Source
- 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 2022 jan to mar-merged.pdf · uploaded 3 Apr 2024Source
- 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 2022 apr to june-merged.pdf · uploaded 3 Apr 2024Source
- 16 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 2022 july to sept-merged.pdf · uploaded 3 Apr 2024Source
- 17 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 2022 oct to dec-merged.pdf · uploaded 3 Apr 2024Source
- 18 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 2023 jan to mar-merged.pdf · uploaded 3 Apr 2024Source
- 19 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 2023 apr to june-merged.pdf · uploaded 3 Apr 2024Source
- 20 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 2023 july to sept-merged.pdf · uploaded 3 Apr 2024Source
- 21 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 2023 oct to dec-merged.pdf · uploaded 3 Apr 2024Source
- 22 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 2024-1-merged.pdf · uploaded 3 Apr 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)Adobe Scan 02-Apr-2024.pdf · uploaded 3 Apr 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Adobe Scan 02-Apr-2024.pdf · uploaded 3 Apr 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Adobe Scan 02-Apr-2024.pdf · uploaded 3 Apr 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Adobe Scan 02-Apr-2024.pdf · uploaded 3 Apr 2024Source
- 3 Certificates of CA (Form 3)2 Certificates of CA (Form 3)- january to march-merged.pdf · uploaded 4 Apr 2024Source
- 4 Certificates of CA (Form 3)form 3 2029 jan to march-merged.pdf · uploaded 4 Apr 2024Source
- 5 Certificates of CA (Form 3)form 3 2029 apr to june-merged.pdf · uploaded 4 Apr 2024Source
- 6 Certificates of CA (Form 3)form 3 2029 july to sept-merged.pdf · uploaded 4 Apr 2024Source
- 7 Certificates of CA (Form 3)form 3 2029 oct to dec-merged.pdf · uploaded 4 Apr 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 2023 (1).pdf · uploaded 5 Apr 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 2023 (2).pdf · uploaded 5 Apr 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 2023 (3).pdf · uploaded 5 Apr 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 2023 (4).pdf · uploaded 5 Apr 2024Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)form 2 2023 (5).pdf · uploaded 5 Apr 2024Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)form 2 2023 (6).pdf · uploaded 5 Apr 2024Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)form 2 2023 (7).pdf · uploaded 5 Apr 2024Source
- 5 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)form 2 2023 (8).pdf · uploaded 5 Apr 2024Source
- 6 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)form 2a 2020-21 (1).pdf · uploaded 5 Apr 2024Source
- 7 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)form 2a 2020-21 (2).pdf · uploaded 5 Apr 2024Source
- 8 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)form 2a 2020-21 (3).pdf · uploaded 5 Apr 2024Source
- 9 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)form 2a 2020-21 (4).pdf · uploaded 5 Apr 2024Source
- 10 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) (1).pdf · uploaded 5 Apr 2024Source
- 11 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) (2).pdf · uploaded 5 Apr 2024Source
- 12 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) (3).pdf · uploaded 5 Apr 2024Source
- 13 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) (4).pdf · uploaded 5 Apr 2024Source
- 14 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)form 2a 2022-23 (1).pdf · uploaded 5 Apr 2024Source
- 15 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)form 2a 2022-23 (2).pdf · uploaded 5 Apr 2024Source
- 16 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)form 2a 2022-23 (3).pdf · uploaded 5 Apr 2024Source
- 17 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)form 2a 2022-23 (4).pdf · uploaded 5 Apr 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Adobe Scan 02-Apr-2024.pdf · uploaded 5 Apr 2024Source
