Plotted · 163 unitsRERA P52100029099

Passport

Deedo IDDP-PUN-XTDY

Its promised completion date, Dec 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 9% of its units are booked.

Vanpuri, Pune 412301 · by Urban Realty, Urban Realty

Delivery1 yr 11 mo past duePromised Dec 2024 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales9% booked15 of 163 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Dec 2024, has passed and MahaRERA does not show it completed

  • This projectRegistered 26 Apr 2021, completion promised 31 Dec 2024, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.
Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100029099
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210002909926 Apr 202131 Dec 202431 Dec 2024Urban RealtyProject page
Documents48

2 documents held by Deedo, 46 filings listed on MahaRERA's project page

Registration certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardUrban Realty Pan.pdf · uploaded 11 Apr 2021Source

Legal

  • Legal Title reportTSR_compressed.pdf · uploaded 11 Apr 2021Source
  • Declaration Form BForm B_compressed.pdf · uploaded 11 Apr 2021Source
  • Declaration Form BForm B.pdf · uploaded 3 Dec 2024Source

Migrated

  • 1 PAN CardUrban Realty Pan.pdf · uploaded 11 Apr 2021Source
  • 1 Copy of the legal title reportTSR_compressed.pdf · uploaded 11 Apr 2021Source
Show all 48 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesDetails of encumbrances.pdf · uploaded 11 Apr 2021Source
  • 1 Copy of Layout Approval (in case of layout)Saction Plan.pdf · uploaded 11 Apr 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentComencement Certificate.pdf · uploaded 11 Apr 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentComencement Certificate.pdf · uploaded 11 Apr 2021Source
  • 1 Declaration in FORM BForm B_compressed.pdf · uploaded 11 Apr 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3Passport200321_compressed.pdf · uploaded 11 Apr 2021Source
  • 1 Proforma of Allotment letterDeclaration for RERA Agreement.pdf · uploaded 11 Apr 2021Source
  • 1 Declaration about Commencement CertificateDisclouser Of Sold Unsold Unit.pdf · uploaded 28 Feb 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 3 Signed_compressed-compressed.pdf · uploaded 28 Feb 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 28 Feb 2022Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Signed_compressed-compressed.pdf · uploaded 28 Feb 2022Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE.pdf · uploaded 27 Apr 2022Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 27 Apr 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5.pdf · uploaded 27 Apr 2022Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 25 Jul 2022Source
  • 1 Disclosure of sold/ booked inventoryDisclouser Of Sold Unsold Unit.pdf · uploaded 25 Jul 2022View
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM3.pdf · uploaded 25 Jul 2022Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Form 9th oct22.pdf · uploaded 14 Oct 2022Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Rera -passport-upto 30_09_2022_compressed.pdf · uploaded 14 Oct 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect.pdf · uploaded 24 Jan 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Form 11th Jan 23.pdf · uploaded 24 Jan 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)form3-1-compressed.pdf · uploaded 24 Jan 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Form Jun23.pdf · uploaded 21 Aug 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Form 3.pdf · uploaded 21 Aug 2023Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Form JUNE 23.pdf · uploaded 4 Dec 2023Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Form SEPT 23.pdf · uploaded 4 Dec 2023Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Certificate - 30-6_compressed.pdf · uploaded 4 Dec 2023Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Certificate - 30-9_compressed.pdf · uploaded 4 Dec 2023Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)SELF DECLARATION- Form 3.pdf · uploaded 24 Feb 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)form 5 (22-23) (2).pdf · uploaded 6 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)URBAN REALTY FORM 5 (2).pdf · uploaded 6 Mar 2024Source
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)SELF DECLARATION.pdf · uploaded 2 Jul 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Self Declaration.pdf · uploaded 8 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Self Declaration.pdf · uploaded 8 Oct 2024Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 3 Dec 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Self Declaration New 1.pdf · uploaded 18 Feb 2025Source

Technical

  • DocumentSaction Plan.pdf · uploaded 11 Apr 2021Source
  • DocumentComencement Certificate.pdf · uploaded 11 Apr 2021Source

Technical (Architect)

  • Documentarchitect.pdf · uploaded 24 Jan 2023Source

Technical (Engineer)

  • DocumentEngineer Certificate Form SEPT 23.pdf · uploaded 4 Dec 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Gat No 22 Part

As registered with MahaRERA and published on its project page

Project type
Plotted
Status on MahaRERA
Certificate Signed
Address
Gat No 22 Part, Vanpuri, VanpuriPIN 412301
Village
Vanpuri, Purandhar taluka
Land area for this project
42,437 sq m (4,56,788 sq ft)
Permissible built-up area
53,856 sq m (5,79,701 sq ft)
Sanctioned built-up area
53,856 sq m (5,79,701 sq ft)
Recreational open space
7,040 sq m (75,778 sq ft)
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

Gat No 22 Part

Land as published on MahaRERA's project page

Gat No 22 Part

Boundaries

North
Gat No 38
South
Gat No 18 Gat No 20
East
Gat No 23 Gat No 24
West
Gat No 22 Part

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectCubix Artictect—
Chartered accountantS.K.P.N & Associates—
Chartered accountantVishal Lunavat & Co—
EngineerPankaj Navalakha—
OtherR. T. Sabarwal—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology