Deedo IDDP-PUN-X4SPIts promised completion date, Apr 2026, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 68% of its units are booked.
Wagholi, Pune 412207 · Property rates in Wagholi · Promoter: Tushar Pramod Nagarkar
Its promised completion date, Apr 2026, has passed and MahaRERA does not show it completed
- This projectRegistered 31 Jul 2017, completion promised 30 Apr 2026, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100002281
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100002281 | 31 Jul 2017 | 30 Apr 2026 | 30 Apr 2026 | Tushar Pramod Nagarkar | Project page |
Documents139
2 documents held by Deedo, 137 filings listed on MahaRERA's project page
Finance
- PAN CardPAN.PDF · uploaded 26 Jul 2017Source
Legal
- Legal Title reportTITLE NOTE.PDF · uploaded 26 Jul 2017Source
- Declaration Form BRERA FORM B TUSHAR NAGARKAR.pdf · uploaded 26 Jul 2017Source
- OtherPage No 1 To 10 out of 31.pdf · uploaded 31 Aug 2017Source
- OtherPage No 11 To 20 out of 31.pdf · uploaded 31 Aug 2017Source
- OtherPAge No 21 to 31 out of 31.pdf · uploaded 31 Aug 2017Source
Show all 139 documentsShow fewer documents
Legal
Migrated
- 1 PAN CardPAN.PDF · uploaded 26 Jul 2017Source
- 1 Copy of the legal title reportTITLE NOTE.PDF · uploaded 26 Jul 2017Source
- 1 Details of encumbrancesENCUMBRANCE.pdf · uploaded 26 Jul 2017Source
- 1 Copy of Layout Approval (in case of layout)Map-01-07.pdf · uploaded 26 Jul 2017Source
- 2 Copy of Layout Approval (in case of layout)Map-02-07.pdf · uploaded 26 Jul 2017Source
- 3 Copy of Layout Approval (in case of layout)Map-04-07.pdf · uploaded 26 Jul 2017Source
- 4 Copy of Layout Approval (in case of layout)Map-05-07.pdf · uploaded 26 Jul 2017Source
- 5 Copy of Layout Approval (in case of layout)Map-06-07.pdf · uploaded 26 Jul 2017Source
- 1 Building Plan Approval (IOD)COMMINCE LETTER.pdf · uploaded 26 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMINCE LETTER.pdf · uploaded 26 Jul 2017Source
- 1 Declaration in FORM BRERA FORM B TUSHAR NAGARKAR.pdf · uploaded 26 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCH CERTIFICATE.pdf · uploaded 26 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERTIFICATE.pdf · uploaded 26 Jul 2017Source
- 1 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 26 Jul 2017Source
- 1 Proforma of Allotment letterLake Tower _Agreement Draft.pdf · uploaded 26 Jul 2017Source
- 2 Proforma of Allotment letterallottement letter.pdf · uploaded 26 Jul 2017Source
- 2 Details of encumbrancesencumbrance affidavit-min.pdf · uploaded 31 Aug 2017Source
- 2 Declaration in FORM Bform b declaration.pdf · uploaded 31 Aug 2017Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 31 Aug 2017Source
- 2 Certificates of CA (Form 3)CA CERTIFICATE.pdf · uploaded 31 Aug 2017Source
- 3 Proforma of Allotment letterPage No 1 To 10 out of 26.pdf · uploaded 31 Aug 2017Source
- 4 Proforma of Allotment letterPage No 10 To 20 out of 26.pdf · uploaded 31 Aug 2017Source
- 5 Proforma of Allotment letterPage no 21 To 26 out of 26.pdf · uploaded 31 Aug 2017Source
- 1 OtherPage No 1 To 10 out of 31.pdf · uploaded 31 Aug 2017Source
- 2 OtherPage No 11 To 20 out of 31.pdf · uploaded 31 Aug 2017Source
- 3 OtherPAge No 21 to 31 out of 31.pdf · uploaded 31 Aug 2017Source
- 4 OtherCORRECTION DEED DA.pdf · uploaded 31 Aug 2017Source
- 3 Details of encumbrancesNew Doc 2018-08-18.pdf · uploaded 24 Aug 2018Source
- 1 Certificates of CA (Form 5)Form 5.pdf · uploaded 15 Oct 2018Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)VA_RERA_NC-LT_ARCHITECT CERTIFICATE 03.pdf · uploaded 9 Jun 2021Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer certificate-compressed.pdf · uploaded 9 Jun 2021Source
- 2 Certificates of CA (Form 5)FORM 5 - 2018-19.pdf · uploaded 14 Jun 2021Source
- 3 Certificates of CA (Form 5)FORM 5 - 2019-20.pdf · uploaded 14 Jun 2021Source
- 1 Disclosure of sold/ booked inventoryRERA - Sold Flat.pdf · uploaded 15 Jun 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORM 5 - 2018-19.pdf · uploaded 15 Jun 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 - 2019-20.pdf · uploaded 15 Jun 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A.pdf · uploaded 18 Jun 2021Source
- 2 Disclosure of sold/ booked inventorySOLD INVENTORY.pdf · uploaded 18 Jun 2021Source
- 1 Details of Restarting of Construction work post lockdownPOST LOCKDOWN CONST.pdf · uploaded 18 Jun 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)SITE ENGINEER CERTIFICATE FORM 2 A.pdf · uploaded 23 Mar 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)CA CERTIFICTE - FORM 5.pdf · uploaded 23 Mar 2022Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1.pdf · uploaded 24 Mar 2022Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2.pdf · uploaded 24 Mar 2022Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2 A.pdf · uploaded 24 Mar 2022Source
- 3 Certificates of CA (Form 3)FORM 3 (1).pdf · uploaded 24 Mar 2022Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE.pdf · uploaded 8 Jul 2022Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERTIFICATE.pdf · uploaded 8 Jul 2022Source
- 1 CERSAI detailsARCHITECT CERTIFICATE.pdf · uploaded 8 Jul 2022Source
- 3 Disclosure of sold/ booked inventorySOLD FLATS.pdf · uploaded 20 Jul 2022Source
- 4 Disclosure of sold/ booked inventorySOLD FLATS.pdf · uploaded 20 Jul 2022Source
- 4 Certificates of CA (Form 3)CA CERTIFICATE.pdf · uploaded 20 Jul 2022Source
- 2 CERSAI detailsCERSAI REPORT.pdf · uploaded 10 Oct 2022Source
- 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE20221107_17245641.pdf · uploaded 8 Nov 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5.pdf · uploaded 18 Nov 2022Source
- 5 Disclosure of sold/ booked inventorySOLD AND UNSOLD INVENTORY20221217_10265307.pdf · uploaded 17 Dec 2022Source
- 4 a Details of encumbrances concerned to FinanceLEGAL.pdf · uploaded 26 Dec 2022Source
- 1 b Details of encumbrances concerned to LegalLEGAL.pdf · uploaded 26 Dec 2022Source
- 1 Declaration about Commencement CertificateCOMMECEMENT.pdf · uploaded 26 Dec 2022Source
- 1 Proforma of Agreement for saleAgreement.pdf · uploaded 26 Dec 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSEPREATE BANK ESCORW ACCOUNT.pdf · uploaded 26 Dec 2022Source
- 1 Deviation Report with respect to Allotment letterALLOTMENT LETTER.pdf · uploaded 26 Dec 2022Source
- 1 Deviation Report with respect to model copy of AgreementMODEL COPY OF AGREEMENT.pdf · uploaded 26 Dec 2022Source
- 2 Deviation Report with respect to model copy of AgreementAGREEMENT FOR SALE.pdf · uploaded 26 Dec 2022Source
- 6 Disclosure of sold/ booked inventorySOLD UNSOLD INVENTORY20221227_12363739.pdf · uploaded 27 Dec 2022Source
- 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE DEC 2022.pdf · uploaded 20 Jan 2023Source
- 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEERS CRTIFICATE OCT 2022.pdf · uploaded 20 Jan 2023Source
- 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEERS CRTIFICATE DEC 2022.pdf · uploaded 20 Jan 2023Source
- 5 Certificates of CA (Form 3)CA CERTIFICATE FORM 320230120_13574305.pdf · uploaded 20 Jan 2023Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)SOCIETY FORMATION REGISTRATION20230426_17103918.pdf · uploaded 26 Apr 2023Source
- 6 Certificates of CA (Form 3)FORM 3 DEC 2022.pdf · uploaded 29 Apr 2023Source
- 7 Disclosure of sold/ booked inventoryAdobe Scan 04-May-2023.pdf · uploaded 5 May 2023Source
- 7 Certificates of CA (Form 3)Form3 Dec2022 (2).pdf · uploaded 15 Sep 2023Source
- 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 -2024.pdf · uploaded 27 Feb 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)form2A21-22.pdf · uploaded 27 Feb 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)form 2 A22-23.pdf · uploaded 27 Feb 2024Source
- 8 Certificates of CA (Form 3)Form3 - 2024.pdf · uploaded 27 Feb 2024Source
- 1 Home Buyer /Allottee Grievance Redressal Cellfreecompress-Revised Final Settlement Agreement - Project Lake Tower (1).pdf · uploaded 27 Feb 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 2022-23.pdf · uploaded 7 Mar 2024Source
- 9 Certificates of CA (Form 3)Form3-march23.pdf · uploaded 12 Mar 2024Source
- 10 Certificates of CA (Form 3)form3-june23.pdf · uploaded 12 Mar 2024Source
- 11 Certificates of CA (Form 3)Form3-sep23.pdf · uploaded 12 Mar 2024Source
- 12 Certificates of CA (Form 3)Form3-dec23.pdf · uploaded 12 Mar 2024Source
- 3 Declaration in FORM BFormB2024.pdf · uploaded 13 Mar 2024Source
- 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form1 2023.pdf · uploaded 13 Mar 2024Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form5-2024.pdf · uploaded 13 Mar 2024Source
- Form 1mar form1.pdf · uploaded 8 Sep 2025Source
- Form 2mar form2.pdf · uploaded 8 Sep 2025Source
- Form 3Form3 31-3-2025.pdf · uploaded 8 Sep 2025Source
- Disclosure of Sold and Booked InventorySold unsold inventory.pdf · uploaded 8 Sep 2025Source
- Withdrawal Update Form 1MAY form1.pdf · uploaded 8 Sep 2025Source
- Withdrawal Update Form 2MAY form2.pdf · uploaded 8 Sep 2025Source
- Withdrawal Update Form 3Form3 29-5-2025.pdf · uploaded 8 Sep 2025Source
- Withdrawal Update Form 1form 1-may 2025.pdf · uploaded 9 Mar 2026Source
- Withdrawal Update Form 1form 1-may 2025.pdf · uploaded 9 Mar 2026Source
- Withdrawal Update Form 1form 1-may 2025.pdf · uploaded 9 Mar 2026Source
- Withdrawal Update Form 2form 2-may 2025.pdf · uploaded 9 Mar 2026Source
- Withdrawal Update Form 2form 2-may 2025.pdf · uploaded 9 Mar 2026Source
- Withdrawal Update Form 2form 2-may 2025.pdf · uploaded 9 Mar 2026Source
- Withdrawal Update Form 3form 3-may 2025.pdf · uploaded 9 Mar 2026Source
- Withdrawal Update Form 3form 3-may 2025.pdf · uploaded 9 Mar 2026Source