- 1 Proforma of Agreement for sale1 Proforma of Allotment letter.pdf · uploaded 5 Apr 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Adobe Scan 02-Apr-2024.pdf · uploaded 7 Apr 2024Source
- 1 Certificates of CA (Form 3)CA Cerificate_March 20.pdf · uploaded 25 Feb 2025Source
- 2 Certificates of CA (Form 3)CA Cerificate_March 21.pdf · uploaded 25 Feb 2025Source
- 3 Certificates of CA (Form 3)CA Cerificate_March 22.pdf · uploaded 25 Feb 2025Source
- 4 Certificates of CA (Form 3)CA Cerificate_March 23.pdf · uploaded 25 Feb 2025Source
- 5 Certificates of CA (Form 3)CA Cerificate_June 23.pdf · uploaded 25 Feb 2025Source
- 6 Certificates of CA (Form 3)CA Cerificate_Sep 23.pdf · uploaded 25 Feb 2025Source
- 7 Certificates of CA (Form 3)CA Cerificate_Dec 23.pdf · uploaded 25 Feb 2025Source
- 8 Certificates of CA (Form 3)CA Cerificate_March 24.pdf · uploaded 25 Feb 2025Source
- 9 Certificates of CA (Form 3)CA Cerificate_June 24.pdf · uploaded 25 Feb 2025Source
- 10 Certificates of CA (Form 3)CA Cerificate_Sep 24.pdf · uploaded 25 Feb 2025Source
- 11 Certificates of CA (Form 3)CA Cerificate_Dec 24.pdf · uploaded 25 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)RERA Audit Report_2020-21.pdf · uploaded 4 Mar 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)RERA Audit Report_2021-22.pdf · uploaded 4 Mar 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)RERA Audit Report_2022-23.pdf · uploaded 4 Mar 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)RERA Audit Report_2023-24.pdf · uploaded 4 Mar 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_March 21.pdf · uploaded 25 Apr 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_March 22.pdf · uploaded 25 Apr 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_March 23.pdf · uploaded 25 Apr 2025Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_June 23.pdf · uploaded 25 Apr 2025Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Sep 23.pdf · uploaded 25 Apr 2025Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Dec 23.pdf · uploaded 25 Apr 2025Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_March 24.pdf · uploaded 25 Apr 2025Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_June 24.pdf · uploaded 25 Apr 2025Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Sep 24.pdf · uploaded 25 Apr 2025Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Dec 24.pdf · uploaded 25 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_March 20.pdf · uploaded 25 Apr 2025Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_March 24.pdf · uploaded 25 Apr 2025Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Dec 24.pdf · uploaded 25 Apr 2025Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Sep 24.pdf · uploaded 25 Apr 2025Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_June 24.pdf · uploaded 25 Apr 2025Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Dec 23.pdf · uploaded 25 Apr 2025Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_June 23.pdf · uploaded 25 Apr 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_March 23.pdf · uploaded 25 Apr 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_March 22.pdf · uploaded 25 Apr 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_March 21.pdf · uploaded 25 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_March 20.pdf · uploaded 25 Apr 2025Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Sep 23.pdf · uploaded 25 Apr 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)RERA Audit Report_2018-19.pdf · uploaded 25 Apr 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)RERA Audit Report_2019-20.pdf · uploaded 25 Apr 2025Source
- 3 Disclosure of sold/ booked inventoryDisclosure_March 22.pdf · uploaded 25 Apr 2025Source
- 11 Disclosure of sold/ booked inventoryDisclosure_Dec 24.pdf · uploaded 25 Apr 2025Source
- 10 Disclosure of sold/ booked inventoryDisclosure_Sep 24.pdf · uploaded 25 Apr 2025Source
- 9 Disclosure of sold/ booked inventoryDisclosure_June 24.pdf · uploaded 25 Apr 2025Source
- 8 Disclosure of sold/ booked inventoryDisclosure_March 24.pdf · uploaded 25 Apr 2025Source
- 7 Disclosure of sold/ booked inventoryDisclosure_Dec 23.pdf · uploaded 25 Apr 2025Source
- 6 Disclosure of sold/ booked inventoryDisclosure_Sep 23.pdf · uploaded 25 Apr 2025Source
- 5 Disclosure of sold/ booked inventoryDisclosure_June 23.pdf · uploaded 25 Apr 2025Source
- 4 Disclosure of sold/ booked inventoryDisclosure_March 23.pdf · uploaded 25 Apr 2025Source
- 2 Disclosure of sold/ booked inventoryDisclosure_March 21.pdf · uploaded 25 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryDisclosure_March 20.pdf · uploaded 25 Apr 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A_March 24.pdf · uploaded 25 Apr 2025Source
- Form 1Form-1-Dec-24.pdf · uploaded 29 Jul 2025Source
- Form 2Form-2-Dec-24.pdf · uploaded 29 Jul 2025Source
- Form 3Form-3-Dec-24.pdf · uploaded 29 Jul 2025Source
- Disclosure of Sold and Booked InventorySold Unsold Disclosure_Dec 24.pdf · uploaded 29 Jul 2025Source
- Withdrawal Update Form 1Architect Certificate - June 25.pdf · uploaded 28 Aug 2025Source
- Withdrawal Update Form 2Engineer Certificate - June 25.pdf · uploaded 28 Aug 2025Source
- Withdrawal Update Form 3CA Certificate Jun 25.pdf · uploaded 28 Aug 2025Source
- Form 16 Architect’s Certificate of Percentage of Completion of Work (Form 1) March 20.pdf · uploaded 15 Sep 2025Source
- Form 26 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 19.pdf · uploaded 15 Sep 2025Source
- Form 34 Certificates of CA (Form 3) Mar 19.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory3 Disclosure of sold_ booked inventory March 20.pdf · uploaded 15 Sep 2025Source
- Form 16 Architect’s Certificate of Percentage of Completion of Work (Form 1) March 20.pdf · uploaded 15 Sep 2025Source
- Form 26 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 19.pdf · uploaded 15 Sep 2025Source
- Form 35 Certificates of CA (Form 3) June 19.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory3 Disclosure of sold_ booked inventory March 20.pdf · uploaded 15 Sep 2025Source
- Form 16 Architect’s Certificate of Percentage of Completion of Work (Form 1) March 20.pdf · uploaded 15 Sep 2025Source
- Form 26 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 19.pdf · uploaded 15 Sep 2025Source
- Form 36 Certificates of CA (Form 3) Sept 19.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory3 Disclosure of sold_ booked inventory March 20.pdf · uploaded 15 Sep 2025Source
- Form 16 Architect’s Certificate of Percentage of Completion of Work (Form 1) March 20.pdf · uploaded 15 Sep 2025Source
- Form 26 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 19.pdf · uploaded 15 Sep 2025Source
- Form 37 Certificates of CA (Form 3) Dec 19.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory3 Disclosure of sold_ booked inventory March 20.pdf · uploaded 15 Sep 2025Source
- Form 16 Architect’s Certificate of Percentage of Completion of Work (Form 1) March 20.pdf · uploaded 15 Sep 2025Source
- Form 26 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 19.pdf · uploaded 15 Sep 2025Source
- Form 38 Certificates of CA (Form 3) March 20.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory3 Disclosure of sold_ booked inventory March 20.pdf · uploaded 15 Sep 2025Source
- Form 17 Architect’s Certificate of Percentage of Completion of Work (Form 1) June 20.pdf · uploaded 15 Sep 2025Source
- Form 27 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 21.pdf · uploaded 15 Sep 2025Source
- Form 38 Certificates of CA (Form 3) March 20.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory3 Disclosure of sold_ booked inventory March 20.pdf · uploaded 15 Sep 2025Source
- Form 18 Architect’s Certificate of Percentage of Completion of Work (Form 1) Sept 20.pdf · uploaded 15 Sep 2025Source
- Form 26 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 19.pdf · uploaded 15 Sep 2025Source
- Form 38 Certificates of CA (Form 3) March 20.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory3 Disclosure of sold_ booked inventory March 20.pdf · uploaded 15 Sep 2025Source
- Form 19 Architect’s Certificate of Percentage of Completion of Work (Form 1) Dec 20.pdf · uploaded 15 Sep 2025Source
- Form 26 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 19.pdf · uploaded 15 Sep 2025Source
- Form 38 Certificates of CA (Form 3) March 20.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory3 Disclosure of sold_ booked inventory March 20.pdf · uploaded 15 Sep 2025Source
- Form 110 Architect’s Certificate of Percentage of Completion of Work (Form 1) March 21.pdf · uploaded 15 Sep 2025Source
- Form 27 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 21.pdf · uploaded 15 Sep 2025Source
- Form 39 Certificates of CA (Form 3) March 21.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory4 Disclosure of sold_ booked inventory March 21.pdf · uploaded 15 Sep 2025Source
- Form 111 Architect’s Certificate of Percentage of Completion of Work (Form 1) June 21.pdf · uploaded 15 Sep 2025Source
- Form 27 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 21.pdf · uploaded 15 Sep 2025Source
- Form 39 Certificates of CA (Form 3) March 21.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory4 Disclosure of sold_ booked inventory March 21.pdf · uploaded 15 Sep 2025Source
- Form 112 Architect’s Certificate of Percentage of Completion of Work (Form 1) Sept 21.pdf · uploaded 15 Sep 2025Source
- Form 27 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 21.pdf · uploaded 15 Sep 2025Source
- Form 39 Certificates of CA (Form 3) March 21.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory4 Disclosure of sold_ booked inventory March 21.pdf · uploaded 15 Sep 2025Source
- Form 113 Architect’s Certificate of Percentage of Completion of Work (Form 1) Dec 21.pdf · uploaded 15 Sep 2025Source
- Form 27 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 21.pdf · uploaded 15 Sep 2025Source
- Form 39 Certificates of CA (Form 3) March 21.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory4 Disclosure of sold_ booked inventory March 21.pdf · uploaded 15 Sep 2025Source
- Form 114 Architect’s Certificate of Percentage of Completion of Work (Form 1) March 22.pdf · uploaded 15 Sep 2025Source
- Form 28 Engineer’s Certificate on Cost Incurred on Project (Form 2) march 22.pdf · uploaded 15 Sep 2025Source
- Form 310 Certificates of CA (Form 3) March 22.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory5 Disclosure of sold_ booked inventory March 22.pdf · uploaded 15 Sep 2025Source
- Form 115 Architect’s Certificate of Percentage of Completion of Work (Form 1) june 22.pdf · uploaded 15 Sep 2025Source
- Form 28 Engineer’s Certificate on Cost Incurred on Project (Form 2) march 22.pdf · uploaded 15 Sep 2025Source
- Form 310 Certificates of CA (Form 3) March 22.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory5 Disclosure of sold_ booked inventory March 22.pdf · uploaded 15 Sep 2025Source
- Form 116 Architect’s Certificate of Percentage of Completion of Work (Form 1) Sept 22.pdf · uploaded 15 Sep 2025Source
- Form 28 Engineer’s Certificate on Cost Incurred on Project (Form 2) march 22.pdf · uploaded 15 Sep 2025Source
- Form 310 Certificates of CA (Form 3) March 22.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory5 Disclosure of sold_ booked inventory March 22.pdf · uploaded 15 Sep 2025Source
- Form 125 Architect’s Certificate of Percentage of Completion of Work (Form 1) Dec 22.pdf · uploaded 15 Sep 2025Source
- Form 28 Engineer’s Certificate on Cost Incurred on Project (Form 2) march 22.pdf · uploaded 15 Sep 2025Source
- Form 310 Certificates of CA (Form 3) March 22.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory5 Disclosure of sold_ booked inventory March 22.pdf · uploaded 15 Sep 2025Source
- Form 126 Architect’s Certificate of Percentage of Completion of Work (Form 1) March 23.pdf · uploaded 15 Sep 2025Source
- Form 29 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 23.pdf · uploaded 15 Sep 2025Source
- Form 311 Certificates of CA (Form 3) March 23.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory6 Disclosure of sold_ booked inventory March 23.pdf · uploaded 15 Sep 2025Source
- Form 127 Architect’s Certificate of Percentage of Completion of Work (Form 1) June 23.pdf · uploaded 15 Sep 2025Source
- Form 210 Engineer’s Certificate on Cost Incurred on Project (Form 2) June 23.pdf · uploaded 15 Sep 2025Source
- Form 312 Certificates of CA (Form 3) June 23.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory7 Disclosure of sold_ booked inventory June 23.pdf · uploaded 15 Sep 2025Source
- Form 128 Architect’s Certificate of Percentage of Completion of Work (Form 1) Sept 23.pdf · uploaded 15 Sep 2025Source
- Form 211 Engineer’s Certificate on Cost Incurred on Project (Form 2) Sept 23.pdf · uploaded 15 Sep 2025Source
- Form 313 Certificates of CA (Form 3) Sept 23.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory8 Disclosure of sold_ booked inventory Sept 23.pdf · uploaded 15 Sep 2025Source
- Form 129 Architect’s Certificate of Percentage of Completion of Work (Form 1) Dec 23.pdf · uploaded 15 Sep 2025Source
- Form 212 Engineer’s Certificate on Cost Incurred on Project (Form 2) Dec 23.pdf · uploaded 15 Sep 2025Source
- Form 314 Certificates of CA (Form 3) Dec 23.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory9 Disclosure of sold_ booked inventory Dec 23.pdf · uploaded 15 Sep 2025Source
- Form 130 Architect’s Certificate of Percentage of Completion of Work (Form 1) March 24.pdf · uploaded 15 Sep 2025Source
- Form 213 Engineer’s Certificate on Cost Incurred on Project (Form 2) March 24.pdf · uploaded 15 Sep 2025Source
- Form 315 Certificates of CA (Form 3) March 24.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory10 Disclosure of sold_ booked inventory March 24.pdf · uploaded 15 Sep 2025Source
- Form 131 Architect’s Certificate of Percentage of Completion of Work (Form 1) June 24.pdf · uploaded 15 Sep 2025Source
- Form 214 Engineer’s Certificate on Cost Incurred on Project (Form 2) June 24.pdf · uploaded 15 Sep 2025Source
- Form 316 Certificates of CA (Form 3) June 24.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory11 Disclosure of sold_ booked inventory June 24.pdf · uploaded 15 Sep 2025Source
- Form 132 Architect’s Certificate of Percentage of Completion of Work (Form 1) Sept 24.pdf · uploaded 15 Sep 2025Source
- Form 215 Engineer’s Certificate on Cost Incurred on Project (Form 2) Sept 24.pdf · uploaded 15 Sep 2025Source
- Form 317 Certificates of CA (Form 3) Sept 24.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventory12 Disclosure of sold_ booked inventory Sept 24.pdf · uploaded 15 Sep 2025Source
- Form 1Ar Mar 25.pdf · uploaded 15 Sep 2025Source
- Form 2Engg Mar 25.pdf · uploaded 15 Sep 2025Source
- Form 3CA Mar 25.pdf · uploaded 15 Sep 2025Source
- Disclosure of Sold and Booked Inventorysold-unsold march 25.pdf · uploaded 15 Sep 2025Source
- Form 2A (FY 2018-2019)2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23) Mar 20.pdf · uploaded 15 Sep 2025Source
- Form 2A (FY 2019-2020)2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23) Mar 20.pdf · uploaded 15 Sep 2025Source
- Form 2A (FY 2020-2021)6 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Mar 21.pdf · uploaded 15 Sep 2025Source
- Form 2A (FY 2021-2022)10 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23) Mar 22.pdf · uploaded 15 Sep 2025Source
- Form 2A (FY 2022-2023)14 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23) Mar 23.pdf · uploaded 15 Sep 2025Source
- Form 2A (FY 2023-2024)Form 2A.pdf · uploaded 16 Sep 2025Source
- Form 2A (FY 2023-2024)Form 2A.pdf · uploaded 16 Sep 2025Source
- Form 2A (FY 2024-2025)Form 2A.pdf · uploaded 16 Sep 2025Source
- Form 2A (FY 2024-2025)Form 2A.pdf · uploaded 16 Sep 2025Source
- Form 5 (FY 2018-2019)2018-19.pdf · uploaded 16 Sep 2025Source
- Form 5 (FY 2019-2020)2019-20.pdf · uploaded 16 Sep 2025Source
- Form 5 (FY 2020-2021)2020-21.pdf · uploaded 16 Sep 2025Source
- Form 5 (FY 2021-2022)2021-22.pdf · uploaded 16 Sep 2025Source
- Form 5 (FY 2022-2023)2022-23.pdf · uploaded 16 Sep 2025Source
