RERA projects in Supe Kh.
1 project under 1 MahaRERA registration, registered 2018–2018. 100% have a completion date extended beyond the one promised.
Locality
1RERA projects
1Registrations
1Completion still due0 past their completion date
24 monthsMedian extension beyond promised date100% of registrations extended
1Regulatory caseson 1 project
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2018 | 1 |
Projects in Supe Kh.
1 project registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Nivaan NirvanaVishal Ashok Chugera | P52100017866 | 24 Sep 2018 | 30 Dec 2024 | 31 Dec 2026 | Extended 24 mo | 1 |
Other localities in Purandhar
Most active promoters
By projects registered here, as named on MahaRERA.
- Vishal Ashok Chugera1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology