Deedo IDDP-PUN-HEV2Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 0% of its units are booked.
Undri, Pune 411060 · Property rates in Undri · Promoter: Bridgestone Landmarks LLP
Completion was pushed back 4 months, to Apr 2027
- This projectRegistered 3 Nov 2021, completion promised 31 Dec 2026, revised to 30 Apr 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100031653
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100031653 | 3 Nov 2021 | 31 Dec 2026 | 30 Apr 2027 | Bridgestone Landmarks LLP | Project page |
Documents96
1 document held by Deedo, 95 filings listed on MahaRERA's project page
Finance
- PAN CardBridgestone Pan Card.pdf · uploaded 23 Mar 2021Source
Legal
Show all 96 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)1-4_compressed (1).pdf · uploaded 7 Oct 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate_compressed.pdf · uploaded 7 Oct 2021Source
- 1 Copy of the legal title reportLegal title report.pdf · uploaded 19 Oct 2021Source
- 1 Details of encumbrancesEncumbrance Certificate.pdf · uploaded 19 Oct 2021Source
- 1 Building Plan Approval / NA Order for plotted development2-4_compressed.pdf · uploaded 19 Oct 2021Source
- 2 Building Plan Approval / NA Order for plotted development3-4_compressed.pdf · uploaded 19 Oct 2021Source
- 3 Building Plan Approval / NA Order for plotted development4-4_compressed.pdf · uploaded 19 Oct 2021Source
- 1 Declaration about Commencement CertificateDeclaration from commencement certificate.pdf · uploaded 19 Oct 2021Source
- 1 Declaration in FORM BForm B Rera.pdf · uploaded 20 Oct 2021Source
- 1 OtherAffidavit for Land Ownership.pdf · uploaded 20 Oct 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 compressed.pdf · uploaded 21 Oct 2021Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 2 Dec 2021Source
- 1 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory.pdf · uploaded 19 Jan 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Bridgestone -Rera Annual Reports Final.pdf · uploaded 4 Oct 2022Source
- 2 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory.pdf · uploaded 12 Dec 2022Source
- 3 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory.pdf · uploaded 9 Jan 2023Source
- 4 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory Q4.pdf · uploaded 24 Jun 2023Source
- 5 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory Q1.pdf · uploaded 7 Jul 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Bridgestone Rera-Annual Reports Final.pdf · uploaded 26 Sep 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer FORM 2.pdf · uploaded 29 Sep 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer FORM 2.pdf · uploaded 29 Sep 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 BRIDGESTONE _compressed.pdf · uploaded 29 Sep 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form -3 BRIDGESTONE compressed.pdf · uploaded 29 Sep 2023Source
- 6 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory Q2.pdf · uploaded 7 Oct 2023Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form -3.pdf · uploaded 24 Nov 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Form 1.pdf · uploaded 25 Nov 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Form 1.pdf · uploaded 25 Nov 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Artichtect Certificate Form 1.pdf · uploaded 25 Nov 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form -2 Bridgestone Landmark LLP.pdf · uploaded 25 Nov 2023Source
- 7 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory Q3.pdf · uploaded 6 Jan 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 7 Feb 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form -3.pdf · uploaded 8 Feb 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 22 Feb 2024Source
- 8 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory Q4.pdf · uploaded 6 Apr 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 11 Apr 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_compressed.pdf · uploaded 25 Apr 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 29 Apr 2024Source
- 9 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory Q1.pdf · uploaded 6 Jul 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 11 Jul 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 19 Jul 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form -3.pdf · uploaded 2 Aug 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 19 Oct 2024Source
- 2 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory Q2.pdf · uploaded 24 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Bridgestone Rera-Annual Reports statement.pdf · uploaded 24 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 19 Nov 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)From 3_compressed.pdf · uploaded 25 Nov 2024Source
- 1 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory Q3.pdf · uploaded 9 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 7 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 7 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 7 Feb 2025Source
- 1 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory Q4.pdf · uploaded 8 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 18 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3.pdf · uploaded 30 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2.pdf · uploaded 30 Apr 2025Source
- Form 2A (FY 2024-2025)Form-2A.pdf · uploaded 11 Aug 2025Source
- Withdrawal Update Form 1Form-1.pdf · uploaded 12 Aug 2025Source
- Withdrawal Update Form 2Form-2.pdf · uploaded 12 Aug 2025Source
- Withdrawal Update Form 3Form-3.pdf · uploaded 12 Aug 2025Source
- Form 5 (FY 2024-2025)Form-5.pdf · uploaded 19 Sep 2025Source
- Withdrawal Update Form 1Form-1.pdf · uploaded 29 Oct 2025Source
- Withdrawal Update Form 2Form-2.pdf · uploaded 29 Oct 2025Source
- Withdrawal Update Form 3Form-3_compressed (3).pdf · uploaded 29 Oct 2025Source
- Withdrawal Update Form 1Form-1.pdf · uploaded 21 Jan 2026Source
- Withdrawal Update Form 2Form-2.pdf · uploaded 21 Jan 2026Source
- Withdrawal Update Form 3Form-3.pdf · uploaded 21 Jan 2026Source
- Withdrawal Update Form 1Form-1.pdf · uploaded 21 Apr 2026Source
- Withdrawal Update Form 2Form-2.pdf · uploaded 21 Apr 2026Source
- Withdrawal Update Form 3Form-3.pdf · uploaded 21 Apr 2026Source
- Form 2A (FY 2025-2026)Form-2A.pdf · uploaded 12 May 2026Source
- Withdrawal Update Form 1Form-1.pdf · uploaded 27 Jul 2026Source
- Withdrawal Update Form 1Form-1.pdf · uploaded 27 Jul 2026Source
- Withdrawal Update Form 2Form-2.pdf · uploaded 27 Jul 2026Source
- Withdrawal Update Form 2Form-2.pdf · uploaded 27 Jul 2026Source
- Withdrawal Update Form 3Form-3.pdf · uploaded 27 Jul 2026Source
- Withdrawal Update Form 3Form-3_compressed.pdf · uploaded 27 Jul 2026Source
- Form 5 (FY 2025-2026)Bridgestone Form 5-Final.pdf · uploaded 14 Aug 2026Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsSr. No. 26/4B
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- —126 units in all
- Address
- Sr. No. 26/4B, Near Undri Chowk, UndriPIN 411060
- Village
- Undri, Haveli taluka
- Location
- 18.45320, 73.92445
- Designated bank account
- 230
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- 26 part
- South
- Katraj Kondhwa Saswad Road
- East
- 26 Part
- West
- 26 Part
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking126 units
126 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 126 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Deepak Honkan | — |
| Chartered accountant | Vinay Chordia | — |
| Engineer | Sudhir Sheth | — |
Source: MahaRERA project page. Contact details are not shown.