Completion was pushed back 4 months, to Jul 2029; no MahaRERA orders on record.
Ravet, Pune 411035 · Property rates in Ravet · Promoter: Kesar Life LLP
Completion was pushed back 4 months, to Jul 2029
- This projectRegistered 7 May 2026, completion promised 31 Mar 2029, revised to 31 Jul 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPR1260002600373
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PR1260002600373 | 7 May 2026 | 31 Mar 2029 | 31 Jul 2029 | Kesar Life LLP | Project page |
Documents22
1 document held by Deedo, 21 filings listed on MahaRERA's project page
Finance
Show all 22 documentsShow fewer documents
Legal
- Declaration Form BFinal Title Report.pdf · uploaded 27 Apr 2026Source
Migrated
Technical
- DocumentApproved Layout.pdf · uploaded 23 Apr 2026Source
- OthersPast Experience Declaration.pdf · uploaded 23 Apr 2026Source
- DocumentBuilding Plan Page No 3.pdf · uploaded 28 Apr 2026Source
- DocumentBuilding Plan Page No 4.pdf · uploaded 28 Apr 2026Source
- DocumentBuilding Plan Page No 5.pdf · uploaded 28 Apr 2026Source
- DocumentBuilding Plan Page No 6.pdf · uploaded 28 Apr 2026Source
- DocumentAnnexure A - Order No 50.pdf · uploaded 29 Apr 2026Source
- DocumentBuilding Plan Page No 2.pdf · uploaded 29 Apr 2026Source
Technical (Architect)
- DocumentForm 1 June26 Sky One.pdf · uploaded 1 Aug 2026Source
Technical (Engineer)
- DocumentForm 2 Sky one June 2026.pdf · uploaded 1 Aug 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsSurvey No. 78 (P)
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —29 units in all
- Address
- Ravet Central Station Road, RavetPIN 411035
- Village
- Ravet, Haveli taluka
- Location
- 18.65444, 73.74047
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- By remaining area in Survey No. 78 (Part)
- South
- By D.P Road
- East
- Survey No. 93 (Part)
- West
- By internal road within the same Survey No. 78 (Part)
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking29 units
29 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 29 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals1
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Engineer | Ajay Vilas Bhilare | — |
Source: MahaRERA project page. Contact details are not shown.