Dolphin Garima
Completion was pushed back 8 months to Aug 2024, and that date has passed too; no MahaRERA orders on record; 53% of its units are booked.
Ravet, Pune 412101 · Property rates in Ravet · Promoter: Dolphin Vastu
Completion was pushed back 8 months to Aug 2024, and that date has passed too
- This projectRegistered 13 Sep 2021, completion promised 31 Dec 2023, revised to 14 Aug 2024, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100030737
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100030737 | 13 Sep 2021 | 31 Dec 2023 | 14 Aug 2024 | Dolphin Vastu | Project page |
Documents87
2 documents held by Deedo, 85 filings listed on MahaRERA's project page
Finance
- PAN Cardvastu pan.pdf · uploaded 14 Jun 2021Source
Legal
- Declaration Form BForm B - Promoter.pdf · uploaded 29 Jul 2021Source
- Legal Title reportSearch title.pdf · uploaded 9 Sep 2021Source
- Declaration Form BGarima_Form-B Declaration_Promoter_19-01-24.pdf · uploaded 29 Jan 2024Source
- Declaration Form BGarima_Form-B_ Co-Promoter_19-01-24 1.pdf · uploaded 29 Jan 2024Source
- Declaration Form BForm B_compressed.pdf · uploaded 11 Dec 2024Source
Show all 87 documentsShow fewer documents
Migrated
- 1 PAN Cardvastu pan.pdf · uploaded 14 Jun 2021Source
- 1 Copy of Layout Approval (in case of layout)Sanctioned Plan.pdf · uploaded 9 Jul 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentSanctioned Plan.pdf · uploaded 9 Jul 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 9 Jul 2021Source
- 1 Details of encumbrancesDetails of Encumbrances.pdf · uploaded 29 Jul 2021Source
- 1 Declaration about Commencement CertificateDeclaraion - Commencement.pdf · uploaded 29 Jul 2021Source
- 1 Declaration in FORM BForm B - Promoter.pdf · uploaded 29 Jul 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 29 Jul 2021Source
- 1 Proforma of Allotment letterAllotment Letter to upload.pdf · uploaded 30 Jul 2021Source
- 2 Proforma of Allotment letterDRAFT AGREEMENT to upload.pdf · uploaded 30 Jul 2021Source
- 1 Copy of the legal title reportSearch title.pdf · uploaded 9 Sep 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)DOLPHIN VASTU.pdf · uploaded 3 Feb 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Garima_Form -1_22-01-22.pdf · uploaded 18 Jan 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 18 Jan 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Garima_Form 1_04-07-2022.pdf · uploaded 18 Jan 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Garima_Form-1_13-10-22.pdf · uploaded 18 Jan 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Garima_Form-1_22-01-23.pdf · uploaded 18 Jan 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Garima Form_1_29-04-2023.pdf · uploaded 18 Jan 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Garima Form_1_03-08-2023.pdf · uploaded 18 Jan 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Garima _ Form-1 _ 30-10-2023.pdf · uploaded 18 Jan 2024Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Garima_Form-1_02-01-24.pdf · uploaded 18 Jan 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Garima_Form-2_13-10-22.pdf · uploaded 18 Jan 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 18 Jan 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Garima_Form-2_29-04-2023.pdf · uploaded 18 Jan 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Garima_Form-2_03-08-2023.pdf · uploaded 18 Jan 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Garima_Form-2_30-10-2023.pdf · uploaded 18 Jan 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Garima_Form-2_14-01-24_11zon.pdf · uploaded 18 Jan 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 compressed.pdf · uploaded 18 Jan 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Garima_Form-3_23-01-22_11zon.pdf · uploaded 18 Jan 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Garima_Form-3_20-10-22_11zon.pdf · uploaded 18 Jan 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Garima_Form-3_23-01-23_11zon.pdf · uploaded 18 Jan 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Garima_Form-3_30-04-2023_11zon.pdf · uploaded 18 Jan 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Garima_Form-3_04-08-2023_11zon.pdf · uploaded 18 Jan 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Garima_Form-3_31-10-23_11zon.pdf · uploaded 18 Jan 2024Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Garima_Form-3_15-01-24_11zon.pdf · uploaded 18 Jan 2024Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Garima_ Form-3_02-05-22 upload_11zon.pdf · uploaded 24 Jan 2024Source
- 2 Declaration in FORM BGarima_Form-B Declaration_Promoter_19-01-24.pdf · uploaded 29 Jan 2024Source
- 3 Declaration in FORM BGarima_Form-B_ Co-Promoter_19-01-24 1.pdf · uploaded 29 Jan 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Garima_Form-2A_05-04-22V1.pdf · uploaded 29 Jan 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Garima_Form - 2A_05-04-2023.pdf · uploaded 29 Jan 2024Source
- 1 Disclosure of sold/ booked inventoryGarima_Circular_29_10-10-2021.pdf · uploaded 29 Jan 2024Source
- 2 Disclosure of sold/ booked inventoryGarima_Circular_29_10-01-2022.pdf · uploaded 29 Jan 2024Source
- 3 Disclosure of sold/ booked inventoryGarima_Circular-29_02-05-22.pdf · uploaded 29 Jan 2024Source
- 4 Disclosure of sold/ booked inventoryGarima_ Circular-29_05-07-22.pdf · uploaded 29 Jan 2024Source
- 5 Disclosure of sold/ booked inventoryGarima_Circular -29_20-10-22.pdf · uploaded 29 Jan 2024Source
- 1 CERSAI detailsGarima_Circular-29_20-10-2022V1.pdf · uploaded 29 Jan 2024Source
- 6 Disclosure of sold/ booked inventoryCircular_29_05-07-2022V1.pdf · uploaded 29 Jan 2024Source
- 7 Disclosure of sold/ booked inventoryGarima_Circular-29_20-10-2022V1.pdf · uploaded 29 Jan 2024Source
- 8 Disclosure of sold/ booked inventoryCircular_29_23-01-2023V1.pdf · uploaded 29 Jan 2024Source
- 9 Disclosure of sold/ booked inventoryGarima_Circular-29_30-04-2023V1.pdf · uploaded 29 Jan 2024Source
- 10 Disclosure of sold/ booked inventoryGarima_Circular-29_04-08-2023V1.pdf · uploaded 29 Jan 2024Source
- 11 Disclosure of sold/ booked inventoryGarima_Circular-29_31-10-23V1.pdf · uploaded 29 Jan 2024Source
- 12 Disclosure of sold/ booked inventoryCircular_29_31-12-2023V1.pdf · uploaded 29 Jan 2024Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)Garima_Form 3_31-12-2023 compressed.pdf · uploaded 29 Jan 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Garima_Form 5_compressed.pdf · uploaded 29 Jan 2024Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1- Final.pdf · uploaded 29 Apr 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Garima - Form 2 - Final .pdf · uploaded 29 Apr 2024Source
- 13 Disclosure of sold/ booked inventoryGarima - Sold Circular - Final.pdf · uploaded 29 Apr 2024Source
- 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)Compress Final Form 3.pdf · uploaded 29 Apr 2024Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Final_compressed (1).pdf · uploaded 19 Jul 2024Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Final_compressed.pdf · uploaded 19 Jul 2024Source
- 14 Disclosure of sold/ booked inventoryVastu_Sold Circular.pdf · uploaded 19 Jul 2024Source
- 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Final_compressed.pdf · uploaded 19 Jul 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_compressed.pdf · uploaded 19 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Final_compressed.pdf · uploaded 19 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Final.pdf · uploaded 19 Oct 2024Source
- 1 Disclosure of sold/ booked inventorySold Circular.pdf · uploaded 19 Oct 2024Source
- 1 Architect’s Certificate on Completion of Project (Form 4)form 4 Final.pdf · uploaded 29 Nov 2024Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentGarima_Part Completion_31-07-2024.pdf · uploaded 29 Nov 2024Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentGarima_Full Completion Cetificate_14-08-2024.pdf · uploaded 29 Nov 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A Final.pdf · uploaded 29 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 Uploaded.pdf · uploaded 5 Dec 2024Source
- 1 Declaration in FORM BForm B_compressed.pdf · uploaded 11 Dec 2024Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals75/4/1
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, Shop43 units in all
- Address
- 75/4/1, BRT Road, RAVETPIN 412101
- Village
- Ravet, Haveli taluka
- Location
- 18.66508, 73.74335
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Mr Bansal Property
- South
- Polite Builder Property
- East
- D P Road
- West
- Survey No 75
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking43 units
23 of 43 units booked (53%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 54.13 sq m · 583 sq ft | 13 | 3 |
| 2BHK | 54.19 sq m · 583 sq ft | 1 | 1 |
| 2BHK | 56.27 sq m · 606 sq ft | 12 | 3 |
| 2BHK | 57.86 sq m · 623 sq ft | 14 | 14 |
| Shop | 36.14 sq m · 389 sq ft | 1 | 0 |
| Shop | 44.12 sq m · 475 sq ft | 1 | 1 |
| Shop | 52.72 sq m · 567 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Yogesh Manakshe | — |
| Chartered accountant | Navdeep Jindal | — |
| Engineer | Akash Kasbe | — |
| Other | Jeevan Satpute | — |
| Other | Siddhivinayak Mep Consultants | — |
Source: MahaRERA project page. Contact details are not shown.