- Form 5 (FY 2023-2024)2023-24.pdf · uploaded 16 Sep 2025Source
- Withdrawal Update Form 1F1 Sept (Manor Crystal).pdf · uploaded 18 May 2026Source
- Withdrawal Update Form 2Engineer certificate Sep.pdf · uploaded 18 May 2026Source
- Withdrawal Update Form 3F3 Sept.pdf · uploaded 18 May 2026Source
- Withdrawal Update Form 1F1 Sept (Manor Crystal).pdf · uploaded 4 Jun 2026Source
- Withdrawal Update Form 1F1 Dec 25 (Manor Crystal).pdf · uploaded 4 Jun 2026Source
- Withdrawal Update Form 1F1 Mar 26 (Manor Crystal)..pdf · uploaded 4 Jun 2026Source
- Withdrawal Update Form 2Engineer certificate Sep 25.pdf · uploaded 4 Jun 2026Source
- Withdrawal Update Form 2Engineer certificate dec 25.pdf · uploaded 4 Jun 2026Source
- Withdrawal Update Form 2Engineer certificate March 26.pdf · uploaded 4 Jun 2026Source
- Withdrawal Update Form 3F3 Sept.pdf · uploaded 4 Jun 2026Source
- Withdrawal Update Form 3F3-Crystal Manor (Dec 25).pdf · uploaded 4 Jun 2026Source
- Withdrawal Update Form 3F3-MARCH-26.pdf · uploaded 4 Jun 2026Source
- Withdrawal Update Form 1F1 Manor Crystal.pdf · uploaded 20 Sep 2026Source
- Withdrawal Update Form 2Form - 2 Engineer Certificate - Manor Crystal Project.pdf · uploaded 20 Sep 2026Source
- Withdrawal Update Form 3F 3 - MANOR CRYSTAL (1).pdf · uploaded 20 Sep 2026Source
Technical
- Documentlayout plan_converted_compressed.pdf · uploaded 27 Feb 2019Source
- DocumentBuilding Plan_converted.pdf · uploaded 27 Feb 2019Source
- DocumentLAYOUT.pdf · uploaded 16 Dec 2023Source
- Other – TechnicalPIMPRI CHINCHWAD MUNICIPAL CORPORATION Mail - Commencement Certificate Verification For Application No - EXT52100017660.pdf · uploaded 11 Mar 2024Source
Technical (Architect)
- DocumentForm 1_March 20.pdf · uploaded 25 Apr 2025Source
- DocumentForm 1_March 21.pdf · uploaded 25 Apr 2025Source
- DocumentForm 1_March 22.pdf · uploaded 25 Apr 2025Source
- DocumentForm 1_March 23.pdf · uploaded 25 Apr 2025Source
- DocumentForm 1_June 23.pdf · uploaded 25 Apr 2025Source
- DocumentForm 1_Sep 23.pdf · uploaded 25 Apr 2025Source
- DocumentForm 1_Dec 23.pdf · uploaded 25 Apr 2025Source
- DocumentForm 1_March 24.pdf · uploaded 25 Apr 2025Source
- DocumentForm 1_June 24.pdf · uploaded 25 Apr 2025Source
- DocumentForm 1_Sep 24.pdf · uploaded 25 Apr 2025Source
- DocumentForm 1_Dec 24.pdf · uploaded 25 Apr 2025Source
- DocumentF1 Manor Crystal.pdf · uploaded 20 Sep 2026Source
Technical (Engineer)
- DocumentForm 2_March 20.pdf · uploaded 25 Apr 2025Source
- DocumentForm 2_March 21.pdf · uploaded 25 Apr 2025Source
- DocumentForm 2_March 22.pdf · uploaded 25 Apr 2025Source
- DocumentForm 2_March 23.pdf · uploaded 25 Apr 2025Source
- DocumentForm 2_June 23.pdf · uploaded 25 Apr 2025Source
- DocumentForm 2_Sep 23.pdf · uploaded 25 Apr 2025Source
- DocumentForm 2_Dec 23.pdf · uploaded 25 Apr 2025Source
- DocumentForm 2_March 24.pdf · uploaded 25 Apr 2025Source
- DocumentForm 2_June 24.pdf · uploaded 25 Apr 2025Source
- DocumentForm 2_Sep 24.pdf · uploaded 25 Apr 2025Source
- DocumentForm 2_Dec 24.pdf · uploaded 25 Apr 2025Source
- DocumentForm - 2 Engineer Certificate - Manor Crystal Project.pdf · uploaded 20 Sep 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsS No137/2/2
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —32 units in all
- Address
- S No137/2/2, Bhumkar Chowk-Karpenagar, Wakad, Pune, Bhumkar Chowk-Karpe Nagar, WakadPIN 411057
- Village
- Wakad, Mulshi taluka
- Location
- 18.59978, 73.73432
- Designated bank account
- 109
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Boundaries
- North
- S No 121 P
- South
- S No 137 P
- East
- S No 137 Other Part
- West
- Raisoni Builder
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking32 units
32 units registered
| Building | Type | Carpet area | Units |
|---|---|---|---|
| A | — | — | 16 |
| B | — | — | 16 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | unusual spaces | — |
| Engineer | Nihal Abdul Shaikh | — |
Source: MahaRERA project page. Contact details are not shown.