Aaradhya Heights
Completion was pushed back 4 months, to Jul 2028; no MahaRERA orders on record.
Undri, Pune 416060 · Property rates in Undri · Promoter: Balaji Associates
Completion was pushed back 4 months, to Jul 2028
- This projectRegistered 21 Jan 2026, completion promised 31 Mar 2028, revised to 31 Jul 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPR1260002502146
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PR1260002502146 | 21 Jan 2026 | 31 Mar 2028 | 31 Jul 2028 | Balaji Associates | Project page |
Documents23
1 document held by Deedo, 22 filings listed on MahaRERA's project page
Finance
Legal
- Declaration Form BDEVELOPMENT AGREEMENT.pdf · uploaded 25 Oct 2025Source
- Declaration Form BPOWER OF ATTORNEY.pdf · uploaded 25 Oct 2025Source
- Declaration Form BUndri Plot Saledeed.pdf · uploaded 26 Oct 2025Source
- Declaration Form BDeclaration regarding Legal Documents.pdf · uploaded 28 Oct 2025Source
- Declaration Form BForm B.pdf · uploaded 28 Oct 2025Source
Show all 23 documentsShow fewer documents
Legal
- OthersPARTNERSHIP DEED.pdf · uploaded 10 Nov 2025Source
- OthersDisclosure Autade.pdf · uploaded 10 Nov 2025Source
- OthersDisclosure Hande.pdf · uploaded 10 Nov 2025Source
- OthersDisclosure Kadam.pdf · uploaded 10 Nov 2025Source
- Declaration Form BCombined Search Report.pdf · uploaded 13 Nov 2025Source
- Declaration Form Bsaat bara.pdf · uploaded 13 Nov 2025Source
Migrated
Technical
Technical (Architect)
- DocumentForm No 1.pdf · uploaded 24 Apr 2026Source
Technical (Engineer)
- DocumentForm 2.pdf · uploaded 28 Apr 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsSR. No. 40 Hissa No.1/6(P)
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —15 units in all
- Address
- Undri, UndriPIN 416060
- Village
- Undri, Haveli taluka
- Location
- 18.49448, 73.93255
- Designated bank account
- 220
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Sr No 40
- South
- Internal Road
- East
- Plot No 12
- West
- Property Of Balaji Associates
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking15 units
15 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 15 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Milind Nagnath Panchal | — |
| Engineer | Rushikesh Bhalchandra Raut | — |
| Engineer | Tejas Bhanudas Kothimbire | — |
Source: MahaRERA project page. Contact details are not shown.