Vantaara
Completion was pushed back 4 months, to Jul 2029; no MahaRERA orders on record.
Wagholi, Pune 412207 · Property rates in Wagholi · Promoter: Reden Realty Buildcon LLP
Completion was pushed back 4 months, to Jul 2029
- This projectRegistered 18 Nov 2025, completion promised 31 Mar 2029, revised to 31 Jul 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
3 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPM1260002501504
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PM1260002501504 | 18 Nov 2025 | 31 Mar 2029 | 31 Jul 2029 | Reden Realty Buildcon LLP | Project page |
Documents34
1 document held by Deedo, 33 filings listed on MahaRERA's project page
Finance
- PAN CardFirm Pan Card.pdf · uploaded 28 Jun 2025Source
- OthersClarification letter.pdf · uploaded 8 Jul 2025Source
- OthersNo Bank Account Declaration.pdf · uploaded 8 Jul 2025Source
- OthersReden Clarification Letter with approved Plan.pdf · uploaded 7 Aug 2025Source
- OthersClarification letter 03092025.pdf · uploaded 4 Sep 2025Source
Show all 34 documentsShow fewer documents
Legal
- Declaration Form BTitle Report-Reden Realty.pdf · uploaded 1 Jul 2025Source
- Declaration Form BSatbara Extract.pdf · uploaded 1 Jul 2025Source
- OthersReden Realty-Disclosure of Interest.pdf · uploaded 7 Aug 2025Source
- OthersLand owner-Partnership Deed.pdf · uploaded 29 Sep 2025Source
- OthersReconstitution Deed.pdf · uploaded 6 Oct 2025Source
- OthersOm Sai Developers-NOC.pdf · uploaded 7 Nov 2025Source
Migrated
- Withdrawal Update Form 1Architect Certificate Dec 2025.pdf · uploaded 14 May 2026Source
- Withdrawal Update Form 2Engineer certificate Dec 2025.pdf · uploaded 14 May 2026Source
- Withdrawal Update Form 3CA Certificate Dec 2025 final.pdf · uploaded 14 May 2026Source
- Withdrawal Update Form 1Architect letter_0001.pdf · uploaded 29 May 2026Source
- Withdrawal Update Form 2Engineer vantaara_0001-Final.pdf · uploaded 29 May 2026Source
- Withdrawal Update Form 3CA VANTAARA_0001-Final.pdf · uploaded 29 May 2026Source
- Withdrawal Update Form 1Architect certificate vantaara_0001.pdf · uploaded 31 Aug 2026Source
- Withdrawal Update Form 2Engineer certificate vantaara_0001 - .pdf · uploaded 31 Aug 2026Source
- Withdrawal Update Form 3CA CERTIFICATE VANTAARA_0001.pdf · uploaded 31 Aug 2026Source
Technical
- DocumentSanction Plan.pdf · uploaded 28 Jun 2025Source
- DocumentAnnexure A One Plot One Reg.pdf · uploaded 8 Jul 2025Source
- OthersEngineer certificate.pdf · uploaded 8 Jul 2025Source
- OthersClarification letter.pdf · uploaded 8 Jul 2025Source
- OthersFormat D.pdf · uploaded 8 Jul 2025Source
- OthersArchitect certificate.pdf · uploaded 8 Jul 2025Source
- OthersReden-CC Confirmation.pdf · uploaded 7 Aug 2025Source
- OthersReden Clarification Letter with approved Plan.pdf · uploaded 7 Aug 2025Source
- OthersClarification letter 03092025.pdf · uploaded 4 Sep 2025Source
Technical (Architect)
- DocumentArchitect certificate vantaara_0001.pdf · uploaded 31 Aug 2026Source
Technical (Engineer)
- DocumentEngineer certificate vantaara_0001 - .pdf · uploaded 31 Aug 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsGut No 1420/2 Part
As registered with MahaRERA and published on its project page
- Project type
- Mixed
- Status on MahaRERA
- Certificate Signed
- Unit types
- —47 units in all
- Address
- Gut no 1420/2 Part, WagholiPIN 412207
- Village
- Wagholi, Haveli taluka
- Location
- 18.58313, 73.97926
- Designated bank account
- 109
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Boundaries
- North
- Gat No 1420 Part
- South
- Wagholi Lohgaon Road
- East
- Wagholi Bhavadi Road
- West
- Gat no 1420 Part
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking47 units
47 units registered
| Building | Type | Carpet area | Units |
|---|---|---|---|
| Wing A | — | — | 16 |
| Wing B | — | — | 31 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Niral Mohit Gangele | — |
| Engineer | Rajabhai Rahimso Karanje | — |
Source: MahaRERA project page. Contact details are not shown.