12th Avenue
Deedo IDDP-PUN-C3JSCompletion was pushed back 3 years and 9 months, to Dec 2028; no MahaRERA orders on record; 61% of its units are booked.
Tathwade, Pune 411033 · Property rates in Tathwade · by Prosper Homes
Buying a flat here?
See every deed registered on it.
Completion was pushed back 3 years and 9 months, to Dec 2028
- This projectRegistered 22 Feb 2022, completion promised 31 Mar 2025, revised to 31 Dec 2028.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
- 12th Avenue - A Wing13 floors · 61 units0% booked
- 12th Avenue - B Wing12 floors · 96 units100% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100033536
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100033536 | 22 Feb 2022 | 31 Mar 2025 | 31 Dec 2028 | Prosper Homes | Project page |
Documents169
2 documents held by Deedo, 167 filings listed on MahaRERA's project page
Finance
- PAN CardPropser Home Pan Card.pdf · uploaded 4 Feb 2022Source
Legal
Show all 169 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted development12th avenue commencement certificate_compressed.pdf · uploaded 4 Feb 2022Source
- 1 Declaration about Commencement Certificatecircular 32.pdf · uploaded 4 Feb 2022Source
- 1 Declaration in FORM Bform B.pdf · uploaded 4 Feb 2022Source
- 1 Proforma of Allotment letterallotment letter.pdf · uploaded 4 Feb 2022Source
- 2 Proforma of Allotment letterRERA_Flat_Agreement_12th_Avenue (1).pdf · uploaded 4 Feb 2022Source
- 1 Copy of the legal title reporttitle report.pdf · uploaded 7 Feb 2022Source
- 1 Copy of Layout Approval (in case of layout)layout 1-7.pdf · uploaded 7 Feb 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentplan 2-7.pdf · uploaded 7 Feb 2022Source
- 2 Building Plan Approval / NA Order for plotted developmentplan 2-7.pdf · uploaded 7 Feb 2022Source
- 3 Building Plan Approval / NA Order for plotted developmentplan 3-7.pdf · uploaded 7 Feb 2022Source
- 4 Building Plan Approval / NA Order for plotted developmentplan 4-7.pdf · uploaded 7 Feb 2022Source
- 5 Building Plan Approval / NA Order for plotted developmentplan 5-7.pdf · uploaded 7 Feb 2022Source
- 6 Building Plan Approval / NA Order for plotted developmentplan 6-7.pdf · uploaded 7 Feb 2022Source
- 7 Building Plan Approval / NA Order for plotted developmentplan 7-7.pdf · uploaded 7 Feb 2022Source
- 1 CERSAI detailsCERSAI_Search_Report_200229678708_For_Asset_Based_Search_07_02_2022_13_29_58_983.pdf · uploaded 7 Feb 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 prosper homes_Sigend.pdf · uploaded 8 Feb 2022Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed Form 3.pdf · uploaded 20 Feb 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)prosper homes fy 21-22.pdf · uploaded 20 Feb 2023Source
- 8 Building Plan Approval / NA Order for plotted developmentMYSCAN_20230317_0001.PDF · uploaded 26 Jun 2023Source
- 9 Building Plan Approval / NA Order for plotted developmentMYSCAN_20230317_0002.PDF · uploaded 26 Jun 2023Source
- 10 Building Plan Approval / NA Order for plotted developmentMYSCAN_20230317_0003.PDF · uploaded 26 Jun 2023Source
- 11 Building Plan Approval / NA Order for plotted developmentMYSCAN_20230317_0004.PDF · uploaded 26 Jun 2023Source
- 12 Building Plan Approval / NA Order for plotted developmentMYSCAN_20230317_0005.PDF · uploaded 26 Jun 2023Source
- 2 Commencement Certificates / NA Order for plotted development20230317023114.pdf · uploaded 26 Jun 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 26 Jun 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 26 Jun 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 26 Jun 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1 432023.pdf · uploaded 30 Dec 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)300623_compressed.pdf · uploaded 30 Dec 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)300923_compressed.pdf · uploaded 30 Dec 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)31322_compressed.pdf · uploaded 30 Dec 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)30622_compressed.pdf · uploaded 30 Dec 2023Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)30922_compressed.pdf · uploaded 30 Dec 2023Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)31122022_compressed.pdf · uploaded 30 Dec 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)form 2a_compressed.pdf · uploaded 30 Dec 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)fy 22-23 form 2 a_compressed.pdf · uploaded 30 Dec 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 31322.pdf · uploaded 30 Dec 2023Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)30062022_compressed.pdf · uploaded 30 Dec 2023Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)30092022_compressed.pdf · uploaded 30 Dec 2023Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 q1_compressed.pdf · uploaded 30 Dec 2023Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)form3 q2_compressed.pdf · uploaded 30 Dec 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)31032022 (2)_compressed (1).pdf · uploaded 2 Jan 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)3062022 (1)_compressed.pdf · uploaded 2 Jan 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)3092022 (2)_compressed.pdf · uploaded 2 Jan 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)22-23.pdf · uploaded 8 Jan 2024Source
- 1 Disclosure of sold/ booked inventory31323_compressed.pdf · uploaded 10 Jan 2024Source
- 2 Disclosure of sold/ booked inventory30062023_compressed.pdf · uploaded 10 Jan 2024Source
- 3 Disclosure of sold/ booked inventory30923_compressed.pdf · uploaded 10 Jan 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)31122023.pdf · uploaded 19 Jan 2024Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)PROSPER HOMES FORM 2 ENG CERT.pdf · uploaded 19 Jan 2024Source
- 4 Disclosure of sold/ booked inventoryprosper homes 311223.pdf · uploaded 19 Jan 2024Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)311223 (1)_compressed.pdf · uploaded 9 Feb 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 01 prosper homes.pdf · uploaded 13 Jun 2024Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)prosper homes form 02 dtd 31324.pdf · uploaded 13 Jun 2024Source
- 5 Disclosure of sold/ booked inventoryprosper homes stock.pdf · uploaded 13 Jun 2024Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Prosper homes form 03 dtd 31324.pdf · uploaded 13 Jun 2024Source
- 2 Copy of Layout Approval (in case of layout)scan0453.pdf · uploaded 9 Jul 2024Source
- 13 Building Plan Approval / NA Order for plotted developmentscan0454.pdf · uploaded 9 Jul 2024Source
- 14 Building Plan Approval / NA Order for plotted developmentscan0455.pdf · uploaded 9 Jul 2024Source
- 15 Building Plan Approval / NA Order for plotted developmentscan0456.pdf · uploaded 9 Jul 2024Source
- 16 Building Plan Approval / NA Order for plotted developmentscan0457.pdf · uploaded 9 Jul 2024Source
- 17 Building Plan Approval / NA Order for plotted developmentscan0458.pdf · uploaded 9 Jul 2024Source
- 18 Building Plan Approval / NA Order for plotted developmentscan0459.pdf · uploaded 9 Jul 2024Source
- 19 Building Plan Approval / NA Order for plotted developmentscan0460.pdf · uploaded 9 Jul 2024Source
- 20 Building Plan Approval / NA Order for plotted developmentscan0461.pdf · uploaded 9 Jul 2024Source
- 21 Building Plan Approval / NA Order for plotted developmentscan0462.pdf · uploaded 9 Jul 2024Source
- 22 Building Plan Approval / NA Order for plotted developmentscan0463.pdf · uploaded 9 Jul 2024Source
- 23 Building Plan Approval / NA Order for plotted developmentscan0464.pdf · uploaded 9 Jul 2024Source
- 24 Building Plan Approval / NA Order for plotted developmentscan0465.pdf · uploaded 9 Jul 2024Source
- 25 Building Plan Approval / NA Order for plotted developmentscan0466.pdf · uploaded 9 Jul 2024Source
- 26 Building Plan Approval / NA Order for plotted developmentscan0467.pdf · uploaded 9 Jul 2024Source
- 27 Building Plan Approval / NA Order for plotted developmentscan0468.pdf · uploaded 9 Jul 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)prosper home form 01 300624.pdf · uploaded 18 Jul 2024Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 02 12 av.pdf · uploaded 18 Jul 2024Source
- 6 Disclosure of sold/ booked inventory12 th avenue stcok 300624.pdf · uploaded 18 Jul 2024Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)3062024.pdf · uploaded 19 Jul 2024Source
- 2 Declaration about Commencement Certificate4 Declaration about Commencement Certificate00_page-0001.pdf · uploaded 22 Jul 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA.pdf · uploaded 25 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGG.pdf · uploaded 25 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARC.pdf · uploaded 26 Oct 2024Source
- 2 Disclosure of sold/ booked inventorySOLD UNSOLD.pdf · uploaded 26 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARC.pdf · uploaded 9 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA.pdf · uploaded 9 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGG.pdf · uploaded 9 Jan 2025Source
- 1 Disclosure of sold/ booked inventorySOLD UNSOLD.pdf · uploaded 9 Jan 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A.pdf · uploaded 10 Jan 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5.pdf · uploaded 10 Jan 2025Source
- 1 a Details of encumbrances concerned to Financeencumbrances of concern to legal.pdf · uploaded 28 Feb 2025Source
- 2 a Details of encumbrances concerned to FinanceFINANCIAL ENCU.pdf · uploaded 28 Feb 2025Source
- 1 Declaration in FORM BFORM B 2.pdf · uploaded 28 Feb 2025Source
- 1 CERSAI detailscresai.pdf · uploaded 28 Feb 2025Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)formate a.pdf · uploaded 28 Feb 2025Source
- 1 Deviation Report with respect to Allotment letterALLOTMENT LETER.pdf · uploaded 28 Feb 2025Source
- 1 b Details of encumbrances concerned to Legalencumbrances of concern to legal.pdf · uploaded 28 Feb 2025Source
- 2 b Details of encumbrances concerned to LegalFINANCIAL ENCU.pdf · uploaded 28 Feb 2025Source
- 1 Other – TechnicalANNEXURE A.pdf · uploaded 28 Feb 2025Source
- 1 Deviation Report with respect to model copy of AgreementDEVIGATION AGGREMENT.pdf · uploaded 28 Feb 2025Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsREAL ESTATE ORGANATION.pdf · uploaded 28 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCHITECT.pdf · uploaded 19 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3CA.pdf · uploaded 19 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ENGENEER.pdf · uploaded 19 Apr 2025Source
- 1 Disclosure of sold/ booked inventorySOLD UNSOLD.pdf · uploaded 19 Apr 2025Source
- Form 1f1.pdf · uploaded 16 Jul 2025Source
- Form 2f2.pdf · uploaded 16 Jul 2025Source
- Form 3f3.pdf · uploaded 16 Jul 2025Source
- Disclosure of Sold and Booked Inventorys.pdf · uploaded 16 Jul 2025Source
- Form 5 (FY 2024-2025)12 th Avenue form 5.pdf · uploaded 8 Oct 2025Source
- Form 1f1.pdf · uploaded 17 Oct 2025Source
- Form 2f2.pdf · uploaded 17 Oct 2025Source
- Form 3f3.pdf · uploaded 17 Oct 2025Source
- Disclosure of Sold and Booked Inventorys.pdf · uploaded 17 Oct 2025Source
- Form 1form 1.pdf · uploaded 19 Jan 2026Source
- Form 2form 2.pdf · uploaded 19 Jan 2026Source
- Form 3from 3_compressed.pdf · uploaded 19 Jan 2026Source
- Disclosure of Sold and Booked Inventorysold unsold.pdf · uploaded 19 Jan 2026Source
- Form 1form 01.pdf · uploaded 18 Apr 2026Source
- Form 2form 02.pdf · uploaded 18 Apr 2026Source
- Form 3form 03_compressed.pdf · uploaded 18 Apr 2026Source
- Disclosure of Sold and Booked Inventorystock.pdf · uploaded 18 Apr 2026Source
- Withdrawal Update Form 1form 01 prosper homes.pdf · uploaded 17 Jul 2026Source
- Withdrawal Update Form 2form 02 prosper homes.pdf · uploaded 17 Jul 2026Source
- Withdrawal Update Form 3form 03 prosper omes.pdf · uploaded 17 Jul 2026Source
- Form 5 (FY 2025-2026)prosper (1).pdf · uploaded 1 Oct 2026Source
Technical
- Documentlayout 1-7.pdf · uploaded 7 Feb 2022Source
- Documentplan 2-7.pdf · uploaded 7 Feb 2022Source
- Documentplan 2-7.pdf · uploaded 7 Feb 2022Source
- Documentplan 3-7.pdf · uploaded 7 Feb 2022Source
- Documentplan 4-7.pdf · uploaded 7 Feb 2022Source
- Documentplan 5-7.pdf · uploaded 7 Feb 2022Source
- Documentplan 6-7.pdf · uploaded 7 Feb 2022Source
- Documentplan 7-7.pdf · uploaded 7 Feb 2022Source
- DocumentMYSCAN_20230317_0001.PDF · uploaded 26 Jun 2023Source
- DocumentMYSCAN_20230317_0002.PDF · uploaded 26 Jun 2023Source
- DocumentMYSCAN_20230317_0003.PDF · uploaded 26 Jun 2023Source
- DocumentMYSCAN_20230317_0004.PDF · uploaded 26 Jun 2023Source
- DocumentMYSCAN_20230317_0005.PDF · uploaded 26 Jun 2023Source
- Documentscan0453.pdf · uploaded 9 Jul 2024Source
- Documentscan0454.pdf · uploaded 9 Jul 2024Source
- Documentscan0455.pdf · uploaded 9 Jul 2024Source
- Documentscan0456.pdf · uploaded 9 Jul 2024Source
- Documentscan0457.pdf · uploaded 9 Jul 2024Source
- Documentscan0458.pdf · uploaded 9 Jul 2024Source
- Documentscan0459.pdf · uploaded 9 Jul 2024Source
- Documentscan0460.pdf · uploaded 9 Jul 2024Source
- Documentscan0461.pdf · uploaded 9 Jul 2024Source
- Documentscan0462.pdf · uploaded 9 Jul 2024Source
- Documentscan0463.pdf · uploaded 9 Jul 2024Source
- Documentscan0464.pdf · uploaded 9 Jul 2024Source
- Documentscan0465.pdf · uploaded 9 Jul 2024Source
- Documentscan0466.pdf · uploaded 9 Jul 2024Source
- Documentscan0467.pdf · uploaded 9 Jul 2024Source
- Documentscan0468.pdf · uploaded 9 Jul 2024Source
- Other – TechnicalANNEXURE A.pdf · uploaded 28 Feb 2025Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 12 P, 13 P
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, 3BHK, 1BHK157 units in all
- Address
- 12 P AND 13 P, Mulshi, TathwadePIN 411033
- Village
- Tathwade, Mulshi taluka
- Land area for this project
- 2,820 sq m (30,354 sq ft)
- Permissible built-up area
- 15,254 sq m (1,64,197 sq ft)
- Sanctioned built-up area
- 15,254 sq m (1,64,197 sq ft)
- Designated bank account
- 43
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
12 P AND 13 P
Boundaries
- North
- BY S NO 13 Part
- South
- BY Road
- East
- By S No 17
- West
- BY S NO 12 part and 13 Part
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking157 units
96 of 157 units booked (61%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| 12th Avenue - A Wing | 2BHK | 54.3 sq m · 584 sq ft | 11 | 0 |
| 12th Avenue - A Wing | 2BHK | 69.43 sq m · 747 sq ft | 23 | 0 |
| 12th Avenue - A Wing | 3BHK | 88.87 sq m · 957 sq ft | 13 | 0 |
| 12th Avenue - A Wing | 3BHK | 92.07 sq m · 991 sq ft | 14 | 0 |
| 12th Avenue - B Wing | 1BHK | 48.24 sq m · 519 sq ft | 2 | 2 |
| 12th Avenue - B Wing | 2BHK | 65.52 sq m · 705 sq ft | 45 | 45 |
| 12th Avenue - B Wing | 2BHK | 68.23 sq m · 734 sq ft | 2 | 2 |
| 12th Avenue - B Wing | 2BHK | 69.37 sq m · 747 sq ft | 47 | 47 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Sachin Sutar | — |
| Chartered accountant | Agh And Associates | — |
| Engineer | Atul Gavhane | — |
Source: MahaRERA project page. Contact details are not shown.