iLife Upper NIBM
Deedo IDDP-PUN-WSRDIts promised completion date, Dec 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 94% of its units are booked.
Undri, Pune 411060 · Property rates in Undri · Promoter: Legacy Fortune Associates
Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed
- This projectRegistered 26 May 2022, completion promised 31 Dec 2025, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100045658
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100045658 | 26 May 2022 | 31 Dec 2025 | 31 Dec 2025 | Legacy Fortune Associates | Project page |
Documents95
1 document held by Deedo, 94 filings listed on MahaRERA's project page
Legal
Migrated
- 1 Copy of the legal title reportTitle and Search Report - S No 24-1-1 UNDRI - Date 24-03-2022_compressed.pdf · uploaded 16 May 2022Source
- 1 Details of encumbrancesScan No Encumbrance Cert.pdf · uploaded 16 May 2022Source
- 1 Copy of Layout Approval (in case of layout)1647343915560_SP01 CC304821 dt31122021.pdf · uploaded 16 May 2022Source
- 2 Copy of Layout Approval (in case of layout)SP02 CC304821 dt31122021.pdf · uploaded 16 May 2022Source
- 3 Copy of Layout Approval (in case of layout)SP03 CC304821 dt31122021.pdf · uploaded 16 May 2022Source
Show all 95 documentsShow fewer documents
Migrated
- 4 Copy of Layout Approval (in case of layout)SP04 CC304821 dt31122021.pdf · uploaded 16 May 2022Source
- 5 Copy of Layout Approval (in case of layout)SP05 CC304821 dt31122021.pdf · uploaded 16 May 2022Source
- 6 Copy of Layout Approval (in case of layout)SP06 CC304821 dt31122021.pdf · uploaded 16 May 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentNA_compressed.pdf · uploaded 16 May 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentCC_compressed.pdf · uploaded 16 May 2022Source
- 1 Declaration about Commencement CertificateScan - Declaration_compressed.pdf · uploaded 16 May 2022Source
- 1 Declaration in FORM BScan- Form B_compressed.pdf · uploaded 16 May 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certi RERA.pdf · uploaded 16 May 2022Source
- 1 CERSAI detailsCERSAI_Search_Report_200237385780_For_Debtor_Based_Search_16_05_2022_15_22_34_177.pdf · uploaded 16 May 2022Source
- 1 Proforma of Allotment letterilovepdf_merged.pdf · uploaded 16 May 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)SKM_C224e22052107050_compressed.pdf · uploaded 21 May 2022Source
- 7 Copy of Layout Approval (in case of layout)PLAN-01-05_compressed.pdf · uploaded 6 Aug 2022Source
- 8 Copy of Layout Approval (in case of layout)PLAN-02-05_compressed.pdf · uploaded 6 Aug 2022Source
- 9 Copy of Layout Approval (in case of layout)PLAN-03-05_compressed.pdf · uploaded 6 Aug 2022Source
- 10 Copy of Layout Approval (in case of layout)PLAN-04-05_compressed.pdf · uploaded 6 Aug 2022Source
- 11 Copy of Layout Approval (in case of layout)PLAN-05-05_compressed.pdf · uploaded 6 Aug 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentCC-0040-22 DT 06-04-2022_compressed.pdf · uploaded 6 Aug 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 01.pdf · uploaded 11 Apr 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM02.pdf · uploaded 11 Apr 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM2A.pdf · uploaded 11 Apr 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM03_compressed.pdf · uploaded 11 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Legacy Form5 2022-23.pdf · uploaded 5 Jul 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 I life.pdf · uploaded 14 Aug 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 I life.pdf · uploaded 14 Aug 2023Source
- 1 Disclosure of sold/ booked inventoryBHUSHAN SIR SET 1_compressed.pdf · uploaded 14 Aug 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 I Life.pdf · uploaded 14 Aug 2023Source
- 12 Copy of Layout Approval (in case of layout)PLAN -01-06_compressed.pdf · uploaded 8 Sep 2023Source
- 13 Copy of Layout Approval (in case of layout)PLAN-02-06_compressed.pdf · uploaded 8 Sep 2023Source
- 14 Copy of Layout Approval (in case of layout)PLAN-03-06_compressed.pdf · uploaded 8 Sep 2023Source
- 15 Copy of Layout Approval (in case of layout)PLAN-04-06_compressed.pdf · uploaded 8 Sep 2023Source
- 16 Copy of Layout Approval (in case of layout)PLAN-05-06_compressed.pdf · uploaded 8 Sep 2023Source
- 17 Copy of Layout Approval (in case of layout)PLAN-06-06_compressed.pdf · uploaded 8 Sep 2023Source
- 3 Commencement Certificates / NA Order for plotted developmentCC-1252-23.pdf · uploaded 8 Sep 2023Source
- 2 Declaration about Commencement CertificateDeclaration About CC iLife UN.pdf · uploaded 8 Sep 2023Source
- 1 Proforma of Agreement for saleResidential Unit- Agreement for Sale - iLife Upper NIBM - Original_compressed-1.pdf · uploaded 16 Sep 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1-1.pdf · uploaded 11 Oct 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2-2.pdf · uploaded 11 Oct 2023Source
- 2 Disclosure of sold/ booked inventoryDisclosure of Sold or Booking Inventory.pdf · uploaded 11 Oct 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Jay Aeram.pdf · uploaded 15 Feb 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Document_2024-01-10_113329.pdf · uploaded 15 Feb 2024Source
- 3 Disclosure of sold/ booked inventoryRera Sheet_compressed.pdf · uploaded 15 Feb 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Legacy Fortune Form 3.pdf · uploaded 15 Feb 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Ilife.pdf · uploaded 16 Apr 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Ilife.pdf · uploaded 16 Apr 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2 A.pdf · uploaded 16 Apr 2024Source
- 4 Disclosure of sold/ booked inventorySold Unsold Ilife.pdf · uploaded 16 Apr 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Ilfe.pdf · uploaded 16 Apr 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 July.pdf · uploaded 19 Jul 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 30th June.pdf · uploaded 19 Jul 2024Source
- 5 Disclosure of sold/ booked inventoryDSU LFA24 30 June.pdf · uploaded 19 Jul 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 July.pdf · uploaded 19 Jul 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)F1 Jan 25-1.pdf · uploaded 23 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)F2 jan 25-1.pdf · uploaded 23 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryIlife Sold Unsold.pdf · uploaded 23 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)20250125143302.pdf · uploaded 3 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)LFA Q4 FORM 1 - 24-25.pdf · uploaded 28 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)LFA Q4 FORM 3 - 24-25_compressed.pdf · uploaded 28 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)LFA Q4 FORM 2 - 24-25.pdf · uploaded 28 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD UNSOLD INVENTORY Q 4- 24-25_compressed.pdf · uploaded 28 Apr 2025Source
- Occupational CertificatePMC PART COMPLETION -24 UNDRI_240311_185420.pdf · uploaded 9 Jul 2025Source
- Occupational CertificatePMC PART COMPLETION -24 UNDRI_240311_185420.pdf · uploaded 9 Jul 2025Source
- Occupational CertificateiLife UpperNIBM OC.pdf · uploaded 30 Sep 2025Source
- Occupational CertificateAdobe Scan Oct 29, 2025.pdf · uploaded 30 Oct 2025Source
Technical
- DocumentNA_compressed.pdf · uploaded 16 May 2022Source
- Document1647343915560_SP01 CC304821 dt31122021.pdf · uploaded 16 May 2022Source
- DocumentSP02 CC304821 dt31122021.pdf · uploaded 16 May 2022Source
- DocumentSP03 CC304821 dt31122021.pdf · uploaded 16 May 2022Source
- DocumentSP04 CC304821 dt31122021.pdf · uploaded 16 May 2022Source
- DocumentSP05 CC304821 dt31122021.pdf · uploaded 16 May 2022Source
- DocumentSP06 CC304821 dt31122021.pdf · uploaded 16 May 2022Source
- DocumentPLAN-01-05_compressed.pdf · uploaded 6 Aug 2022Source
- DocumentPLAN-02-05_compressed.pdf · uploaded 6 Aug 2022Source
- DocumentPLAN-03-05_compressed.pdf · uploaded 6 Aug 2022Source
- DocumentPLAN-04-05_compressed.pdf · uploaded 6 Aug 2022Source
- DocumentPLAN-05-05_compressed.pdf · uploaded 6 Aug 2022Source
- DocumentPLAN -01-06_compressed.pdf · uploaded 8 Sep 2023Source
- DocumentPLAN-02-06_compressed.pdf · uploaded 8 Sep 2023Source
- DocumentPLAN-03-06_compressed.pdf · uploaded 8 Sep 2023Source
- DocumentPLAN-04-06_compressed.pdf · uploaded 8 Sep 2023Source
- DocumentPLAN-05-06_compressed.pdf · uploaded 8 Sep 2023Source
- DocumentPLAN-06-06_compressed.pdf · uploaded 8 Sep 2023Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsSurvey No. 24/1/1
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- Shop, 2BHK, 3BHK125 units in all
- Address
- Survey No. 24/1/1, NIBM Undri Road, UndriPIN 411060
- Village
- Undri, Haveli taluka
- Location
- 18.45452, 73.91886
- Designated bank account
- 76
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Boundaries
- North
- By Land out of Survey No 24
- South
- By Land out of Survey No 24
- East
- By Land out of Survey No 24
- West
- Mohammadwadi Undri Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking125 units
117 of 125 units booked (94%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Commercial Building | Shop | 43.61 sq m · 469 sq ft | 1 | 1 |
| Commercial Building | Shop | 55.26 sq m · 595 sq ft | 1 | 0 |
| Commercial Building | Shop | 56.99 sq m · 613 sq ft | 1 | 1 |
| Commercial Building | Shop | 61.56 sq m · 663 sq ft | 1 | 0 |
| Commercial Building | Shop | 62.07 sq m · 668 sq ft | 1 | 1 |
| Commercial Building | Shop | 64.93 sq m · 699 sq ft | 2 | 1 |
| Commercial Building | Shop | 68.62 sq m · 739 sq ft | 1 | 1 |
| Commercial Building | Shop | 69.27 sq m · 746 sq ft | 1 | 1 |
Show all 21 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Residential Building | 2BHK | 66.38 sq m · 715 sq ft | 12 | 11 |
| Residential Building | 2BHK | 68.02 sq m · 732 sq ft | 38 | 37 |
| Residential Building | 2BHK | 70.33 sq m · 757 sq ft | 2 | 1 |
| Residential Building | 2BHK | 74.96 sq m · 807 sq ft | 7 | 7 |
| Residential Building | 2BHK | 76.84 sq m · 827 sq ft | 1 | 1 |
| Residential Building | 2BHK | 77.27 sq m · 832 sq ft | 7 | 7 |
| Residential Building | 2BHK | 78.83 sq m · 849 sq ft | 1 | 1 |
| Residential Building | 2BHK | 80.13 sq m · 863 sq ft | 12 | 12 |
| Residential Building | 2BHK | 81 sq m · 872 sq ft | 11 | 11 |
| Residential Building | 3BHK | 90.57 sq m · 975 sq ft | 1 | 0 |
| Residential Building | 3BHK | 95.25 sq m · 1,025 sq ft | 12 | 11 |
| Residential Building | 3BHK | 95.79 sq m · 1,031 sq ft | 11 | 11 |
| Residential Building | 3BHK | 102.37 sq m · 1,102 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Jay Aeram and Associates | — |
| Chartered accountant | Satish Aghav and Associates | — |
| Chartered accountant | Satish M Aghav | — |
| Engineer | Sagar Shinde | — |
Source: MahaRERA project page. Contact details are not shown.