Deedo IDDP-PUN-YJ75Completion was pushed back 3 years and 2 months, to Feb 2027; no MahaRERA orders on record; 81% of its units are booked.
Wagholi, Pune 412207 · Property rates in Wagholi · Promoter: Ravinanda Landmarks
Completion was pushed back 3 years and 2 months, to Feb 2027
- This projectRegistered 6 Aug 2017, completion promised 30 Dec 2023, revised to 28 Feb 2027.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
8 buildings
Open a building to see every flat, floor by floor.
- C Wing16 floors · 95 units98% booked
- D Wing16 floors · 95 units91% booked
- E Wing16 floors · 96 units94% booked
- F Wing16 floors · 95 units91% booked
- G Wing17 floors · 95 units36% booked
- Row House 12 floors · 1 unit0% booked
- Row House 22 floors · 1 unit0% booked
- Row House 32 floors · 1 unit0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100003645
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100003645 | 6 Aug 2017 | 30 Dec 2023 | 28 Feb 2027 | Ravinanda Landmarks | Project page |
Documents268
2 documents held by Deedo, 266 filings listed on MahaRERA's project page
Finance
- PAN Cardpan.pdf · uploaded 29 Jul 2017Source
Legal
- Other14.pdf · uploaded 29 Jul 2017Source
- Legal Title reportsearch title (1).pdf · uploaded 29 Jul 2017Source
- Declaration Form Bform b.pdf · uploaded 29 Jul 2017Source
- Declaration Form BForm B Affidavid.pdf · uploaded 7 Mar 2024Source
- Declaration Form BAffidavit cum Declaration.pdf · uploaded 12 Mar 2025Source
Show all 268 documentsShow fewer documents
Migrated
- 1 PAN Cardpan.pdf · uploaded 29 Jul 2017Source
- 1 Copy of the legal title reportsearch title (1).pdf · uploaded 29 Jul 2017Source
- 1 Details of encumbrancesemu.pdf · uploaded 29 Jul 2017Source
- 1 Copy of Layout Approval (in case of layout)1.pdf · uploaded 29 Jul 2017Source
- 1 Building Plan Approval (IOD)1.pdf · uploaded 29 Jul 2017Source
- 2 Building Plan Approval (IOD)2.pdf · uploaded 29 Jul 2017Source
- 3 Building Plan Approval (IOD)3.pdf · uploaded 29 Jul 2017Source
- 4 Building Plan Approval (IOD)4.pdf · uploaded 29 Jul 2017Source
- 5 Building Plan Approval (IOD)5.pdf · uploaded 29 Jul 2017Source
- 6 Building Plan Approval (IOD)6.pdf · uploaded 29 Jul 2017Source
- 7 Building Plan Approval (IOD)7.pdf · uploaded 29 Jul 2017Source
- 8 Building Plan Approval (IOD)8.pdf · uploaded 29 Jul 2017Source
- 9 Building Plan Approval (IOD)9.pdf · uploaded 29 Jul 2017Source
- 10 Building Plan Approval (IOD)10.pdf · uploaded 29 Jul 2017Source
- 11 Building Plan Approval (IOD)11.pdf · uploaded 29 Jul 2017Source
- 12 Building Plan Approval (IOD)12.pdf · uploaded 29 Jul 2017Source
- 13 Building Plan Approval (IOD)13.pdf · uploaded 29 Jul 2017Source
- 14 Building Plan Approval (IOD)14.pdf · uploaded 29 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentcc.pdf · uploaded 29 Jul 2017Source
- 1 Declaration in FORM Bform b.pdf · uploaded 29 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)img028.pdf · uploaded 29 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ESTI.pdf · uploaded 29 Jul 2017Source
- 1 Certificates of CA (Form 3)ca.pdf · uploaded 29 Jul 2017Source
- 2 Certificates of CA (Form 3)annex.pdf · uploaded 29 Jul 2017Source
- 1 Proforma of Allotment letterallotment.pdf · uploaded 29 Jul 2017Source
- 2 Proforma of Allotment letteragreement.pdf · uploaded 29 Jul 2017Source
- 1 Other14.pdf · uploaded 29 Jul 2017Source
- 1 Certificates of CA (Form 5)RNL FORM 5.PDF · uploaded 21 Dec 2018Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)skylights form 2_compressed (1).pdf · uploaded 8 Jun 2020Source
- 2 Certificates of CA (Form 5)RAVINANDA LANDMARKS RERA 2020.pdf · uploaded 28 Jun 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)RAVINANDA LANDMARKS RERA 2019.pdf · uploaded 28 Jun 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)RAVINANDA LANDMARKS RERA 2020.pdf · uploaded 28 Jun 2021Source
- 15 Building Plan Approval (IOD)20211012015946.pdf · uploaded 12 Oct 2021Source
- 16 Building Plan Approval (IOD)20211012020019.pdf · uploaded 12 Oct 2021Source
- 17 Building Plan Approval (IOD)20211012020102.pdf · uploaded 12 Oct 2021Source
- 18 Building Plan Approval (IOD)20211012020140.pdf · uploaded 12 Oct 2021Source
- 19 Building Plan Approval (IOD)20211012020211.pdf · uploaded 12 Oct 2021Source
- 20 Building Plan Approval (IOD)20211012020234.pdf · uploaded 12 Oct 2021Source
- 21 Building Plan Approval (IOD)20211012020303.pdf · uploaded 12 Oct 2021Source
- 22 Building Plan Approval (IOD)20211012020335.pdf · uploaded 12 Oct 2021Source
- 23 Building Plan Approval (IOD)20211012020404.pdf · uploaded 12 Oct 2021Source
- 24 Building Plan Approval (IOD)20211012020427.pdf · uploaded 12 Oct 2021Source
- 25 Building Plan Approval (IOD)20211012020451.pdf · uploaded 12 Oct 2021Source
- 26 Building Plan Approval (IOD)20211012020451.pdf · uploaded 12 Oct 2021Source
- 27 Building Plan Approval (IOD)20211012020518.pdf · uploaded 12 Oct 2021Source
- 28 Building Plan Approval (IOD)20211012020637.pdf · uploaded 12 Oct 2021Source
- 29 Building Plan Approval (IOD)20211012020702.pdf · uploaded 12 Oct 2021Source
- 30 Building Plan Approval (IOD)20211012020731.pdf · uploaded 12 Oct 2021Source
- 31 Building Plan Approval (IOD)20211012020806.pdf · uploaded 12 Oct 2021Source
- 32 Building Plan Approval (IOD)20211012020806.pdf · uploaded 12 Oct 2021Source
- 33 Building Plan Approval (IOD)20211012020906.pdf · uploaded 12 Oct 2021Source
- 34 Building Plan Approval (IOD)20211012020906.pdf · uploaded 12 Oct 2021Source
- 35 Building Plan Approval (IOD)20211012020938.pdf · uploaded 12 Oct 2021Source
- 36 Building Plan Approval (IOD)20211012021101.pdf · uploaded 12 Oct 2021Source
- 37 Building Plan Approval (IOD)20211012021128.pdf · uploaded 12 Oct 2021Source
- 38 Building Plan Approval (IOD)20211012020518.pdf · uploaded 12 Oct 2021Source
- 39 Building Plan Approval (IOD)20211012020610.pdf · uploaded 12 Oct 2021Source
- 40 Building Plan Approval (IOD)20211012020838.pdf · uploaded 12 Oct 2021Source
- 41 Building Plan Approval (IOD)20211012021028.pdf · uploaded 12 Oct 2021Source
- 2 Commencement Certificates / NA Order for plotted development20211012020610.pdf · uploaded 12 Oct 2021Source
- 3 Commencement Certificates / NA Order for plotted developmentScan10001-converted.pdf · uploaded 12 Oct 2021Source
- 4 Commencement Certificates / NA Order for plotted developmentScan10002-converted.pdf · uploaded 12 Oct 2021Source
- 5 Commencement Certificates / NA Order for plotted developmentScan10003-converted.pdf · uploaded 12 Oct 2021Source
- 6 Commencement Certificates / NA Order for plotted developmentScan10004-converted.pdf · uploaded 12 Oct 2021Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Annexure A -Architect Certificate.pdf · uploaded 23 Feb 2024Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 23 Feb 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A 2020-21.pdf · uploaded 23 Feb 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A 2021-22.pdf · uploaded 23 Feb 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A 2022-23.pdf · uploaded 23 Feb 2024Source
- 3 Certificates of CA (Form 3)Form-3 Chartered Accountant Certificate_compressed.pdf · uploaded 23 Feb 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 Annual Report Statement 20-21.pdf · uploaded 23 Feb 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 Annual Report Statement 21-22.pdf · uploaded 23 Feb 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Annual Report Statement-22-23.pdf · uploaded 23 Feb 2024Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Cert 1.pdf · uploaded 26 Feb 2024Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Cert 2.pdf · uploaded 26 Feb 2024Source
- 1 Disclosure of sold/ booked inventoryDisclosure of Sold Unsold_compressed.pdf · uploaded 26 Feb 2024Source
- 2 Copy of Layout Approval (in case of layout)1-2.pdf · uploaded 7 Mar 2024Source
- 42 Building Plan Approval (IOD)2.pdf · uploaded 7 Mar 2024Source
- 43 Building Plan Approval (IOD)3.pdf · uploaded 7 Mar 2024Source
- 44 Building Plan Approval (IOD)4.pdf · uploaded 7 Mar 2024Source
- 45 Building Plan Approval (IOD)5.pdf · uploaded 7 Mar 2024Source
- 46 Building Plan Approval (IOD)6.pdf · uploaded 7 Mar 2024Source
- 47 Building Plan Approval (IOD)7.pdf · uploaded 7 Mar 2024Source
- 48 Building Plan Approval (IOD)8.pdf · uploaded 7 Mar 2024Source
- 49 Building Plan Approval (IOD)9.pdf · uploaded 7 Mar 2024Source
- 50 Building Plan Approval (IOD)10.pdf · uploaded 7 Mar 2024Source
- 51 Building Plan Approval (IOD)11.pdf · uploaded 7 Mar 2024Source
- 52 Building Plan Approval (IOD)12.pdf · uploaded 7 Mar 2024Source
- 53 Building Plan Approval (IOD)13.pdf · uploaded 7 Mar 2024Source
- 54 Building Plan Approval (IOD)14-1.pdf · uploaded 7 Mar 2024Source
- 55 Building Plan Approval (IOD)15.pdf · uploaded 7 Mar 2024Source
- 56 Building Plan Approval (IOD)16.pdf · uploaded 7 Mar 2024Source
- 57 Building Plan Approval (IOD)17.pdf · uploaded 7 Mar 2024Source
- 58 Building Plan Approval (IOD)18.pdf · uploaded 7 Mar 2024Source
- 59 Building Plan Approval (IOD)19.pdf · uploaded 7 Mar 2024Source
- 60 Building Plan Approval (IOD)20.pdf · uploaded 7 Mar 2024Source
- 61 Building Plan Approval (IOD)21.pdf · uploaded 7 Mar 2024Source
- 62 Building Plan Approval (IOD)22.pdf · uploaded 7 Mar 2024Source
- 63 Building Plan Approval (IOD)23.pdf · uploaded 7 Mar 2024Source
- 7 Commencement Certificates / NA Order for plotted developmentc c 2021.pdf · uploaded 7 Mar 2024Source
- 1 Declaration about Commencement CertificateDeclaration About Commencement Certificate.pdf · uploaded 7 Mar 2024Source
- 2 Declaration in FORM BForm B Affidavid.pdf · uploaded 7 Mar 2024Source
- 1 CERSAI detailsLETTER CERSAI.pdf · uploaded 7 Mar 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A - Dilip.PDF · uploaded 7 Mar 2024Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A -Sameer R Jain.pdf · uploaded 7 Mar 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeviation to No Escrow.pdf · uploaded 7 Mar 2024Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)30-03-2019.pdf · uploaded 8 Mar 2025Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)31-03-2018.pdf · uploaded 8 Mar 2025Source
- 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)30-09-2024.pdf · uploaded 8 Mar 2025Source
- 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)31-12-2024.pdf · uploaded 8 Mar 2025Source
- 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)29-06-2024.pdf · uploaded 8 Mar 2025Source
- 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)30-03-2024.pdf · uploaded 8 Mar 2025Source
- 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)30-12-2023.pdf · uploaded 8 Mar 2025Source
- 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)30-09-2023.pdf · uploaded 8 Mar 2025Source
- 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)30-06-2023.pdf · uploaded 8 Mar 2025Source
- 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)31-03-2023.pdf · uploaded 8 Mar 2025Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)31-03-2022.pdf · uploaded 8 Mar 2025Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)31-03-2021.pdf · uploaded 8 Mar 2025Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)31-03-2020.pdf · uploaded 8 Mar 2025Source
- 14 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 31-12-2024.pdf · uploaded 8 Mar 2025Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 31-03-2019.pdf · uploaded 8 Mar 2025Source
- 13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 30-09-2024.pdf · uploaded 8 Mar 2025Source
- 12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 30-06-2024.pdf · uploaded 8 Mar 2025Source
- 11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 30-06-2024.pdf · uploaded 8 Mar 2025Source
- 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 31-03-2024.pdf · uploaded 8 Mar 2025Source
- 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 31-12-2023.pdf · uploaded 8 Mar 2025Source
- 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 30-09-2023.pdf · uploaded 8 Mar 2025Source
- 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 30-06-2023.pdf · uploaded 8 Mar 2025Source
- 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 31-03-2023.pdf · uploaded 8 Mar 2025Source
- 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 31-03-2022.pdf · uploaded 8 Mar 2025Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 31-03-2021.pdf · uploaded 8 Mar 2025Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 31-03-2020.pdf · uploaded 8 Mar 2025Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 31-03-2018.pdf · uploaded 8 Mar 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A 23-24.pdf · uploaded 8 Mar 2025Source
- 1 Declaration in FORM BAffidavit cum Declaration.pdf · uploaded 12 Mar 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 23-24.pdf · uploaded 17 Mar 2025Source
- 1 Proforma of Agreement for saleSKYLIGHTS DRAFT 1.pdf · uploaded 9 Apr 2025Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Skylight FORM 1 MARCH 2025.pdf · uploaded 19 Apr 2025Source
- 1 Certificates of CA (Form 3)skylights Form 3 Mar 18.pdf · uploaded 19 Apr 2025Source
- 13 Certificates of CA (Form 3)skylights Form 3 Mar 25.pdf · uploaded 19 Apr 2025Source
- 12 Certificates of CA (Form 3)skylights Form 3 Dec 24.pdf · uploaded 19 Apr 2025Source
- 11 Certificates of CA (Form 3)Skylight Form 3 Sept 24.pdf · uploaded 19 Apr 2025Source
- 10 Certificates of CA (Form 3)skylights Form 3 Jun 24.pdf · uploaded 19 Apr 2025Source
- 9 Certificates of CA (Form 3)skylights Form 3 Mar 24.pdf · uploaded 19 Apr 2025Source
- 8 Certificates of CA (Form 3)skylights Form 3 Sept 23.pdf · uploaded 19 Apr 2025Source
- 7 Certificates of CA (Form 3)Skylight Form 3 June 2023.pdf · uploaded 19 Apr 2025Source
- 6 Certificates of CA (Form 3)skylights Form 3 Mar 23.pdf · uploaded 19 Apr 2025Source
- 5 Certificates of CA (Form 3)skylights Form 3 Mar 22.pdf · uploaded 19 Apr 2025Source
- 4 Certificates of CA (Form 3)skylights Form 3 Mar 21.pdf · uploaded 19 Apr 2025Source
- 3 Certificates of CA (Form 3)skylights Form 3 Mar 20.pdf · uploaded 19 Apr 2025Source
- 2 Certificates of CA (Form 3)skylights Form 3 Mar 19.pdf · uploaded 19 Apr 2025Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Skylights Form 2 Dated Mar 25.pdf · uploaded 19 Apr 2025Source
- 1 Disclosure of sold/ booked inventorySkylight sold Unsold Mar 25 (3).pdf · uploaded 19 Apr 2025Source
- 1 Other – TechnicalPert Chat Skylight.pdf · uploaded 19 Apr 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 Ravinanda Landmarks FY 2023-24.pdf · uploaded 19 Apr 2025Source
- 1 Certificates of CA (Form 3)Skylight Form 3 March 23.pdf · uploaded 22 Apr 2025Source
- 2 Certificates of CA (Form 3)Skylight Form 3 June 23.pdf · uploaded 22 Apr 2025Source
- 3 Certificates of CA (Form 3)Skylight Form 3 Sept 23.pdf · uploaded 22 Apr 2025Source
- 4 Certificates of CA (Form 3)Skylight Form 3 March 24.pdf · uploaded 22 Apr 2025Source
- 5 Certificates of CA (Form 3)Skylight Form 3 June 24.pdf · uploaded 22 Apr 2025Source
- 6 Certificates of CA (Form 3)Skylight Form 3 Sept 2024.pdf · uploaded 22 Apr 2025Source
- 7 Certificates of CA (Form 3)Skylight Form 3 Dec 2024.pdf · uploaded 22 Apr 2025Source
- 8 Certificates of CA (Form 3)Skylight Form 3 March 25.pdf · uploaded 22 Apr 2025Source
Technical
- Document1.pdf · uploaded 29 Jul 2017Source
- Document14.pdf · uploaded 29 Jul 2017Source
- Document12.pdf · uploaded 29 Jul 2017Source
- Document13.pdf · uploaded 29 Jul 2017Source
- Document7.pdf · uploaded 29 Jul 2017Source
- Document8.pdf · uploaded 29 Jul 2017Source
- Document9.pdf · uploaded 29 Jul 2017Source
- Document10.pdf · uploaded 29 Jul 2017Source
- Document11.pdf · uploaded 29 Jul 2017Source
- Document1.pdf · uploaded 29 Jul 2017Source
- Document2.pdf · uploaded 29 Jul 2017Source
- Document3.pdf · uploaded 29 Jul 2017Source
- Document4.pdf · uploaded 29 Jul 2017Source
- Document5.pdf · uploaded 29 Jul 2017Source
- Document6.pdf · uploaded 29 Jul 2017Source
- Document20211012020518.pdf · uploaded 12 Oct 2021Source
- Document20211012020610.pdf · uploaded 12 Oct 2021Source
- Document20211012020838.pdf · uploaded 12 Oct 2021Source
- Document20211012021028.pdf · uploaded 12 Oct 2021Source
- Document20211012015946.pdf · uploaded 12 Oct 2021Source
- Document20211012020019.pdf · uploaded 12 Oct 2021Source
- Document20211012020102.pdf · uploaded 12 Oct 2021Source
- Document20211012020140.pdf · uploaded 12 Oct 2021Source
- Document20211012020211.pdf · uploaded 12 Oct 2021Source
- Document20211012020234.pdf · uploaded 12 Oct 2021Source
- Document20211012020303.pdf · uploaded 12 Oct 2021Source
- Document20211012020335.pdf · uploaded 12 Oct 2021Source
- Document20211012020404.pdf · uploaded 12 Oct 2021Source
- Document20211012020427.pdf · uploaded 12 Oct 2021Source
- Document20211012020451.pdf · uploaded 12 Oct 2021Source
- Document20211012020451.pdf · uploaded 12 Oct 2021Source
- Document20211012020518.pdf · uploaded 12 Oct 2021Source
- Document20211012020637.pdf · uploaded 12 Oct 2021Source
- Document20211012020702.pdf · uploaded 12 Oct 2021Source
- Document20211012020731.pdf · uploaded 12 Oct 2021Source
- Document20211012020806.pdf · uploaded 12 Oct 2021Source
- Document20211012020806.pdf · uploaded 12 Oct 2021Source
- Document20211012020906.pdf · uploaded 12 Oct 2021Source
- Document20211012020906.pdf · uploaded 12 Oct 2021Source
- Document20211012020938.pdf · uploaded 12 Oct 2021Source
- Document20211012021101.pdf · uploaded 12 Oct 2021Source
- Document20211012021128.pdf · uploaded 12 Oct 2021Source
- Document1-2.pdf · uploaded 7 Mar 2024Source
- Document2.pdf · uploaded 7 Mar 2024Source
- Document3.pdf · uploaded 7 Mar 2024Source
- Document4.pdf · uploaded 7 Mar 2024Source
- Document5.pdf · uploaded 7 Mar 2024Source
- Document6.pdf · uploaded 7 Mar 2024Source
- Document7.pdf · uploaded 7 Mar 2024Source
- Document8.pdf · uploaded 7 Mar 2024Source
- Document9.pdf · uploaded 7 Mar 2024Source
- Document10.pdf · uploaded 7 Mar 2024Source
- Document11.pdf · uploaded 7 Mar 2024Source
- Document12.pdf · uploaded 7 Mar 2024Source
- Document13.pdf · uploaded 7 Mar 2024Source
- Document14-1.pdf · uploaded 7 Mar 2024Source
- Document15.pdf · uploaded 7 Mar 2024Source
- Document16.pdf · uploaded 7 Mar 2024Source
- Document17.pdf · uploaded 7 Mar 2024Source
- Document18.pdf · uploaded 7 Mar 2024Source
- Document19.pdf · uploaded 7 Mar 2024Source
- Document20.pdf · uploaded 7 Mar 2024Source
- Document21.pdf · uploaded 7 Mar 2024Source
- Document22.pdf · uploaded 7 Mar 2024Source
- Document23.pdf · uploaded 7 Mar 2024Source
- Other – TechnicalPert Chat Skylight.pdf · uploaded 19 Apr 2025Source
Technical (Architect)
- DocumentArchitect Cert 2.pdf · uploaded 26 Feb 2024Source
- Document31-03-2018.pdf · uploaded 8 Mar 2025Source
- Document30-03-2019.pdf · uploaded 8 Mar 2025Source
- Document31-03-2020.pdf · uploaded 8 Mar 2025Source
- Document31-03-2021.pdf · uploaded 8 Mar 2025Source
- Document31-03-2022.pdf · uploaded 8 Mar 2025Source
- Document31-03-2023.pdf · uploaded 8 Mar 2025Source
- Document30-06-2023.pdf · uploaded 8 Mar 2025Source
- Document30-09-2023.pdf · uploaded 8 Mar 2025Source
- Document30-12-2023.pdf · uploaded 8 Mar 2025Source
- Document30-03-2024.pdf · uploaded 8 Mar 2025Source
- Document29-06-2024.pdf · uploaded 8 Mar 2025Source
- Document31-12-2024.pdf · uploaded 8 Mar 2025Source
- Document30-09-2024.pdf · uploaded 8 Mar 2025Source
- DocumentSkylight FORM 1 MARCH 2025.pdf · uploaded 19 Apr 2025Source
Technical (Engineer)
- DocumentForm 2.pdf · uploaded 23 Feb 2024Source
- DocumentForm 2 31-03-2018.pdf · uploaded 8 Mar 2025Source
- DocumentForm 2 31-03-2019.pdf · uploaded 8 Mar 2025Source
- DocumentForm 2 31-03-2020.pdf · uploaded 8 Mar 2025Source
- DocumentForm 2 31-03-2021.pdf · uploaded 8 Mar 2025Source
- DocumentForm 2 31-03-2022.pdf · uploaded 8 Mar 2025Source
- DocumentForm 2 31-03-2023.pdf · uploaded 8 Mar 2025Source
- DocumentForm 2 30-06-2023.pdf · uploaded 8 Mar 2025Source
- DocumentForm 2 30-09-2023.pdf · uploaded 8 Mar 2025Source
- DocumentForm 2 31-12-2023.pdf · uploaded 8 Mar 2025Source
- DocumentForm 2 31-03-2024.pdf · uploaded 8 Mar 2025Source
- DocumentForm 2 30-06-2024.pdf · uploaded 8 Mar 2025Source
- DocumentForm 2 30-06-2024.pdf · uploaded 8 Mar 2025Source
- DocumentForm 2 30-09-2024.pdf · uploaded 8 Mar 2025Source
- DocumentForm 2 31-12-2024.pdf · uploaded 8 Mar 2025Source
- DocumentSkylights Form 2 Dated Mar 25.pdf · uploaded 19 Apr 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsGAT 2444
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, 1BHK, Row house, Rowhouse479 units in all
- Address
- GAT 24-44, Off Bavadi Road, WagholiPIN 412207
- Village
- Wagholi, Haveli taluka
- Location
- 18.58621, 73.98462
- Designated bank account
- 119
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Boundaries
- North
- Gat No 50
- South
- 570
- East
- Gat No 570
- West
- Gat No 46
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking479 units
389 of 479 units booked (81%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| C Wing | 2BHK | 38.89 sq m · 419 sq ft | 9 | 9 |
| C Wing | 2BHK | 39.89 sq m · 429 sq ft | 1 | 1 |
| C Wing | 2BHK | 41.99 sq m · 452 sq ft | 12 | 12 |
| C Wing | 2BHK | 46.45 sq m · 500 sq ft | 1 | 0 |
| C Wing | 2BHK | 50.55 sq m · 544 sq ft | 12 | 12 |
| C Wing | 2BHK | 50.82 sq m · 547 sq ft | 36 | 36 |
| C Wing | 2BHK | 51.04 sq m · 549 sq ft | 12 | 12 |
| C Wing | 2BHK | 54.3 sq m · 584 sq ft | 12 | 11 |
Show all 33 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| D Wing | 2BHK | 38.89 sq m · 419 sq ft | 7 | 0 |
| D Wing | 2BHK | 50.55 sq m · 544 sq ft | 1 | 0 |
| D Wing | 2BHK | 54.16 sq m · 583 sq ft | 21 | 20 |
| D Wing | 2BHK | 58.06 sq m · 625 sq ft | 2 | 2 |
| D Wing | 2BHK | 69.59 sq m · 749 sq ft | 54 | 54 |
| D Wing | 2BHK | 82.77 sq m · 891 sq ft | 10 | 10 |
| E Wing | 1BHK | 38.89 sq m · 419 sq ft | 1 | 0 |
| E Wing | 1BHK | 39.31 sq m · 423 sq ft | 47 | 42 |
| E Wing | 2BHK | 59.33 sq m · 639 sq ft | 36 | 36 |
| E Wing | 2BHK | 59.69 sq m · 642 sq ft | 12 | 12 |
| F Wing | 2BHK | 38.89 sq m · 419 sq ft | 8 | 0 |
| F Wing | 2BHK | 54.16 sq m · 583 sq ft | 21 | 20 |
| F Wing | 2BHK | 69.59 sq m · 749 sq ft | 56 | 56 |
| F Wing | 2BHK | 82.77 sq m · 891 sq ft | 10 | 10 |
| G Wing | 1BHK | 82.06 sq m · 883 sq ft | 10 | 6 |
| G Wing | 2BHK | 46.45 sq m · 500 sq ft | 2 | 0 |
| G Wing | 2BHK | 54.16 sq m · 583 sq ft | 21 | 9 |
| G Wing | 2BHK | 57.59 sq m · 620 sq ft | 2 | 0 |
| G Wing | 2BHK | 57.87 sq m · 623 sq ft | 2 | 0 |
| G Wing | 2BHK | 58.06 sq m · 625 sq ft | 2 | 0 |
| G Wing | 2BHK | 68.41 sq m · 736 sq ft | 34 | 9 |
| G Wing | 2BHK | 68.88 sq m · 741 sq ft | 22 | 10 |
| Row House 1 | Row house | 46.45 sq m · 500 sq ft | 1 | 0 |
| Row House 2 | Rowhouse | 58.06 sq m · 625 sq ft | 1 | 0 |
| Row House 3 | Row house | 58.06 sq m · 625 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals11
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Cubix Architect And Associate | — |
| Chartered accountant | P B Shah | — |
| Engineer | Stucture Vizion | — |
| Other | Zohan Constructions | — |
| Registered real estate agent | 360 Realtors LLP | — |
| Registered real estate agent | Bharat Chandanmal Kothari | — |
| Registered real estate agent | Mansoor Kutubuddin Polan | — |
| Registered real estate agent | Nitin Shankar Kadde | — |
Show all 11 professionalsShow fewer professionals
| Role | Name | Registration no. |
|---|---|---|
| Registered real estate agent | Optimus Realtors | — |
| Registered real estate agent | Property Pointer Private Limited | — |
| Registered real estate agent | R-Constellation Pvt. Ltd. | — |
Source: MahaRERA project page. Contact details are not shown.