- Withdrawal Update Form 3form 3-may 2025.pdf · uploaded 9 Mar 2026Source
- Form 2A (FY 2025-2026)Form 2A 2025-26.pdf · uploaded 17 Apr 2026Source
- Withdrawal Update Form 1form 1-may 2025.pdf · uploaded 18 Apr 2026Source
- Withdrawal Update Form 2form 2-may 2025.pdf · uploaded 18 Apr 2026Source
- Withdrawal Update Form 3Form 3 March 2026.pdf · uploaded 18 Apr 2026Source
- Form 5 (FY 2025-2026)Form5 25-26.pdf · uploaded 18 Apr 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 30 Apr 2026Source
- Withdrawal Update Form 2Form 2 (6).pdf · uploaded 30 Apr 2026Source
- Withdrawal Update Form 3Form 3 March 2026.pdf · uploaded 30 Apr 2026Source
- Occupational CertificateFull OC B wing along with declaration.pdf · uploaded 7 May 2026Source
Technical
- DocumentMap-01-07.pdf · uploaded 26 Jul 2017Source
- DocumentMap-02-07.pdf · uploaded 26 Jul 2017Source
- DocumentMap-04-07.pdf · uploaded 26 Jul 2017Source
- DocumentMap-05-07.pdf · uploaded 26 Jul 2017Source
- DocumentMap-06-07.pdf · uploaded 26 Jul 2017Source
- DocumentCOMMINCE LETTER.pdf · uploaded 26 Jul 2017Source
- DocumentMap-01-07-layout plan.pdf · uploaded 24 Apr 2026Source
- DocumentMap-03-07_compressed (1).pdf · uploaded 24 Apr 2026Source
- Documentplan 1 highlighted.pdf · uploaded 30 Apr 2026Source
- Documentplan 2.pdf · uploaded 30 Apr 2026Source
- Documentplan 3.pdf · uploaded 30 Apr 2026Source
- Documentplan 4.pdf · uploaded 30 Apr 2026Source
- Documentplan 5.pdf · uploaded 30 Apr 2026Source
- Documentplan 6.pdf · uploaded 30 Apr 2026Source
- Documentplan 7.pdf · uploaded 30 Apr 2026Source
- Documenthighlighted building approval plan.pdf · uploaded 30 Apr 2026Source
Technical (Architect)
- DocumentForm 1.pdf · uploaded 27 Apr 2026Source
Technical (Engineer)
- DocumentForm 2 (6).pdf · uploaded 30 Apr 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsPlot No 217 Gat NO 1420
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2.5 BHK, 2BHK, 3BHK87 units in all
- Address
- Plot No 217 Gat NO 1420, PUNE - NAGAR HIGHWAY, WAGHOLI, PUNEPIN 412207
- Village
- Wagholi, Haveli taluka
- Location
- 18.69838, 73.53287
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- BY Open Space No 1
- South
- BY A Type building of Hotel
- East
- BY Remaining Plot No 217
- West
- BY 12 m Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking87 units
59 of 87 units booked (68%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2.5 BHK | 56.07 sq m · 604 sq ft | 4 | 2 |
| 2.5 BHK | 56.59 sq m · 609 sq ft | 1 | 1 |
| 2.5 BHK | 60.71 sq m · 653 sq ft | 11 | 6 |
| 2BHK | 47.58 sq m · 512 sq ft | 11 | 8 |
| 2BHK | 51.29 sq m · 552 sq ft | 21 | 16 |
| 2BHK | 51.99 sq m · 560 sq ft | 11 | 5 |
| 2BHK | 56.01 sq m · 603 sq ft | 6 | 6 |
| 3BHK | 82.39 sq m · 887 sq ft | 22 | 15 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals9
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Praveen Desai | — |
| Architect | Vikas Achalkar | — |
| Engineer | Mahadev J Borade | — |
| Engineer | Sagar D Tapsale | — |
| Other | Ace Consultants | — |
| Other | Dinesh Sharma | — |
| Other | Harsh Enterprises | — |
| Other | Parag Chopda | — |
| Other | Zopate Electricals Consultancy Pvt Ltd | — |
Source: MahaRERA project page. Contact details are not shown.