Skip to content
Residential / Group Housing · 1 building · 10 unitsRERA PR1260002502645

Parmar Supreme

Deedo IDDP-PUN-TJR1

Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 30% of its units are booked.

Ravet, Pune 412101 · Property rates in Ravet · by Parmar Developers

DeliveryExtended 4 moPromised Dec 2028 · now due Apr 2029RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales30% booked3 of 10 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2029

  • This projectRegistered 9 Mar 2026, completion promised 31 Dec 2028, revised to 30 Apr 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPR1260002502645
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PR12600025026459 Mar 202631 Dec 202830 Apr 2029Parmar DevelopersProject page
Documents34

1 document held by Deedo, 33 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardParmar Developers Pan Card.pdf · uploaded 17 Jan 2026Source
  • OthersCa letter.pdf · uploaded 26 Jan 2026Source
  • GSTIN DocumentParmar Developers GST Certificate.pdf · uploaded 3 Mar 2026Source

Legal

  • OthersLegal Encumbarance.pdf · uploaded 17 Jan 2026Source
  • Declaration Form B1-10.pdf · uploaded 17 Jan 2026Source
  • Declaration Form B11-20.pdf · uploaded 17 Jan 2026Source
  • Declaration Form B21-25.pdf · uploaded 17 Jan 2026Source
Show all 34 documentsShow fewer documents

Legal

  • OthersANNEXURE A - DECLARATION.pdf · uploaded 26 Jan 2026Source
  • Othersno past experiance_page-0001.pdf · uploaded 24 Feb 2026Source
  • OthersPLOT AREA UNDER 500 SQM.pdf · uploaded 24 Feb 2026Source
  • OthersRAMESH PARMAR ANNEXURE A.pdf · uploaded 24 Feb 2026Source
  • OthersTARUN PARMAR ANNEXURE A.pdf · uploaded 24 Feb 2026Source
  • OthersUPDATEDE DECLARATION PLOT AREA UNDER 500 SQM.pdf · uploaded 24 Feb 2026Source
  • OthersANNEXYER A_page-0001-1.pdf · uploaded 24 Feb 2026Source
  • Declaration Form BFORMAT SERCH_page-0001.pdf · uploaded 24 Feb 2026Source
  • Declaration Form Bform b_page-0001-3.pdf · uploaded 24 Feb 2026Source
  • Declaration Form B712.pdf · uploaded 24 Feb 2026Source

Migrated

  • Withdrawal Update Form 1Form 1.pdf · uploaded 29 Apr 2026Source
  • Withdrawal Update Form 2Form - 2.pdf · uploaded 29 Apr 2026Source
  • Withdrawal Update Form 3Form3.pdf · uploaded 29 Apr 2026Source
  • Withdrawal Update Form 102Architect Certificate_Form 1_08Jul2026.pdf · uploaded 10 Jul 2026Source
  • Withdrawal Update Form 202PD_Engg Certificate_Form - 2_05Jul2026.pdf · uploaded 10 Jul 2026Source
  • Withdrawal Update Form 303Parmar Developers_CA Form3_05Jul2026.pdf · uploaded 10 Jul 2026Source
  • Withdrawal Update Form 1form 1.pdf · uploaded 8 Oct 2026Source
  • Withdrawal Update Form 203PD_Engg Certificate_Form - 2_06Oct2026.pdf · uploaded 8 Oct 2026Source
  • Withdrawal Update Form 304Parmar Developers_CA Form3_06Oct2026.pdf · uploaded 8 Oct 2026Source

Technical

  • Documentsanction Plan Copy (1)_compressed.pdf · uploaded 17 Jan 2026Source
  • DocumentANNEXURE A - DECLARATION CUM UNDERTAKING (1).pdf · uploaded 17 Jan 2026Source
  • OthersDECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf · uploaded 17 Jan 2026Source
  • Others1.pdf · uploaded 26 Jan 2026Source
  • Otherscc verification.pdf · uploaded 24 Feb 2026Source

Technical (Architect)

  • Documentform 1.pdf · uploaded 8 Oct 2026Source

Technical (Engineer)

  • Document03PD_Engg Certificate_Form - 2_06Oct2026.pdf · uploaded 8 Oct 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot Number 72, Survey Number 95 (P)

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—10 units in all
Address
Celestial City Road, RavetPIN 412101
Village
Ravet, Haveli taluka
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

Plot Number 72Survey Number 95 (P)

Boundaries

North
S No 95 (P)
South
S No 95 (P)
East
6 M Road
West
S No 95 (P)

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking10 units

10 units registered

— · 10 units
TypeCarpet areaUnits
——10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Chartered accountantAmol Kankariya—
EngineerShashank Tatke—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology