Others · 1 building · 126 unitsRERA P52100031653

Trimurti Spaces

Deedo IDDP-PUN-HEV2

Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 0% of its units are booked.

Undri, Pune 411060 · Property rates in Undri · Promoter: Bridgestone Landmarks LLP

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 126 units · as the promoter reported to MahaRERA
Trimurti Spaces project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 3 Nov 2021, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100031653
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000316533 Nov 202131 Dec 202630 Apr 2027Bridgestone Landmarks LLPProject page
Documents96

1 document held by Deedo, 95 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardBridgestone Pan Card.pdf · uploaded 23 Mar 2021Source

Legal

  • Legal Title reportLegal title report.pdf · uploaded 19 Oct 2021Source
  • OtherAffidavit for Land Ownership.pdf · uploaded 20 Oct 2021Source
  • Declaration Form BForm B Rera.pdf · uploaded 20 Oct 2021Source

Migrated

  • 1 PAN CardBridgestone Pan Card.pdf · uploaded 23 Mar 2021Source
  • 1 Proforma of Allotment letterTrimurti Spaces Draft_Allotment_Letter.pdf · uploaded 19 Jun 2021Source
  • 2 Proforma of Allotment letterDraft Agreement-Bridgestone.pdf · uploaded 1 Jul 2021Source
Show all 96 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)1-4_compressed (1).pdf · uploaded 7 Oct 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate_compressed.pdf · uploaded 7 Oct 2021Source
  • 1 Copy of the legal title reportLegal title report.pdf · uploaded 19 Oct 2021Source
  • 1 Details of encumbrancesEncumbrance Certificate.pdf · uploaded 19 Oct 2021Source
  • 1 Building Plan Approval / NA Order for plotted development2-4_compressed.pdf · uploaded 19 Oct 2021Source
  • 2 Building Plan Approval / NA Order for plotted development3-4_compressed.pdf · uploaded 19 Oct 2021Source
  • 3 Building Plan Approval / NA Order for plotted development4-4_compressed.pdf · uploaded 19 Oct 2021Source
  • 1 Declaration about Commencement CertificateDeclaration from commencement certificate.pdf · uploaded 19 Oct 2021Source
  • 1 Declaration in FORM BForm B Rera.pdf · uploaded 20 Oct 2021Source
  • 1 OtherAffidavit for Land Ownership.pdf · uploaded 20 Oct 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 compressed.pdf · uploaded 21 Oct 2021Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 2 Dec 2021Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory.pdf · uploaded 19 Jan 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Bridgestone -Rera Annual Reports Final.pdf · uploaded 4 Oct 2022Source
  • 2 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory.pdf · uploaded 12 Dec 2022Source
  • 3 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory.pdf · uploaded 9 Jan 2023Source
  • 4 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory Q4.pdf · uploaded 24 Jun 2023Source
  • 5 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory Q1.pdf · uploaded 7 Jul 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Bridgestone Rera-Annual Reports Final.pdf · uploaded 26 Sep 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer FORM 2.pdf · uploaded 29 Sep 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer FORM 2.pdf · uploaded 29 Sep 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 BRIDGESTONE _compressed.pdf · uploaded 29 Sep 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form -3 BRIDGESTONE compressed.pdf · uploaded 29 Sep 2023Source
  • 6 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory Q2.pdf · uploaded 7 Oct 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form -3.pdf · uploaded 24 Nov 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Form 1.pdf · uploaded 25 Nov 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Form 1.pdf · uploaded 25 Nov 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Artichtect Certificate Form 1.pdf · uploaded 25 Nov 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form -2 Bridgestone Landmark LLP.pdf · uploaded 25 Nov 2023Source
  • 7 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory Q3.pdf · uploaded 6 Jan 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 7 Feb 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form -3.pdf · uploaded 8 Feb 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 22 Feb 2024Source
  • 8 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory Q4.pdf · uploaded 6 Apr 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 11 Apr 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_compressed.pdf · uploaded 25 Apr 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 29 Apr 2024Source
  • 9 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory Q1.pdf · uploaded 6 Jul 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 11 Jul 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 19 Jul 2024Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form -3.pdf · uploaded 2 Aug 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 19 Oct 2024Source
  • 2 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory Q2.pdf · uploaded 24 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Bridgestone Rera-Annual Reports statement.pdf · uploaded 24 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 19 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)From 3_compressed.pdf · uploaded 25 Nov 2024Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory Q3.pdf · uploaded 9 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 7 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 7 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 7 Feb 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory Q4.pdf · uploaded 8 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 18 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3.pdf · uploaded 30 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2.pdf · uploaded 30 Apr 2025Source
  • Form 2A (FY 2024-2025)Form-2A.pdf · uploaded 11 Aug 2025Source
  • Withdrawal Update Form 1Form-1.pdf · uploaded 12 Aug 2025Source
  • Withdrawal Update Form 2Form-2.pdf · uploaded 12 Aug 2025Source
  • Withdrawal Update Form 3Form-3.pdf · uploaded 12 Aug 2025Source
  • Form 5 (FY 2024-2025)Form-5.pdf · uploaded 19 Sep 2025Source
  • Withdrawal Update Form 1Form-1.pdf · uploaded 29 Oct 2025Source
  • Withdrawal Update Form 2Form-2.pdf · uploaded 29 Oct 2025Source
  • Withdrawal Update Form 3Form-3_compressed (3).pdf · uploaded 29 Oct 2025Source
  • Withdrawal Update Form 1Form-1.pdf · uploaded 21 Jan 2026Source
  • Withdrawal Update Form 2Form-2.pdf · uploaded 21 Jan 2026Source
  • Withdrawal Update Form 3Form-3.pdf · uploaded 21 Jan 2026Source
  • Withdrawal Update Form 1Form-1.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 2Form-2.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 3Form-3.pdf · uploaded 21 Apr 2026Source
  • Form 2A (FY 2025-2026)Form-2A.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 1Form-1.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 1Form-1.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 2Form-2.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 2Form-2.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 3Form-3.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 3Form-3_compressed.pdf · uploaded 27 Jul 2026Source
  • Form 5 (FY 2025-2026)Bridgestone Form 5-Final.pdf · uploaded 14 Aug 2026Source

Technical

  • Document1-4_compressed (1).pdf · uploaded 7 Oct 2021Source
  • Document2-4_compressed.pdf · uploaded 19 Oct 2021Source
  • Document3-4_compressed.pdf · uploaded 19 Oct 2021Source
  • Document4-4_compressed.pdf · uploaded 19 Oct 2021Source

Technical (Architect)

  • DocumentForm 1.pdf · uploaded 19 Oct 2024Source
  • DocumentForm 1.pdf · uploaded 7 Feb 2025Source
  • DocumentForm 1.pdf · uploaded 18 Apr 2025Source
  • DocumentForm-1.pdf · uploaded 27 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 19 Nov 2024Source
  • DocumentForm 2.pdf · uploaded 7 Feb 2025Source
  • DocumentForm-2.pdf · uploaded 30 Apr 2025Source
  • DocumentForm-2.pdf · uploaded 27 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsSr. No. 26/4B

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
—126 units in all
Address
Sr. No. 26/4B, Near Undri Chowk, UndriPIN 411060
Village
Undri, Haveli taluka
Designated bank account
230
Developed in phases
No

Survey, CTS, gat or plot numbers

Sr. No. 26/4B

Boundaries

North
26 part
South
Katraj Kondhwa Saswad Road
East
26 Part
West
26 Part

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking126 units

126 units registered

— · 126 units
TypeCarpet areaUnits
——126

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDeepak Honkan—
Chartered accountantVinay Chordia—
EngineerSudhir Sheth—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology